IN THE HIGH COURT OF KARNATAKA AT BENGALURU
Abhay S. Oka, Suraj Govindaraj, JJ.
Union Of India Represented By Executive Engineer Bangalore Central Division Iii Central Public Works Department - Appellant
Versus
M/S. Warsaw Engineers No.3/89 and Ors. – Respondents
COMAP NO.25 OF 2021
Decided On : 17-04-2021
Commercial Courts Act, 2015 - sub-section (1A) of Section 13 - Arbitration and Conciliation Act, 1996 - Section 34 - Whether grounds urged are available under sub-section (2) and sub-section (2A) of Section 34 of said Act of 1996 - Whether grounds have been established - Whether same can be applied to facts of case before him - Petition under Section 34 of said Act of 1996 was to the award by learned Sole Arbitrator - Arbitration clause was incorporated in agreement concerning construction of Aircraft hanger and associated facilities consisting of various works - Dispute was as regards amount payable to respondents - One of main contentions raised is grounds which are urged by the appellant in support of the petition under Section 34 1996 have not been specifically dealt with by learned Judge of Commercial Court –
Finding of the Court:
Judicial Officer dealing with petition under Section 34 of said Act of 1996 to precisely record the submissions made by counsel for petitioner in support of petition under Section 34 of the said Act of 1996 - Impugned judgment and order will have to be set aside only on the aforesaid grounds - Court are conscious of fact that normally, the Appellate Court should be slow in passing orders of remand - There is non-consideration of the grounds pleaded in support of the petition under Section 34 of said Act of 1996 - Appellate Court for the first time goes into grounds urged and gives its own findings, perhaps one of the parties will be deprived of a right of statutory appeal provided in Section 13 of Commercial Courts Act - Court have no option but to remit the case for a fresh decision of the Commercial Court –
Result: Appeal is partly allowed
JUDGMENT :
On the last date, we have heard the submissions of the learned counsel appearing for the appellant and the learned counsel for the respondents.
2. By this appeal preferred under sub-section (1A) of Section 13 of the Commercial Courts Act, 2015 (for short, "the Commercial Courts Act"), the appellant has taken an exception to the judgment and order dated 25th September 2020 passed by a learned Judge of the Commercial Court at Bengaluru. By the said judgment and order, a petition filed by the appellant under Section 34 of the Arbitration and Conciliation Act, 1996 (for short, "the said Act of 1996") has been dismissed.
3. The challenge in the petition under Section 34 of the said Act of 1996 was to the award dated 1st February 2016 made by the learned Sole Arbitrator. The arbitration clause was incorporated in the agreement dated 22nd August 2007 concerning construction of Aircraft hanger and associated facilities at Belur Campus, Bengaluru consisting of various works. The dispute was as regards the amount payable to the respondents for the work carried out. The dispute was referred to the learned Arbitrator.
4. The learned Arbitrator granted the claims made by the respondents partially. The award was made in the sum of Rs.1,07,05,858/-along with the interest at the rate of 10% per annum payable by the appellant.
5. Various submissions have been canvassed by the learned counsel for the appellant in support of the appeal. One of the main contentions raised is that the grounds which are urged by the appellant in support of the petition under Section 34 of the said Act of 1996 have not been specifically dealt with by the learned Judge of the Commercial Court. The other submission is that the reasons have not been recorded for rejecting the challenge made by the appellant.
6. The learned counsel for the respondents supported the impugned judgment and order. He submitted that, in fact, no ground of challenge which is covered by Section 34 of the said Act of 1996 was made out and there is nothing wrong with the ultimate conclusion drawn by the learned Judge of the Commercial Court. He would submit that considering the limited scope of interference under Section 34 of the said Act of 1996, no fault can be found with the ultimate conclusion drawn by the learned Judge of the Commercial Court that there is no ground to interfere with the award.
7. We have given careful consideration to the submissions. As far as the scope of interference in a petition under Section 34 of the said Act of 1996 is concerned, the law is well settled. As far as the approach and scope of interference is concerned, we may make a reference to the decision of the Apex Court in the case of DYNA TECHNOLOGIES PRIVATE LIMITED vs. CROMPTION GREAVES LIMITED, (2019) 20 SCC 1 . In paragraphs 24 and 25, the Apex Court held thus:
25. Moreover, umpteen number of judgments of this Court have categorically held that the Courts should not interfere with an award merely because an alternative view on facts and inter
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.