IN THE HIGH COURT OF BOMBAY
P.S. Patankar, J.
Miss Pinky N. Hotchandani ..... Plaintiff.
Versus
M/s. Daya Builders and others..... Defendants.
Notice of Motion No. 1234 of 1993, in Suit No. 1922 of 1993, decided on 9-2-1998.
Advocates appeared :
Mahabaleshwar N. Morje with Ms. Ratan Bharvan and V. Mallick, for plaintiffs.
Pankaj Kawli i/b Mayur Narendra and Co., for defendant Nos. 1 to 6.
Pankaj S. Shah, for defendant No. 11.

Important Points

A party cannot terminate an agreement for sale of a flat without completing the construction of the flat and without giving the other party 15 days' notice of termination.

Subject

Contract Law - Specific Performance

Act Referred

CIVIL PROCEDURE CODE : O.39 R.1, O.39 R.2, R.1, O.39, O.40 R.1, O.40, R.2

Headnote

{'KEYWORD': 'Specific Performance', 'SUBJECT': 'Agreement for Sale of Flat', 'ACT SECTION LIST': 'Not Applicable'}

Fact of the Case:

The plaintiff entered into an agreement with the defendant for the purchase of a flat. The plaintiff paid a substantial amount of the consideration. However, the defendant failed to complete the construction of the flat and terminated the agreement. The plaintiff filed a suit for specific performance of the agreement.

Finding of the Court:

The court held that the defendant was not justified in terminating the agreement and that the plaintiff was entitled to specific performance of the agreement. The court also held that the defendant No. 11 was not a bonafide purchaser for value without notice.

Issues: Whether the defendant was justified in terminating the agreement.

Ratio Decidendi: The court held that the defendant was not justified in terminating the agreement because the defendant had not completed the construction of the flat and had not given the plaintiff 15 days' notice of termination as required by the model agreement.

Final Decision: The court appointed a Court Receiver to take possession of the flat and ordered the plaintiff to deposit a sum of Rs. 1,04,000/- within 6 weeks. If the plaintiff failed to make the deposit, the defendant No. 11 was to be appointed as Agent of the Court Receiver.

JUDGMENT -P.S. PATANKAR, J.:---This Notice of Motion is taken out by the plaintiff praying for appointment of the Court Receiver and for injunction during the pendency of the suit.

2.The suit is filed for specific performance of the agreement entered into under letter of allotment dated 7-5-1989 and 27-5-1989 and revised on 27-3-1990, in respect of Flat No. 2, B-Wing, Daya Sarita, Gokuldham, Malad (East), Bombay 400 063.

3.The defendant No. 1 is a firm of developers and builders. Defendant Nos. 2 to 6 are partners thereof. Defendant Nos. 7 to 10 are owners of the plot of land on which the building Daya Sarita was to be built.

4.The plaintiff booked flat No. 2 admeasuring about 560 sq. ft. on 27-5-1989. Consideration agreed was fixed at Rs. 3,30,555/-. It was subsequently revised to Rs. 3,36,560/- in view of increase in area. However it was shown as Rs. 2,06,250/- (Rs. 1,37,500/- for flat and Rs. 68,750/- for extra amenities) in the original letter of allotment dated 27-5-1989. According to the plaintiff the plaintiff has paid an amount of Rs. 2,52,560/- mentioned in para 10 of the said agreement - 3 times by cash and 3 times by cheques. Out of the said amount, Rs. 50,000/- which was paid on 6-4-1990 by cash came to be refunded on 6-6-1990, by defendant Nos. 1 to 6 in cash. Thus plaintiff paid Rs. 2,02,560/- to defendants 1 to 6. From time to time letters were written to defendant No. 1 to furnish copies of agreements. But there was no reply. Finally the plaintiff has lodged the letter of allotment for registration by payment of stamp duty under Amensty Scheme on 29-3-1995.

5.According to the plaintiff defendant Nos. 1 to 6 were not carrying out the construction as agreed and they were delaying the same on one or the other ground deliberately. On 3-11-1992 defendants 1 to 6 by making a false averments that payment was not made has agreed terminated the allotment agreement. Thereafter the correspondence followed between the parties and the plaintiff requested this defendants 1 to 6 to withdraw the same. The plaintiff thereafter filed the suit for specific performance on 4-3-1993. On 13-7-1993 the plaintiff registered lis pendense with respect to the suit flat.

6.Defendants on 12-3-1994 issued notice in the newspaper for the in respect of this flat and again on 19-3-1994. The plaintiff on 28-11-1993, thereafter gave public notice in Mumbai Samachar requesting the purchaser to be aware that this flat was purchased by the plaintiff. However, again on 16-4-1994, defendants 1 to 6 published an advertisement for selling of the said flat.

7.The contentions raised on behalf of the defendants Nos. 1 to 6 are two folds. It is first contended that the plaintiff was not prepared to pay the agreed installments and hence there was proper termination of the agreement and cannot seek specific performance. It is further submitted that the plaintiff has not averred that he is ready and willing to comply with the obligations imposed upon her under the agreement/letters of allotment. It is not possible to accept any of these contentions. No doubt defendant Nos. 1 to 6 written letters and calling upon the plaintiff to make the payments. However, these payments were depending upon the completion of slabs of the building as envisaged under the letter of allotment Exh.A to the plaint. It is not the case of the defendant Nos. 1 to 6 that they have demanded the payment after completion of the work as contemplated by it. It that was so, the defendant Nos. 1 to 6 had no right to make the demands without making the necessary progress in the construction. In fact it is the contention of the plaintiff that the work was deliberately delayed and plaintiff was not given any access to watch it. No letter of the defendants 1 to 6 mentions about progress of the construction. As far as the second contention is concerned, I find that in para 15 of the plaint, there is clear averment made that the plaintiff has already paid substantial amount to the extent of 75% of the to