SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2006 Supreme(AP) 983

2006 (6) ALT 37
IN THE HIGH COURT OF JUDICATURE, ANDHRA PRADESH AT HYDERABAD
GODA RAGHURAM, J.
A.R.K. Murthy - Applicant.
v.
Senior Divisional Engineer, South, S.C. Railway,
Secunderabad and others - Respondents.
Arbitration Application No.14 of 1997
Decided on 31-8-2006.
Advocates Appeared
Mr. K.V.N Bhupal, Advocate for the Applicant (not present).
Mr. T. Ramakrishna Rao, S.C. for South Central Railways for the Respondents.

Headnote:Arbitration & Conciliation Act, 1996 - Section 11(6) - Arbitration - Basis of - Arbitration, not a process of compulsive adjudication as before civil court of competent jurisdiction - power, authority and jurisdiction of arbitrator to arbitrate upon disputes referred is founded an agreement between parties to agreement contained in arbitration clause

       Held : Existence of an arbitration agreement is the foundation for the jurisdiction to refer to arbitration When an arbitrator has no jurisdiction in the matter and reference of a dispute to an arbitrator was invalid, the entire proceedings before the arbitrator, including the award made by him, were null and void

       In the event of the claims arising within the ambit of excepted matters , the question of assumption of jurisdiction by any arbitrator either with or without the intervention of the court would not arise

       It is not possible to accept the position that no adjudication is involved in the constitution of an Arbitral Tribunal, while exercising jurisdiction under Section 11 (6) of the Act

       the legal principle is established that excepted matters are not to be referred to arbitration On text and authority and the clear text of the provisions of Clause 39 of SGCC, the additional items claimed to have been executed by the petitioner and the disputes in relation to those additional items of work that have arisen between the parties to the agreement, clearly comprise excepted matters and are therefore not liable to be referred to arbitration as arbitral jurisdiction is specifically excluded in respect of excepted matters This is the unambiguous position on a true and fair construction of the provisions of Clauses 39, 63 and 64 of the SGCC which govern the relationship between the parties and define the contours of the jurisdiction, power and authority of an arbitrator

ORDER

This application tiled seeks appointment of an Arbitrator for settlement of the claims and disputes between the parties herein with regard to the amounts claimed as due and payable by the respondents to the petitioner in respect of an agreement No.53/DEN/S/BG/ SC dated 3-10-1990.

2. The petitioner asserts that the 1st respondent issued a tender notice for the work - Warangal-Water Supply Bulk Water Drawal from Warangal Municipality and provision of overhead tank and pipelines. The petitioner was one of the bidders in the tender. His bid was accepted and he was awarded the work. The work could not be completed within the time stipulated and the petitioners request for extension of time was also accorded.

3. During the currency of the work, the petitioner asserts, the capacity of the overhead tank was raised from 20,000 gallons to 33,000 gallons. The petitioner executed this increased quantum of work. The petitioner asserts that the scope of the work was enhanced in excess of the specifications as per the agreed items under the agreement between the parties and as a consequence, the value of the work increased from Rs.4,20,858-25 ps., to Rs.10,61,121-70 ps. The respondents failed to settle and pay in full the amounts due to the petitioner and therefore he preferred writ petition (W.P. No.26369 of 1995) seeking settlement of the final bill. By the judgment dated 1-8-1996, W.P. No.26369 of 1996was disposed of by this Court directing the 1st respondent to pay the admitted amount of Rs.1,00,000-00 to the petitioner for construction of the original specification of the overhead tank, within three weeks from the date of receipt of a copy of the judgment of this Court. This Court further directed the respondents to hold negotiations with the petitioner for payment with regard to the additional works claimed to have been executed by the petitioner viz., the construction of 33,000 gallons capacity overhead tank; and if the negotiations failed, the respondents were directed to pay to the petitioner the amounts admitted by them for both the works and refer the matter to the arbitrator or review committee for resolution of disputes that still remained unresolved and that such arbitration or review shall be completed within eight weeks from the date of reference.

4. As the respondents have, despite the order of this court above, failed to refer the dispute between the parties to the arbitration, despite the petitioner making several representations in this behalf, this arbitration application is filed.

5. It is the defence of the respondents, in particular the 1st respondent that the total work executed by the petitioner (both the original and additional) is of a value of Rs.10,40,164-87 ps., (the value of the original work at Rs.1,29,693-65 ps., and the value of the additional work at Rs.9,10,471-22 ps.,). This was a figure arrived at in a negotiating committee meeting held on 28-10-1996. As against this amount payable to the petitioner, the amount due from the petitioner is Rs.35, 191-53 ps., (some of the details are: the value of the unreturned cement bags at RS.390-00 and the unreturned value of the steel supplied for execution of the work Rs.18,357-00). The petitioner was stated to have been paid Rs.10,56,809-00. Thus, according to the respondents, the petitioner himself is due to the respondents a sum of Rs.35, 191-53 ps.

6. The above is the dispute between the parties on the amounts claimed by the petitioner as due from the respondents and claimed by the respondents as due from the petitioner.

7. On the substantive merit of the petitioners application seeking reference to arbitration, the respondents contend that as the dispute is with regard to the additional work done by the petitioner, the same is not covered by the arbitration clause and falls within the excepted matters and therefore no reference to arbitration could be made and the petitioner cannot invoke the arbitration clause.

8. It is the admitted position between the partie






















Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top