SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2006 Supreme(AP) 1121

Andhra Pradesh High Court
Judges : P.S.NARAYANA
PADALA HARINATHA REDDY - Appellant
Versus
ANDHRA PRADESH STATE ELECTRICITY BOARD REP.BY ITS ASSISTANT Accounts OFFICER, ELECTRICITY REVENUE OFFICE, RAMACHANDRAPURAM EAST Godavari DISTRICT - Respondent
Decided On : 09/26/2006
SECOND APPEAL 265 Of 1996

Advocates Appeared: N.Siva Reddy, SRIRAMULU REDDY

Headnote:

Delay/Laches/Limitation – Limitation Act, 1963 – Articles 113 and 137 – Agreement for Agricultural electricity service Connection – Whether Suit is barred by limitation – Plaintiff pleaded that plaintiff is an agriculturist owning lands and had entered into an agreement with the plaintiff Board for agricultural electricity service connection and the said agreement was entered with the plaintiff Board – Contracted and connected load in 10 H. P. and electricity supply was released – Whether courts below had arrived at correct conclusion on question of limitation in facts and circumstances of case – Counsel pointed out to respective pleadings of parties, evidence available on record and also findings recorded by Court of first instance and also appellate Court and would contend that if period from date of appellate order - Ex. A. 11 to be reckoned with, same is beyond the period of limitation – On contrary, learned Counsel representing respondent would contend that inasmuch as some further time had been specified under Ex. A. ll, period to be reckoned with after thirty days, after the making of the order- Ex. A. 11 and hence, same is within period of limitation – Held, Any suit for which no period of limitation is provided elsewhere in this Schedule", period of limitation is three years – Period begins to run from when the right to sue accrues. The cause of action to institute a suit would arise after the expiry of the period specified in Ex. A. 11 – It is needless to say that the said period would come to an end only after lapse of 30 days which had been specified in the order made by the appellate Authority under Ex,. A. 11 – Both Courts had taken this aspect into consideration and arrived at a conclusion that suit is perfectly within limitation and ultimately decreed the suit. In the light of concurrent findings recorded by both Courts below and also in light of contents of Ex. A. 11 and in view of Article 113 of the Limitation Act 1963 – Court opinion that suit is perfectly within period of limitation and hence the findings recorded by the Court of first instance and the decree made by said Court which had been, in fact, confirmed! by Appellate Court do not suffer from any illegality, whatsoever – Appeal shall stand dismissed.

( 1 ) HEARD Sri N. Siva Reddy, the Counsel representing appellant and Sri Sreeramulu Reddy, the Counsel representing respondent.

( 2 ) THIS Court on 21-5-1996 made the following order :-

"admit in view of substantial questions of law especially the one relating to limitation. "

( 3 ) SRI Siva Reddy, the learned Counsel representing appellant would submit that the only substantial question of law which would arise for consideration is "whether the courts below had arrived at correct conclusion on the question of limitation in the facts and circumstances of the case?" The learned Counsel pointed out to the respective pleadings of the parties, the evidence available on record and also the findings recorded by the Court of the first instance and also the appellate Court and would contend that if the period from the date of the appellate order - Ex. A. 11 to be reckoned with, the same is beyond the period of limitation.

( 4 ) ON the contrary, the learned Counsel representing respondent would contend that inasmuch as some further time had been specified under Ex. A. ll, the period to be reckoned with after thirty days, after the making of the order- Ex. A. 11 and hence, the same is within the period of limitation.

( 5 ) HEARD the Counsel and perused the findings recorded by the Court of the first instance and also the appellate court.

( 6 ) THE unsuccessful defendant in O. S. No. 33/85 on the file of the Principal District Munsif, Ramachandrapuram and the appellant in A. S. No. 18/93 on the file of the Subordinate judge, Ramachandrapuram, had preferred this appeal. The andhra Pradesh State Electricity Board - respondent herein is the plaintiff in the said suit. The suit was filed for recovery of rs. 10,747-60 ps. , with subsequent interest at 12 % per annum. The parties hereinafter would be referred to as plaintiff and defendant as arrayed in the original suit for the purpose of convenience.

( 7 ) THE plaintiff pleaded that the plaintiff is an agriculturist owning lands and had entered into an agreement with the plaintiff Board for agricultural electricity service connection no. 17481 of Konkuduru village and the said agreement was entered into on 21-1-1977 with the plaintiff Board. The contracted and connected load in 10 H. P. and the electricity supply was released. On 6-6-1978 at 14. 40 hours p. Sriramarao, Junior Engineer (DPE), Rajahmundry accompanied by M. Raghavendra Rao S. O. , Rayavaram, p. Satyanarayana, Lineman, Pandalapaka, P. Venkanna, helper, Konkuduru and VVSRIR Narasimha Rao, Junior engineer, D. P. E. , Rajahmundry surprised and checked the defendants service connection and during the check the following incriminating points wens found :-

1) The meter cover 3 seals are found to be counterfeit seals imitating the A. P. S. E. B. Laboratory sealing plier of the impression APSEB MRT R-2. 2) Supply is not available to check the working condition of the meter. 3) Consumption allowed to be recorded by the meter is low.

The said observation proves that the defendant pilferred electrical energy by removing the original seals of the meter putting back actually recorded consumption and putting counterfeit seals to the meter cover and thus caused immense loss to the respondent Board. At the time of inspection, Karri sattireddi, a friend of the defendant and Padala Srinivasa reddy, the son of the defendant also were present and on information passed on to the Assistant Engineer, Operation, ramachandrapuram, regarding the inspection, the said assistant Engineer - P. W. 2 disconnected the service connection and issued a provisional order dt. 7. 7. 1978 -Ex. A. 4 to the defendant assessing the loss caused to the board at Rs. 9,212-50 ps. , in addition to the service charge of rs. 50/- and reconnection charges of Rs. 20/- giving option to the defendant to pay half of the said amount + Rs. 50/- + rs. 20/- as mentioned above if the defendant wanted reconnection. The said notice was received by the defendant on the same day but howe











Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

SupremeToday

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top