IN THE HIGH COURT OF BOMBAY
J.A. Patil, J.
Hector Hoshang Mehta others .... Plaintiffs.
Versus
Marol Nand Dham Udyog Premises Co-op. Society Ltd..... Defendants.
Suit No. 93 of 1977, decided on 19-10-2001.
Advocates appeared :
Pravin R. Diwan i/b. D.N. Nanavati, for plaintiffs.
D.V. Merchant with Deepak Thakkar i/b. Motafram Co., for defendants.
The main legal point established in the judgment is that the defendants breached their obligations under the lease deed, justifying the termination of the lease and entitling the plaintiffs to recover possession of the suit land. The court also granted the plaintiffs' claim for arrears of rent and compensation for unauthorized use and occupation of the suit land.
Headnote:
JUDGMENT - suit for declaration of title, possession and arrears of rent together with incidental prayers - Maharashtra Co-operative Societies Act - [JURISDICTION, LEASE DEED, BREACH OF OBLIGATIONS, INSURANCE, RENT, COMPENSATION, POSSESSION] - The court found in favor of the plaintiffs on the issues of jurisdiction, validity of the lease deed, breach of obligations by the defendants, failure to insure the buildings, and arrears of rent. The court also granted compensation for unauthorized use and occupation of the suit land and ordered the defendants to pay the arrears of rent and compensation with interest. The court dismissed the suit in respect of the prayer for a declaration of title.
Fact of the Case:
The plaintiffs filed a suit for declaration of title, possession, and arrears of rent against the defendants, a Co-operative Society registered under the Maharashtra Co-operative Societies Act. The plaintiffs alleged that the defendants, as lessees, committed breach of their obligations by failing to pay rent for three months and neglecting to insure the building structure on the suit land as per the lease agreement. The plaintiffs terminated the lease and sought possession of the suit land and buildings.
Finding of the Court:
The court found in favor of the plaintiffs, holding that the defendants breached their obligations under the lease deed by failing to pay rent and neglecting to insure the buildings. The court granted the plaintiffs' claim for arrears of rent and compensation for unauthorized use and occupation of the suit land, and ordered the defendants to deliver possession of the suit land to the plaintiffs.
Issues: The court analyzed and found in favor of the plaintiffs on the issues of jurisdiction, validity of the lease deed, breach of obligations by the defendants, failure to insure the buildings, arrears of rent, and compensation for unauthorized use and occupation of the suit land.
Ratio Decidendi: The court held that the defendants breached their obligations under the lease deed by failing to pay rent and neglecting to insure the buildings, justifying the termination of the lease and entitling the plaintiffs to recover possession of the suit land. The court also granted the plaintiffs' claim for arrears of rent and compensation for unauthorized use and occupation of the suit land.
Final Decision: The court partly decreed the suit, ordering the defendants to deliver vacant possession of the suit land to the plaintiffs, pay the arrears of rent and compensation with interest, and undergo an inquiry into future mesne profits. The court dismissed the suit in respect of the prayer for a declaration of title.
2. The plaintiffs have alleged that the defendants, as the lessees, committed breach of their obligations on two counts. Firstly, they failed and neglected to pay to the plaintiffs rent in respect of the suit land payable for the months of April, May and June, 1976 aggregating to Rs. 27,000/- and thereby committed a breach of Clause 2(a) of the Indenture of the lease. Secondly, the defendants failed and neglected to insure the building structure upon the suit land as stated in Clause 2(h) of the indenture of lease. The plaintiffs therefore, sent a notice dated 13th July, 1976 to the defendants and pointed out the aforesaid two breaches and called upon them to pay to the plaintiffs the arrears of rent of three months and also to ensure the buildings upon the suit land and produce for the plaintiffs' inspection the insurance policies and receipts of payment of premia. The plaintiffs have alleged that the defendants after receiving the notice, did not comply with the demands made therein and failed to remedy the breaches pointed out to them. The plaintiffs, therefore, by their second notice dated 21st September, 1976 terminated the lease and decided to exercise the power of re-entry. They called upon the defendants to deliver possession of the suit land together with the buildings and structures thereon. According to the plaintiffs they are always ready and willing to perform their obligations under the Indenture of lease but the defen