Jurisdiction - Maharashtra Rent Control Act - Condonation of Delay
Fact of the Case:
The petitioner challenges the order condoning the delay in filing an application for leave to defend under the Maharashtra Rent Control Act.
Finding of the Court:
The Court found that the Competent Authority had no jurisdiction to condone the delay in making an application for leave to defend, as there was no provision in the Act empowering the Competent Authority to do so.
Issues: The issue was whether the Competent Authority had the power to condone the delay in making an application for leave to defend under the Maharashtra Rent Control Act.
Ratio Decidendi: The Court held that as there was no provision in the Act empowering the Competent Authority to condone the delay, the order condoning the delay and granting leave to defend were null and void.
Final Decision: The petition succeeded, and both the orders condoning delay and granting leave to defend were set aside. The Competent Authority was directed to pass further orders on the application of the petitioner in accordance with the law.
2. Perusal of the provisions of sub-section (4) of section 43 lays down that a tenant or licensee on whom summons is duly served shall not contest the prayer for eviction from the premises unless within 30 days of the service of summons on him as aforesaid he files an affidavit setting grounds on which he seeks to contest the application for eviction and obtain leave from the Competent Authority. Sub-section (4) further lays down the consequences of the tenant not seeking such a leave. In case the tenant does not seek leave or makes an application for leave but it is not granted, the consequence is that the landlord becomes entitled to an order of eviction. In the Act, there is no provision which empowers the Competent Authority to condone delay in making an application for leave to defend.
3. The learned Counsel appearing for respondent is not in a position to point out any provision in the Act or any other law which will vest power in the Competent Authority to condone delay in making an application for leave to defend. In this view of the matter therefore, it is clear that the order dated 20th September, 2001 passed by the Competent Authority is an order made by the Authority without having jurisdiction to do so and therefore, the order is null and void and is therefore liable to be set aside. By another order dated 17th January, 2002, the Competent Authority has also granted leave to defend. As the Competent Authority had no power to condone the delay, obviously it could not have entertained the application filed by the respondent for grant of leave to defend. In the result therefore, the present petition succeeds and is allowed, both the orders impugned in this petition viz. the order condoning delay and the order granting leave to defend are set aside. The Competent Authority is directed to pass further orders on the application of the petitioner in accordance with law.
Parties to act on the copy of this order duly authenticated by the Sheristedar/Personal Secretary as true copy.
Certified copy expedited.
Order accordingly.
-----
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.