SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1989 Supreme(AP) 213

Andhra Pradesh High Court
Judges : K.RAMASWAMY
State Of A.P.represented by the Superintending Engineer, N.S.C Circle, Ongole - Appellant
Versus
Chelamani Ramalinga Reddy - Respondent
C.R.P.No. 1085/89
Decided On : 04-25-89
Advocates Appeared :
Mr. K. Subrahmanya Reddy

Headnote:ARBITRATION ACT, Sec 8 (1) (b) - One of the named arbitrators by Government becoming incapable to act as arbitrator due to upgradation of his post - Appointment of a retired Engineer as sale arbitrator by Court - Valid

       Held : In this case, the incapacity has arisen due to the upgradation of the post as Joint Secretary and promotion of him as Joint Secretary, and the Deputy Secretary no longer discharges the duties as the Deputy Secretary after his assumption Office as Joint Secretary The parties did not intend to supply the vacancy and that the parties intend to arbitrate their dispute by a panel of the three named arbitrators though by virtue of their Office

       When there is a vacancy in the panel of the three arbitrators, the two arbitrators are incapable of performing the duties and there is no intention to supply the vacancy between the parties Therefore, the Court has power and jurisdiction under Sec 8 (1) (b) to supercede the panel of arbitrators under the Act and appoint sale arbitrator

       CR P Dismissed

K. RAMA SWAMY, J.

( 1 ) THE respondent by an agreement dated July 27, 1982, undertook to execute lining to the bed and side slopes of D. B Canal from M5/6 to M6/0 and M6/0 to 6/2. Ninety percent of the contract was completed by June 30, 1984 and the balance on April 16, 1985. Accordingly, the work was handed over. Despite repeated requests to settle the claims, no action was taken by the petitioners. By letter daced February 19, 1986, he requested to settle the claims within thirty days from the date of receipt of that letter. But however, oo July 25, 1986, the petitioners have rejected the claim. Thus arose the dispute between the respondent and the petitioners. As a result, the respondent invoked Arbitration Clause 73. Thereunder, a Panel of three arbitrators, viz. , the Chief Engineer, Srisailam Project; Deputy secretary, Finance, Government of Andhra Pradesh and the Director of Accounts, Pochampad Projects are the designated arbitrators. The government, in G. O. Rt. No. 5, Finance and Planning dt. January 2, 1988, upgraded the post of the Deputy Secretary, Finance to the post of Joint secretary and he was kept in-charge of the subjects hitherto being dealt with. The Chief Engineer, Srisailam Project, in his letter dated February 24, 1988 requested the respondent to enter into a supplemental agreement agreeing for arbitration by the Joint Secretary, Finance and Planning as well. The respondent has stated that as there is no post of Deputy Secretary of Finance which is one of the designated arbitrators and the Joint Secretary is not the Deputy Secretary, thereby, the Deputy Secretary of Finance is incapable of acting as an arbitrator and as a consequence, a vacancy in the panel of arbitrators has arisen. As tbe contract provides for arbitration by the named three arbitrators and the second arbitrator viz , the Deputy Secretary is incapable of performing the duties as an arbitrator, he requested by his notice dated April 18, 1988 under Section 8 of the Indian Arbitration Act (Act 10 of 1940), for short, "the Act , to refer the dispute within fifteen days from the date of receipt of the notice to any of the named four retired Chief engineers from the service of the first petitioner and reiterated in his notice dated April 20, and April 21,1988 respectively. Since it revoked no response, he invoked the jurisdiction of the Court below under Sections 8, 1 1 and 12 of the Act for appointment of a retired Chief Engineer as a sole arbitrator and intimated to the petitioners. This was resisted by the petitioners. It is contended that the Joint Secretary, Finance, is looking after the same subject viz , arbitration also, therefore, he is one of the designated arbitrators under the contract; a supplemental agreement was asked to be entered into; the respondent did not agree for the same; therefore, the petitioners are prepared to arbitrate through the remaining two arbitrators. They are not agreeable for the appointment of a sole arbitratora retired chief Engineer. Tbe Court below, after giving reasonable opportunity to both patties and after considering the documentary evidence and the contentions advanced, appointed one Sri A. P. Ranganatha Swamy, a retired Chief engineer as sole arbitrator and directed him to give award withia four months from the date of his entering in the reference. Assailing the legality thereof, the revision petitoin has been filed. At the stage of admission, the respondent has taken notice and Sri Subrahmanya Reddy, Advocate has entered his appearance on behalf of the respondent. Both sides addressed the arguments on merits.

( 2 ) SRI Suryaprakasa. Rao, learned Government Pleader has contendedthat the Post of Deputy Secretary, Finance and Planning was upgraded to the post of Joint Secretary, Finance with the same duties; in the contract he is one of the designated arbitrators; therefore, the Court below is devoid of power under Section 8 to displace the agreed arbitrators and appoint sole arbitrator. Alternat






















Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

SupremeToday

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top