SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1996 Supreme(Bom) 580

IN THE HIGH COURT OF BOMBAY
V.P. Tipnis S.S. Nijjar, JJ.
The Century Textiles Industries Ltd. another ..... Petitioners.
Versus
The Maharashtra State Electricity Board another ......Respondents. .
Writ Petition No. 1917 of 1982, decided on 10-12-1996.
Advocates appeared :
A.J. Rana with K.J. Presswalla and D.J. Kapadia i/b. Mulla Mulla Craigie Blunt Caroe, for the petitioners.
Atul Rajadhyaksha with Gaurav Joshi i/b. Little Co., for respondent No. 1.
M.N. Zambre, Asstt. Govt. Pleader, for respondent No. 2.

Headnote:Article 226-Electricity-Supply Act. 1948. Section 49-Respondent entitled to charge supply of electrical energy at the rate of 75% of the Contract Demand-Even the demand is less then 75% of the contract-The minimum charge Is justified In view of fact that board has to maintain constant generating capacity and distribution system Irrespective of the fact whether energy is utillised by the consumer or not-Lock-out declared by petitioner cannot be taken as forced measure-Petition dismissed.

       Section 49-See Constitution of India, Article 226.

JUDGMENT - V.P. TIPNIS, J. :---Petitioner No. 1 - The Century Textiles Industries Limited - is a company and petitioner No. 2 is a shareholder of the company. The issue raised in the petition is as to whether the Maharashtra State Electricity Board is entitled to charge for supply of electrical energy in accordance with the tariff for the supply of electricity at high tension in accordance with the provisions of Clause 1 entitled "Minimum Bill" at the rate of 75% of the contract demand even when no demand is registered or the actual demand registered is much less than 75% of the contract demand owing to the circumstances beyond the control of the company like strike, lock-out, etc.

2.Prior to 1st July 1980, the company was receiving electrical energy at its divisions known as "Century Rayon, Rayon Division, Century Rayon Tyre Cord Division and Century Chemicals Divisions" situate at Shahad, Dist. Thane, from the Tata Electric Supply Company Ltd. As and from the midnight of 30th June/1st July 1980, the supply of electrical energy to certain areas which was being supplied by the Tata Electric Supply Company Ltd. was taken over by the Maharashtra State Electricity Board by a public notice dated 26th May, 1980. the terms and conditions under which the Maharashtra State Electricity Board supplied electrical energy were contained in the "Conditions and Miscellaneous Charge for supply of Electrical Energy." Those conditions were effective from 1st January 1976. It further appears that respondent No. 1 framed tariffs under section 49 of the Electricity (Supply) Act, 1948. Under Clause V(2) at the Tariff, "Contract Demand" is defined as follows :-

"Contract Demand means the maximum KW/KVA for the supply of which the Board undertakes to provide facilities from time to time."

Under Clause V(4) of the Tariff, "Billing Demand is defined as follows :-

"Billing Demand" means the demand used for billing purposes and computed as the highest of the following :

(i) the maximum demand established during the month as defined above ;

(ii) 75% of the Contract Demand as defined above ;

(iii) 50 KVA, or such other lower figures as may be approved by the Chief Engineer in the case of the licensees................."

The contract demand in the case of petitioner No. 1 during the relevant period was fixed at 27,750 KVA. During the relevant period, there was power cut of 22 1/2% imposed by the State of Maharashtra and thereby the contract demand was reduced to 21,080 KVA.

3.It is asserted by the petitioners that on or about 30th April, 1982 the management of the company was forced to declare a lock-out at the company's aforesaid divisions. Consequently, the company was not able to utilise its normal contract demand quota as the manufacturing activities at the aforesaid divisions came to a standstill. The actual demand registered by the company from 30th April 1982 onwards was reduced to approx. 2000 KVA. The company requested the Board to waive its demand charges for the unutilised demand during the lock-out period and to charge it for the actual demand registered by it. The respondents rejected the said request of the company. The respondent-Board informed that there is no provisions under the Tariff for waiver of demand charges. By further letter dated 14-6-1982 the company pointed out that there was a power-cut of 22 1/2% and the company was not in a position to utilise its contracted demand and the Board could profitably divert the unutilised demand to other units and, as such, no loss would be caused to the Board. The Board was again requested to give special consideration to the situation. However, the Board by its bill dated 2nd June 1982 for the month of May 1982 demanded the amount at 75% of the contract demand. In the bill, the actual demand registered for the period was 4,800 KVA. However, the Board charged the company at 75% of the contract demand i.e. 20,813 KVA. According to the petitioners, in the process, the company was compelled to pay to





























Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top