SupremeToday Landscape Ad
Back
Next
Headnote Court Copy Facts Arguments Court observation Judicial Analysis Case Map Category Hierarchy Table of Content
Listen Article Pause Article
judgment-img

2020 Supreme(SC) 828

SUPREME COURT OF INDIA
Rohinton Fali Nariman, S. Ravindra Bhat, V. Ramasubramanian, JJ.
Union Of India & Ors. - Appellants
Versus
Gopaldas Bhagwan Das & Ors. - Respondents
Civil Appeal No. 3636 of 2016
Decided On : 04-02-2020

Important Points

Point of Law: Publication of preliminary notification and powers of officers thereupon - A mandatory condition of a section 4 notification not being adhered to, would amount to there being no acquisition at all in eye of law.

Subject

Land Acquisition - Section 4 Notification

Act Referred

Headnote

Defence of India Rules, 1939 - Rule 75A - Land Acquisition Act, 1894 - Section 4(1), 6, 11, 18 and 30 - Constitution of India, 1950 - Article 141 and 142 - Enforcement of decrees and orders of Supreme Court and unless as to discovery etc - Law declared by Supreme Court to be binding on all courts The law declared by the Supreme Court shall be binding on all courts within the territory of India - Whether delay would apply as a good ground for dismissing a writ petition on ground of laches insofar as challenges to land acquisition proceedings are concerned, and that we should await judgment of Constitution Bench before proceeding with judgment in this case.

Finding of the court:

Requirement of publication in the Official Gazette and public notices of the substance of the notification being given in the locality in which lands are acquired, both of which were held to be cumulative and mandatory requirements of section 4 - Court unable to agree with counsel contention that he Section 4 notification not only deals with various other lands in Village Malad but also deals with a land in a different village altogether viz., Village Wadhawan, and that this Court's judgment did not go to the extent of declaring the acquisition bad so far as village Wadhawan is concerned. So far as village Malad is concerned, where land in Kulsum R. Nadiadwala's case was land that was adjacent to present land, very section 4 notification has been struck down and declared null and void, and this being case, it would not be in interest of justice to allow present appeal in favour of Union of India, as this would amount to a discrimination between two persons who are otherwise similarly placed - It is important to make a distinction between a declaration of law which would bind other future cases under Article 141 of Constitution of India and an order made in facts of case which may equally be made to do substantial justice on facts of a given case, sometimes under Article 142.

Result: Appeal dismissed

Legal Category Hierarchy

  • administrative law
    • land acquisition
      • mandatory procedures (Para 3, 10)
  • constitutional law
    • judicial precedent (Para 8, 14)
    • fundamental rights
      • right to equality (Para 8)
  • practice and procedure
    • writ jurisdiction
      • delay and laches (Para 5, 6, 8, 9)

Advocates appeared:
Rekha Pandey, Advocate, Arvind Kumar Sharma, Advocate, Shyam Diwan, Advocate, Y. Raja Gopala Rao, Advocate, Y. Vismai Rao, Advocate, Bhav Ratan, Advocate

Table of Contents

1. Land acquisition under Section 4 of the Land Acquisition Act, 1894 — Challenge to notification validity based on non-compliance with mandatory publication requirements. (Para 2 )

2. Whether delay and laches bar the challenge — Whether personal notice waives mandatory publication requirements — Whether a prior judgment striking down the same notification is binding. (Para 6 , 7 )

3. Mandatory publication requirements under Section 4 are cumulative; non-compliance renders acquisition null and void, regardless of personal notice or delay when the same notification is concerned. (Para 3 , 8 , 9 , 10 )

4. Publication in the Official Gazette and public notices in the locality under Section 4 of the Land Acquisition Act are cumulative mandatory requirements. (Para 3 , 10 )

5. Appeal dismissed. (Para 16 )

6. Are publication in the Official Gazette and public notices in the locality under Section 4 of the Land Acquisition Act, 1894, both mandatory?

Yes, these are cumulative mandatory conditions. Failure to comply with both requirements renders the entire acquisition proceeding null and void, even if the interested persons have knowledge of the proceedings. (Para 3 , 10 )

7. Does the personal service of notice to landowners waive the requirement for public notices under Section 4 of the Land Acquisition Act?

No. When a statute prescribes a particular manner for performing an act, it must be done in that manner. Personal notice or knowledge of the proceedings does not excuse non-compliance with mandatory statutory publication requirements. (Para 3 , 9 )

8. Does the principle of delay and laches apply when a mandatory statutory condition for land acquisition is not met?

While delay and laches typically bar stale litigation, if a mandatory condition is not met, the acquisition is void. Furthermore, if the same notification was previously struck down, the same result applies to similarly placed persons to avoid discrimination. (Para 3 , 8 )

JUDGMENT

R. F. Nariman, J. - This matter has a somewhat chequered history.

2. In 1943, Government of India requisitioned 4 acres and 34 gunthas of the land owned by one Rajabahadur Bhagwandas Haridas, bearing Survey No. 120/2 (Part) of Village Malad, Mumbai, in exercise of powers conferred under Rule 75A of the DEFENCE OF INDIA RULES , 1939. On 27.07.1949, the Collector, Thane, de-requisitioned 2.68 acres in the Survey No. 120 Part 2 out of the aforesaid 4 acres 34 gunthas. Ultimately, despite the land having first being requisitioned, a notification under Section 4(1) of the Land Acquisition Act, 1894 (hereinafter referred to as 'Act'), was issued on 24.10.1975 acquiring the aforesaid extent of 8623 square meters. A declaration under Section 6 of the Act was issued on 30.11.1978. According to the respondents herein, a Draft Award was passed under Section 11 of the Act on 23.09.1986, against which references were made, both under Section 18 and 30, of the Act. The respondents confirmed that after symbolic possession was taken on 06.01.1987 by the State, such possession has remained with the State till date.

3. In a proceeding that was filed, insofar as other lands in Village Malad were concerned, covered by the same section 4 notification, this Court in Kulsum R. Nadiadwala v. State of Maharashtra and Ors., (2012) 6 SCC 348 , allowed an appeal by the land owner. After stating in paragraph 2 that the very same section 4 notification was issued in order that a Central Ordinance Depot for the Union of India be made for defence purposes, the judgment records that the beneficiary of these lands, being the Central Government, was served, but did not appear at the time of hearing of the appeal. The appellant in Kulsum R. Nadiadwala's case (supra) argued several points before this Court, which were resisted by the learned counsel appearing for the State of Maharashtra, basically on the ground that the writ petition should have been dismissed on the ground of delay and laches as was done by the impugned High Court judgment. After setting out Section 4 of the Act, this Court observed that the requirement that the notification under Section 4 be published in the Official Gazettee and the requirement that the Acquiring Authority should publish public notices of the substances of such notification in a convenient place or places in the locality in which the land proposed to be acquired is situate, are cumulative conditions, both being mandatory. The Court then held: -

"13. In the instant case, the respondents before the High Court had filed their reply affidavit. They did not dispute the contentions of the appellants that they had not issued any public notices as required under Section 4 of the Act. They only reiterated that such notification was published in the Official Gazette. Since the mandatory requirement as required under Section 4(1) of the Act is not complied with by the respondents, while acquiring the lands in question, in our opinion, the entire acquisition proceedings requires to be declared as null and void.

14. This Court in J&K Housing Board v. Kunwar Sanjay Krishan Kaul has observed that all the formalities of serving notice to the interested person, stipulated under Section 4 of the Act, has to be mandatorily complied with in the manner provided therein, even though the interested persons have knowledge of the acquisition proceedings. This Court further observed thus:

"32. It is settled law that when any statutory provision provides a particular manner for doing a particular act, the said thing or act must be done in accordance with the manner prescribed therefor in the Act. Merely because the parties concerned were aware of the acquisition proceedings or served with individual notices does not make the position alter when the statute makes it very clear that all the procedures/modes have to be strictly complied with in the manner provided therein. Merely because the landowners failed to submit their objections within 15

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad