2026 Supreme(Kar) 877
IN THE HIGH COURT OF KARNATAKA AT BENGALURU
Vibhu Bakhru, C.J., K.S. Hemalekha, J.
Bangalore Development Authority - Appellant
Versus
M/S NCC Limited - Respondent
Commercial Appeal No.175 of 2026
Decided On : 30-09-2026
Act Referred
COMMERCIAL COURTS ACT : S.13(1)(a)
CONTRACT ACT : S.23, S.55, S.73
For the Appellant :Sri. K. Arvind Kamath, Senior Advocate For Sri. Ajay Kumar M., Advocate
For the Respondent:Sri. Sriranga S., Senior Advocate For Smt. Sumana Naganand & Smt. Supriya N., Advocates
JUDGMENT :
K.S. HEMALEKHA, J.
1. The appellant, Bangalore Development Authority (BDA), has preferred the present appeal under Section 37 (1) (C) of the Arbitration and Conciliation Act, 1996 [A&C Act] read with Section 13 (1A) of the Commercial Courts Act, 2015, impugning the judgment dated 24.02.2026 [the impugned judgment] passed by the learned LXXXII Additional City Civil and Sessions Judge, Bengaluru [Commercial Court] in Com. A.P No. 161/2024. By the impugned judgment, the learned Commercial Court dismissed the petition filed by the BDA under Section 34 of the A&C Act and consequently declined to interfere with the arbitral award dated 05.08.2024 [the impugned award] passed by the learned Sole Arbitrator [the Arbitral Tribunal].
Brief facts
2. The BDA entrusted the respondent, (M/s. NCC) with the work of renovation and reconstruction of the "Puttanna Kanagal Theatre" and adjoining shopping complexes at 4th Block, Jayanagar, Bengaluru. Pursuant there to, the parties entered into an agreement dated 27.06.2012 (agreement) for a contract price of Rs. 252.27 crores.
3. The work comprised demolition and reconstruction of 4 blocks, namely, blocks 1 to 4. Under the contract data, possession of Block No.1 was required to be handed over within 7 days from the date of work order. Insofar as Blocks 2 to 4 were concerned, clause 8 of the contract data contemplated that they were to be handed over upon completion and rehabilitation of Block No.1.
4. The existing premises in Block Nos.2 to 4 were occupied by vendors/lessees. The arrangement contemplated under the agreement, required such occupants to be relocated to the rehabilitated Block No.1 before possession of Block Nos.2 to 4 could be made available for execution of the remaining work.
5. Clause 7 of the Special Conditions of Contract [SCC] contained provisions governing claims for compensation on account of delay in commencement or execution of the work and stipulated that the employer would not accept liability towards claims for overheads and profits, except to the extent specifically contemplated under the contract.
6. The work relating to Block No.1, which was stipulated to be completed within 8 months from the date of the notice to proceed, was completed only in December 2014/January 2015. Possession of Block No.1 was thereafter handed over to the Bruhat Bengaluru Manahanagara Palike [BBMP] on 06.01.2018. The relocation of the vendors/lessees occupying Block Nos.2 to 4 and consequential handing over the said blocks for execution of the remaining work did not take place within the time period originally contemplated. In the interregnum, proceedings were initiated before the Lokayukta concerning the relocation of the occupants, and the process of shifting the vendors and making the remaining blocks available for execution was further delayed. These circumstances ultimately resulted in disputes between the parties concerning the execution of the balance work and the financial consequences arising there from.
7. M/s NCC invoked the arbitration clause, and on 28.09.2018 commenced arbitral proceedings. The learned Arbitrator was appointed to adjudicate the disputes between the parties.
8. Before the Arbitral Tribunal, M/s. NCC raised 10 claims, aggregating to Rs. 117,29,36,970, apart from the applicable taxes under various head. The claims made by M/s. NCC and the amount claimed are extracted below in a tabular form :

9. The Arbitral Tribunal, after completion of the arbitral proceedings, passed the arbitral award dated 05.08.2024 partly allowing the claims. The BDA being aggrieved by the said award instituted proceedings under Section 34 of the A&C Act before the Commercial Court. The said petition came to be dismissed by the judgment resulting in the present appeal. By the impugned award dated 05.08.2024, the Arbitral Tribunal partly allowed the claim Nos.1 to 4 and 7 to 9, while claim Nos.5 and 6 were rejected. In addition to claim No.1, an amount awarded under claim Nos.2, 3, 4, 7, 8 and