IN THE HIGH COURT OF KARNATAKA (DHARWAD BENCH)
H.B. PRABHAKARA SASTRY, J.
The Hubli Electricity Supply Company and Ors. - Appellant
Vs.
Shreeshail - Respondent
Civil Revision Petition No. 100076/2018
Decided On : 10-12-2020
Code of Civil Procedure, 1908 - Order VII Rule 11 read with Section 151 – Electricity Act, 2003 - Section 86, 97, 145 and 143(1) - Suit for specific performance of contract - Civil Court not to have jurisdiction - Power to adjudicate - Seeking for rejection of plaint on the ground that, it was not maintainable in view of Section 145 of Act, 2003. Trial Court after inviting objection to the said application and hearing both side, by its impugned order, rejected the said application. Aggrieved by the said order, the defendants in the trial Court have preferred the present revision petition - Present petitioners as defendants appeared in the suit and filed their written statement denying the plaint averments – Held, Section 86(f) mentions that the State Commission shall discharge the function of adjudication upon the dispute between the licensees and the generating company and to refer any dispute for Arbitration - Since such dispute falling under Section 86 of the Act [including Section 86(f)] cannot be delegated to Adjudicating Officer under Section 97 of the Act, the bar under Section 145 of the Act that the matter which can be adjudicated by the Adjudicating Officer cannot be entertained by the Civil Court, does not apply in the instant case. The trial Court though has rejected the application with other reasons, but its finding that there is no bar for it to proceed with the matter cannot be found fault with - Civil Revision Petition stands dismissed.
ORDER :
H.B. PRABHAKARA SASTRY, J.
1. The present respondent as a plaintiff has instituted a suit against the present petitioners arraying them as defendants in O.S. No. 56/2017 in the Court of the learned Additional Senior Civil Judge at Jamkhandi (for brevity hereinafter referred to as 'the trial Court') for the relief of specific performance of contract and as an alternate relief, for the costs. The present petitioners as defendants appeared in the suit and filed their written statement denying the plaint averments. Further, the defendants filed an application i.e. I.A. No. V in the said suit under Order VII Rule 11 read with Section 151 of Code of Civil Procedure, 1908, (for brevity hereinafter referred to as 'CPC'), seeking for rejection of the plaint on the ground that, it was not maintainable in view of Section 145 of the Electricity Act, 2003 (for brevity hereinafter referred to as 'the Act'). The trial Court after inviting objection to the said application and hearing both side, by its impugned order dated 03.07.2018, rejected the said application. Aggrieved by the said order, the defendants in the trial Court have preferred the present revision petition.
2. The respondent is being represented by his counsel.
3. Though this matter is listed today for Admission, however, with the consent from both sides, the matter is taken up for its final disposal.
4. Heard arguments from both sides. Perused the materials placed before this Court.
5. Learned counsel for the petitioners in his arguments submitted that, Section 145 of the Act when clearly mentions that the Civil Court has no jurisdiction to entertain any suit or proceeding which an Assessing Officer or an Appellate Authority or an Adjudicating Officer can decide. As such, in the instant case since the dispute is between the petitioners (defendants) which is a licensee and the plaintiff (respondent herein) which is a generating company, the said dispute has to be decided by the Adjudicating Officer appointed by the State Commission to whom the power of adjudication can be delegated by the State Commission.
6. Learned counsel for the respondent in his brief argument submitted that, even though the defendant No. 1 is the licensee and the plaintiff is a generating company and the State Commission can appoint an Adjudicating Officer, but the said Adjudicating Officer cannot adjudicate the present dispute which falls under Section 86 of the Act, as such, the impugned order sustains.
7. Admittedly, the suit is for specific performance of a contract said to have been in existence between the plaintiff and the defendants. Under the said alleged contract the plaintiff has prayed for a direction against the defendants for commissioning of 49 kWp Solar Roof Top Photovoltaic System of the plaintiff and also for granting the ancillary relief of the profits. In the alternate he has prayed for awarding the costs of a particular sum. The present petitioners in their I.A. No. V filed under Order VII Rule 11 of CPC, have taken only the contention that in view of the bar under Section 145 of the Act, the suit before the Civil Court is not maintainable. Section 145 of the Act, reads as below:
8. As admitted by both sides, the present dispute between the parties won't fall either under Section 126 or Section 127 of the Act, as such, the bar for under those two Sections is not applicable. According to the learned counsel for the petitioners, the present dispute between the parties in th
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.