SUPREME COURT OF INDIA
R.V. RAVEENDRAN, A.K. PATNAIK, JJ.
Oil and Natural Gas Corporation Ltd. - Petitioner
Versus
Off-Shore Enterprises Inc. - Respondent
Civil Appeal No(s). 4368 of 2005
Decided on : 23-02-2011.
Arbitration Act, 1940 - Cost of Arbitration – Evidence - Challenge by ONGC - Respondent initiated arbitration proceedings in respect of dispute relating to non payment of balance price - An award was made against ONGC in regard to balance price due to respondent - Certain counter claims by ONGC were also allowed - It is stated that challenge by ONGC to said award is pending adjudication in court - During pendency of said arbitration, ONGC sought to raise issue of defective stability of Drill-ship – Held, To explain this conduct on part of Arbitrators learned counsel for appellant submitted that increase was based on a comparative statement that was filed before Arbitrators at final stages of hearing, where three alternatives were given in regard claim of ONGC first option was for a claim for prices discounting the 1995 prices). The second option was for based on 1982 prices third option was a claim with reference to only constant in all three options is towards lay up charges for 180 days. Arbitrators have chosen third option of 1995 cost on basis of claim - It is un-understandable how such alternative claims could be made during arguments with reference to alleged cost of repair/additions/alterations in without actually repairing vessel particularly when ONGC had arrived it as - This again shows that claim was casual imaginary and not based on any facts figures or actual rates - In regard to a drillship supplied in year in which defects were allegedly found in but claim made in a hypothetical claim for cost of repairs cannot be accepted - As award apparently proceeds on a legal principle which is wholly erroneous award cannot be sustained above also demonstrates that Arbitrators have exceeded their jurisdiction and gone beyond reference - Appeal dismissed
ORDER
R.V. Raveendran J.
Under a contract dated 14.7.1981 between appellant and the respondent, the respondent agreed to supply the equipment and engineering drawings and provide the project management and construction supervision to M/s Paul Lindenau GmbH to assist with the design, building, equipping and launching of a drillship known as 'Sagar Prabhat' purchased by the appellant. The appellant had simultaneously entered into an agreement with M/s Paul Nindenau GmbH for purchase of the said drillship. The said drillship equipped and mobilised by the respondent reached Bombay on 5.6.1982. American Bureau of Shipping ("ABS" for short) vide certificate dated 25.6.1982 certified that the machinery of the drillship and the stability of the drillship were in accordance with its rules and standards. On the basis of the said certificate dated 25.6.1982, the appellant took delivery of the Drill-ship on 29.6.1982. The appellant thereafter found some defects in the drill-ship and therefore withheld the payment to the respondent. ABS revised its certificate on 18.6.1985, stating that its earlier certificate dated 25.6.1982 was based on incorrect data supplied by Paul Lindenau GmbH (builder of the drillship) and the respondent (designer, equipment supplier and construction supervisor of the drillship).
2. The respondent initiated arbitration proceedings in respect of the dispute relating to non payment of the balance price. An award was made against ONGC, in regard to the balance price due to the respondent. Certain counter claims by ONGC were also allowed. It is stated that challenge by ONGC to the said award is pending adjudication in court. During the pendency of the said arbitration, ONGC sought to raise the issue of defective stability of the Drill-ship. As that issue was beyond the reference of the ongoing arbitration, it was decided that a separate reference would be made in regard to dispute relating to the stability/defects of the drillship.
3. As the respondent disputed the claim of ONGC that the Drill-ship was defective and the defects affected its stability, it issued a notice dated 1.8.1986 stating that a dispute had arisen in regard to the claim of the appellant about the defects/ deficiencies in the stability of the Drill-ship. The said dispute was referred to arbitration by an Arbitral Tribunal with Shri K.H. Bhabha, Senior Advocate and Vice-Admiral Shri N.P. Datta as members. The said Arbitral Tribunal entered upon the reference on 4.9.1986.
4. ONGC filed its Statement of Claim on 2.12.1987 in regard to its claim relating to defects/deficiencies in regard to the stability of the Drill-ship. Para 27 thereof containing the claim and prayer of the appellant is extracted below:
The Respondent, therefore, pray:
(a) That the claimants be directed
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.