2020 Supreme(Kar) 648
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
P.S. Dinesh Kumar, J.
Bharat Fritz Werner Limited Having Its Registered Office - Appellant
Versus
Office Of The Development Commissioner - Respondent
Writ Petition No. 8433 of 2020
Decided On : 23-07-2020
Nikhilesh Rao M, Advocate, D.N. Mamatha, Advocate
The rejection of a bid in a specific location does not necessarily give rise to jurisdiction in another location, and other factors such as the location of the petitioner's office and the COVID-19 pandemic may not justify the court's jurisdiction.
Headnote:
Jurisdiction - Tender Rejection - ONGC Case - Information Technology Act, 2000 - Bengaluru - New Delhi - Section 13(3) - E-mail Communication - Cause of Action - Bank Guarantee - COVID-19 Pandemic - Commercial Transaction
Fact of the Case:
The petitioner submitted a bid for the supply of CNC Milling Machines, but the tender was awarded to another party. The petitioner claimed that the rejection of the bid in New Delhi gave rise to a part of the cause of action in Bengaluru, justifying the jurisdiction of the court.
Finding of the Court:
The court found that the facts of the case were similar to those in the ONGC case, where the Supreme Court held that the rejection of a bid in New Delhi did not give rise to jurisdiction in another location. The court dismissed the writ petition, stating that it had not examined the merits of the case and that the dismissal did not preclude the petitioner from seeking relief elsewhere.
Issues: The main issue was whether the rejection of the bid in New Delhi gave rise to jurisdiction in Bengaluru, and whether other factors such as the location of the petitioner's office and the COVID-19 pandemic justified the court's jurisdiction.
Ratio Decidendi: The court applied the precedent set in the ONGC case and held that the rejection of the bid in New Delhi did not give rise to jurisdiction in Bengaluru. The court also found that other factors such as the location of the petitioner's office and the COVID-19 pandemic did not justify the court's jurisdiction.
Final Decision: The writ petition was dismissed, and all pending interlocutory applications were disposed of. No costs were awarded.
JUDGMENT
P S Dinesh Kumar, J. - Though this petition is listed for orders regarding completion of service of notices on respondents, Smt.D.N.Mamatha, learned CGC placing reliance on the decision of Hon'ble Supreme Court in Oil and Natural Gas Commission Vs. Utpal Kumar Basu and Others, (1994) 4 SCC 711 raised a preliminary objection regarding jurisdiction and strongly urged that writ petition is not maintainable and submitted that any further proceedings in this writ petition is uncalled for.
2. Heard Shri Nikhilesh Rao, learned advocate for the petitioner and learned CGC for the Union of India - respondent No.1.
3. Undisputed facts of the case are, the Development Commissioner of Ministry of Micro, Small and Medium Enterprises (MSME), New Delhi, called tender for supply of CNC Milling Machines in February, 2019. Petitioner having its registered office and works at Bengaluru submitted its bid on 17.07.2019. The bid was opened by the Development Commissioner on 18.07.2019 at New Delhi. Petitioner was declared as "L1" in respect of machines described in lot No.3. Petitioner was declared as "L3" in respect of machines described in lot No.1. Petitioner has quoted Rs.18.69 Crores for supply of machines in lot No.3. However, the Development Officer has awarded tender on 05.06.2020 to M/s. Phillips Corporation, Hanover, Maryland, USA (respondent No.2) who has quoted higher price than the petitioner.
4. The principal objection raised by the learned CGC is that tender was called for in New Delhi. Tender bids were submitted in New Delhi and the communication rejecting petitioner's bid dated 09.06.2020 (Annexure-N) has been sent from New Delhi. Therefore, authority in the case of ONGC (supra) is applicable to the facts of this case and hence, this Court has no jurisdiction to entertain this writ petition.
5. Shri Nikhilesh Rao urged following contentions;
Petitioner has its office and manufacturing unit at Bengaluru;
Bid was valid for 120 days and the Development Commissioner sought to extend the term of the bid and petitioner has consented for extension of term of the bid by E-mail on various dates from Bengaluru as per Annexures-M series ending with the last extension till 18.05.2020;
Respondent No.1 is the Union of India and therefore, in this COVID-19 situation, they ought not have raised this contention with regard to jurisdiction;
Petitioner has obtained bank guarantee from Canara Bank situated in Infantry Road, Bengaluru. With the above submissions, Shri Nikhilesh Rao submitted that part of cause of action has arisen in Bengaluru and therefore, this Court has jurisdiction to entertain this writ petition.
6. In support of his contentions, Shri Nikhilesh Rao placed reliance on following decisions;
(i) Om Prakash Srivastava Vs. Union of India and another, (2006) 6 SCC 207 ; and
(ii) M/s. P.R.Transport Agency Vs. Union of India, (2006) AIR Allahabad 23
7. I have carefully considered rival submissions and perused the records.
8. In ONGC case (supra), bid was called for by ONGC having its office at New Delhi. Respondent therein was having its office at Calcutta. The bid was rejected by ONGC, New Delhi. Writ petitioner moved Calcutta High Court. The Calcutta High Court entertained the writ petition and allowed it. ONGC challenged the same before the Supreme Court of India. The Apex Court allowed the appeal filed by the ONGC by holding thus:
"14. Before we part we must clarify that we have confined ourselves to deciding whether on the averments made in the petition any part of the cause of action is shown to have arisen within the jurisdiction of the Calcutta High Court. Even if we had come to the conclusion that the averments disclosed that a part of the cause of action had arisen within the jurisdiction of the said Court and therefore the petition could be entertained by that Court, it would still have been open for the opposite party to dispute the said averments were not true and correct, the petition, though entertained, would fail fo