IN THE HIGH COURT OF ANDHRA PRADESH AT AMARAVATI
Arup Kumar Goswami, J.
V.B. Cold Storage Private Limited – Appellant
Versus
Bajaj Allianz General Insurance Company Limited – Respondent
Arbitration Application No. 165 of 2014
Decided On : 24-09-2021
Arbitration and Conciliation Act, 1996 - Section 11(4) and (6) - Appointment of an arbitrator - Dispute Resolution - A major fire accident had taken place in cold-storage unit due to short circuit resulting in entire premises of cold-storage unit being gutted - All commodities stored in cold storage also went up in flames - On that day itself, applicant informed respondent about incident - Discussions had ensued in between representatives of applicant and respondent with regard to calculation of claim and applicant was informed that calculation of loss would be on basis of average of everyday stock values of each month, which was not acceptable to applicant as applicant has been submitting declaration statements basing on quantum of stock stored on last date of each month - Whether discharge of liability in present case upon acceptance of compensation amount by signing Indemnity Bond, Discharge Bond and consent letter was voluntary or under coercion or undue influence and whether applicant is justified in invoking Section 11(6) of Act of 1996 – Held, restricted and limited review is to check and protect parties from being forced to arbitrate when matter is demonstrably "non-arbitrable" and to cut off deadwood - Court by default would refer matter when contentions relating to non-arbitrability are plainly arguable; when consideration in summary proceedings would be insufficient and inconclusive; when facts are contested; when party opposing arbitration adopts delaying tactics or impairs conduct of arbitration proceedings - This is not stage for court to enter into a mini trial or elaborate review so as to usurp jurisdiction of Arbitral Tribunal but to affirm and uphold integrity and efficacy of arbitration as an alternative dispute resolution mechanism - Notwithstanding that petitioner had executed Indemnity Bond, Discharge Bond and consent letter, as petitioner had raised various pleas with regard to such execution, dispute between parties is required to be referred to an arbitrator, as there is a valid arbitration agreement - Arbitration Application allowed.
JUDGMENT :
Arup Kumar Goswami, J.
1. This application is filed under Section 11(4) and (6) of the Arbitration and Conciliation Act, 1996 (for short, "the Act of 1996") for appointment of an arbitrator.
2. The applicant is in the business of running a cold-storage for perishable consumables belonging to farmers/vendors. It had taken a Standard Fire & Special Perils Policy from the respondent-company for the year 2010-11. For the year 2011-12, the applicant had taken two Standard Fire & Special Perils Policies bearing Nos. OG-12-1819-4005-00000009 for Rs. 2,00,00,000/- (Rupees Two Crores) and OG-12-1819-4005-00000010 for Rs. 3,00,00,000/- (Rupees Three Crores) from the respondent-company on 28.05.2011. It was regularly paying the premium and submitting monthly stock declaration statements.
3. On 21.12.2011, a major fire accident had taken place in the cold-storage unit due to short circuit resulting in the entire premises of the cold-storage unit being gutted. All the commodities stored in the cold storage also went up in flames. On that day itself, the applicant informed the respondent about the incident. Discussions had ensued in between the representatives of the applicant and the respondent with regard to calculation of the claim and the applicant was informed that the calculation of loss would be on the basis of average of everyday stock values of each month, which was not acceptable to the applicant as the applicant has been submitting declaration statements basing on the quantum of stock stored on the last date of each month.
4. It is pleaded that the applicant had suffered losses to the tune of Rs. 1,51,34,922/-. On 07.03.2012, the applicant addressed a letter to the surveyors of the respondent, amongst others, requesting to complete the survey report at the earliest and also requesting to recommend to the respondent to release an interim amount of Rs. 60,00,000/- to disburse the same to some farmers who were under great financial loss.
5. A letter dated 05.05.2012 was issued by the applicant to the respondent to pay the claim amount of Rs. 1,51,34,922/- and another letter dated 25.05.2012 was issued requesting to finalize the report on the basis of the declaration submitted by the applicant. A letter dated 23.07.2012 was issued by the respondent that the stock declaration statements submitted by the applicant did not conform to the procedure laid down in the fire declaration policy and requested the applicant to submit fresh declarations on either the average of the values at risk on each day of the month or the highest value at risk during the month, much to the consternation of the applicant, as the respondent had never made a whisper that the stock declaration statements submitted by the applicant were not conforming to the fire declaration policy for the previous three years.
6. Subsequently, on 08.08.2012, the respondent sent a letter to the applicant enclosing a copy of the surveyor's letter along with the mode of assessment and requesting the applicant to give its consent to enable the respondent to process the claim. It is the pleaded case of the applicant that because of the turn of events, he was in a very depressed state of mind and as vendors/farmers were constantly pressing the applicant to settle the claims and had threatened the applicant with dire consequences if the claims were not settled, the applicant had no option but to accept the survey report, which settled the claim of the applicant for Rs. 62,88,241/-. Accordingly, he was compelled to sign the Indemnity Bond, which was a pre-requisite condition for release of the aforesaid amount. On 12.12.2012, the applicant addressed a letter to the respondent informing that he was compelled to accept the insurance claim under duress and that the applicant would treat the issue of settlement as a dispute and that the applicant would initiate arbitration proceedings as per clause 10 of the General Conditions of the Commercial Package Policy and the said letter was re
Associated Construction v. Pawanhans Helicopters Ltd.
Dell Computer Corpn. v. Union des Consommateurs & Olivier Dumoulin
Duro Felguera, SA v. Gangavaram Port Ltd.
Himangni Enterprises v. Kamaljeet Singh Ahluwalia
Konkan Railway Corpn. Ltd. v. Mehul Construction Co.
Konkan Railway Corpn. Ltd. v. Rani Construction (P) Ltd.
Mayavati Trading Private Limited v. Pradyuat Deb Burman
National Insurance Co. Ltd. v. Boghara Polyfab (P) Ltd.
National Insurance Company Limited v. Boghara Polyfab (P) Ltd.
Oriental Insurance Co. Ltd. V. Dicitex Furnishing Ltd.
Oriental Insurance Company and another v. Dicitex Furnishing Limited
United India Insurance Company Limited v. Antique Art Exports Private Limited
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.