SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(AP) 65

IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
R. RAGHUNANDAN RAO, J.
Nautilus Shipping India Pvt. Ltd. - Petitioner
Versus
Dredging Corporation of India Ltd. & Ors. - Respondents
Writ Petition No. 17813 of 2020
Decided On : 23-02-2021

Advocates Appeared:
For the Petitioners: Sri P. Roy Reddy.
For the Respondents: Sri A. Krishnam Raju, Sri M. Balanaga Srinivas.

Point of law: In defiance of the restraint order, the alienation/assignment was made. If we were to let it go as such, it would defeat the ends of justice and the prevalent public policy. When the court intends a particular state of affairs to exist while it is in seisin of a lis, that state of affairs is not only required to be maintained, but it is presumed to exist till the court orders otherwise. The court, in these circumstances has the duty, as also the right, to treat the alienation/assignment as having not taken place at all for its purposes

Headnote:

Contract Act – Section 63 – Agreement – Notice of unilateral termination – Petitioner which undertakes various shipping activities, had entered in to an agreement dated 06.12.2018 with the 1st respondent Corporation for the purposes of “manning and technical management of DCI dredge XIV at various ports in India”. – This contract was for a period of one year, which was extendable by another year on behalf of the 1st respondent for a value of Rs.3,99,90,991/-. – According to the terms of the agreement, the petitioner was required to offer a performance guarantee in the form of a bank guarantee. – Accordingly, the petitioner had furnished a bank guarantee through the 2nd respondent for a sum of Rs.39,99,099/-. – The Petitioner was put in possession of the said vessel and started managing the same. – By a letter 1st respondent claimed default on the part of the petitioner and issued a notice of unilateral termination and takeover of the vessel belonging to the 1st respondent – The petitioner replied to the said notice and sought amicable resolution of the issues. – As there was no response, the petitioner again sent an e-mail dated 19.08.2019, denying the claims of the 1st respondent and sought clearance of pending dues before the vessel could be delivered to the 1st respondent.

Finding of law: Process of invocation and encashment of the bank guarantee was initiated by 2nd respondent on 27.04.2020 and the same had failed. Subsequently, after receipt of a notice of the order of this Court on 29.04.2020, the 2nd respondent again went through the process of encashment of the bank guarantee on 30.04.2020. – The statement of the 2nd respondent that the process of encashment which commenced on 27.04.2020 and ended on 30.04.2020 is a continuous process cannot be accepted. – The 2nd respondent unequivocally states that after the first attempt had failed, a second attempt was done and the description of the second attempt clearly shows there was manual intervention in this process. – In these circumstances, it has to be held that the payment on the basis of the invocation of the bank guarantee was in violation of the orders of this Court dated 29.4.2020.

Result: Writ Petition Allowed

ORDER :

The petitioner which undertakes various shipping activities, had entered in to an agreement dated 06.12.2018 with the 1st respondent Corporation for the purposes of “manning and technical management of DCI dredge XIV at various ports in India”. This contract was for a period of one year, which was extendable by another year on behalf of the 1st respondent for a value of Rs.3,99,90,991/-. According to the terms of the agreement, the petitioner was required to offer a performance guarantee in the form of a bank guarantee. Accordingly, the petitioner had furnished a bank guarantee bearing No.0462OBG18022589 dated 04.12.2018 through the 2nd respondent for a sum of Rs.39,99,099/-. The Petitioner was put in possession of the said vessel and started managing the same.

2. By a letter dated 07.08.2019, the 1st respondent claimed default on the part of the petitioner and issued a notice of unilateral termination and takeover of the vessel belonging to the 1st respondent on 21.08.2019. The petitioner replied to the said notice on 12.08.2019 and sought amicable resolution of the issues. As there was no response, the petitioner again sent an e-mail dated 19.08.2019, denying the claims of the 1st respondent and sought clearance of pending dues before the vessel could be delivered to the 1st respondent.

3. The 1st respondent by an e-mail dated 20.08.2019 accepted the offer of the petitioner for a mutual resolution of the issues. However, the petitioner received another e-mail dated 20.08.2019, where the 1st respondent reiterated its intention to repossess the vessel on 21.08.2019 and that no payment would be made to the petitioner. This was replied by the petitioner on 20.08.2018 itself. However, there was a meeting between the representatives of the petitioner and 1st respondent on 22.08.2018 during which, certain issues were discussed and minutes of the meeting were prepared. The petitioner contends that in this meeting, the 1st respondent had undertaken not to invoke the bank guarantee issued by the petitioner, as performance guarantee, pending resolution of the disputes. On that basis, the petitioner had handed over the vessel of the 1st respondent on 23.08.2019. However, on 26.08.2019, the 1st respondent sought a modification of the minutes to the effect that the undertaking of the 1st respondent was substituted to state that the same would be dealt as per contractual terms and conditions.

4. The petitioner further contends that even though the contract ended effectively on 23.08.2019 and the 1st respondent was bound under the general conditions of the contract to return the bank guarantee, the 1st respondent went ahead and sought encashment of the bank guarantee. At that stage, the petitioner approached this Court by way of Writ Petition No.8301 of 2020, challenging the action of the 1st respondent seeking to encash the bank guarantee. On 29.04.2020 this Court, by way of an interim order, had directed the respondents not to encash the bank guarantee for a period of one week after the lock down is lifted. However, the bank guarantee was invoked and the proceeds were paid out to the 1st respondent.

5. Aggrieved by the said action of the respondents 1 and 2, the petitioner has now approached this Court contending that the invocation of the bank guarantee by the 1st respondent and the payment, arising out of such invocation, by the 2nd respondent is bad, arbitrary and required to be set-aside for the following grounds:

A. In the meeting on 22.08.2019, the 1st respondent gave an undertaking, as reflected in the minutes, that it would not invoke the bank guarantee until the issues between the petitioner and the 1st respondent were resolved. On the basis of this undertaking, the petitioner had given back the vessel under its management and possession to the 1st respondent. By doing so, the petitioner had changed its position to its detriment on the basis of the undertaking given by the 1st respondent. In such a situation, the invocation of

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon Back to top