SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2002 Supreme(Bom) 1308

IN THE HIGH COURT OF BOMBAY
Rebello F.I., J.
Skanska Cementation India Ltd. .... Petitioner.
Versus
Bajranglal Agarwal others.... Respondents.
Arbitration Petition Nos. 185 186 of 2002, decided on 13-12-2002.
Advocates appeared :
D.D. Madon with P.A. Kabadi i/b., Doijode Phaterphekar, for petitioners.
Anil Agarwal, for respondent No. 1.

Headnote:Arbitration and Conciliation Act, 1996 - Section 7 - Contract Act, Section 28 - Arbitration agreement. - Where invoices for purchase order containing arbitral clause was accepted and money paid under invoices without protest then contract between parties clearly contemplated a provision for arbitration.

       Arbitration and Conciliation Act, 1996 - Section 7 - Purchase order - Arbitration agreement - Goods sent under delivery challan - Acceptance of without, protest - Delivery challan containing condition for reference of dispute to arbitration - Contract clearly contemplated a provision for arbitration. - The purchase order by itself would not be a contract between the parties. It is only on accepting the terms of the purchase order would a contract come into being. Clause I of the purchase order does provide that execution of this order shall be deemed to be acceptance of the conditions stated hereinabove. Clause II of the purchase order provided that the respondents could draw attention of the company to conditions which they find unacceptable. By the terms contained in the delivery challan the petitioner company is deemed to have been informed that the condition that their decision was final was not acceptable and that the dispute if any should be referred to arbitration of Bharat Chamber of Commerce. As such even though the purchase order was received, the respondents did not accept the purchase order and drew the attention of the company that the term of resolving the dispute was not acceptable by sending the goods under delivery challan which contained clauses 4 and 7. Clause 4 made it clear, that it is in the nature of counter-offer by the respondents to the petitioners for accepting the goods. In other words the respondents had not agreed to clause 10 of the purchase order. Even otherwise considering clause 11 the respondent had specifically informed the petitioners that they were sending the goods under the delivery challan with a different condition. The petitioners accepted the goods under the challan without protest. As such pursuant to the counter-offer or counter- proposal the terms of the delivery stood amended even considering clause 11 of the purchase order and accordingly the contract apart from the terms and conditions of the purchase order which were agreed by the parties would contain additional terms under which the goods were despatched and accepted by the petitioners. The respondents also sent invoices. Under the invoices again there was an arbitral clause. The invoices were accepted, moneys paid under the invoices without protest. According to Court, therefore, the contract between the parties clearly contemplated a provision for arbitration.

       Contract Act, 1872 - - Section 28 - Void agreement - Purchase order - Bars remedy of having recourse to Court of Law - In view of Section 28 of Act it is void. - The purchase order which bars the remedy of party of having recourse to Court of Law by leaving the matter to decision of the company would normally if an issue was raised would have been held to be void considering Section 28 of the Indian Contract Act.

       Arbitration and Conciliation Act, 1996 - Section 34 - Powers of Tribunal - Arbitral award - Setting-aside of - Parties to arbitration not permitted to engage lawyers - Discretion of Tribunal - No denial of an opportunity - Discretion exercised cannot be interfered with. - The exercise of discretion surely cannot be a matter for interference by the Courts under Section 34 by contending that the petitioners were denied an opportunity. The decision to permit engagement of lawyers was within the discretion of the Tribunal. Both the parties had sought the opportunity of engaging lawyers. Both have been dealt with equally.

       Arbitration and Conciliation Act, 1996 - Sections 31(7) and 34(2) - Setting aside of arbitral award. - When parties chose a forum to get their disputes adjudicated, Courts, should be slow in setting aside awards on technicalities when there is a ground available under Section 34(2) of Act.

       Arbitration and Conciliation Act, 1996 - Section 19 - Procedure followed by Arbitral Tribunal. - Once parties had accepted procedure followed by Tribunal then that procedure would be of Arbitration Rules of Chamber.

JUDGMENT -REBELLO F.I., J.:---Both the petitions are being disposed of by a common order as there are common challenges in both the petitions. The common challenges may be set out as under:-

(1) There was no agreement for arbitration in writing between the parties. Consequently the Award of the Arbitral Tribunal is without jurisdiction.

(2) The Arbitral Tribunal conducted the proceedings in Hindi, though a request was made to conduct them in English. Minutes of the order of the Arbitral Tribunal were made available to the petitioners as requested but were made available to the respondents as demonstrated by the respondents producing the minutates before this Court. It is further contended that though the proceedings were to be in Hindi, nevertheless an Award is passed in English. In these circumstances the petitioners were denied opportunity of presenting their case. The Award is therefore, liable to be set aside on that count. The petitioner were also denied the opportunity of opposing through Advocates even though an opportunity was sought. This was more so considering that the procedure was to be in the Hindi language. There was discretion in the Arbitral Tribunal, as the opportunity was denied. Considering the material available it is clear that the respondent Nos. 2 and 3 were not convenient with the English language yet the final Award has been pronounced in English. This would disclose no non-application of mind by the arbitrators. It was, therefore, contended that the petitioner's were denied sufficient opportunity and as such were unable to present their case.

(3) It is contended that the Arbitral Tribunal has awarded interest on interest which it could not have done. This would be again against the substantive law of India and consequently would be against public policy and as such the Award is liable to be set aside.

In addition, in so far as Arbitration Petition No. 186 of 2002, the additional challenge is:-

(a) The costs awarded are without jurisdiction as the costs are not in respect of the subject matter of the arbitral proceedings, but other litigation between the parties. That was not the subject matter of submission nor could have arisen from the arbitral clause. In these circumstances the Award to that extent is liable to be set aside.

2.A few facts may be now noted to enable this Court to dispose of the present petitions. Admittedly the petitioners in both the petition had placed purchase orders on the respondents. The dispute is regarding the balance unpaid amounts and the interest on the unpaid amounts. The petitioners in support of their contentions that there was no arbitral clause relied on the purchase order and more specifically Clauses 1, 10 and 11 which may be reproduced as under:-

"1. The execution of this order shall be deemed to be an acceptance of the conditions stated herein. The contract shall be deemed to have been made in Bombay, and shall be subject to jurisdiction of courts in Bombay.

"10. In case of any dispute the decision of the company shall be final and binding on the suppliers."

"11. In acknowledging the order the supplier is required to draw attention of the company specifically to any conditions contained in the order which he finds unacceptable and in the absence of such notification, the conditions contained herein shall exclusively govern this order."

It is, therefore, the contention of the petitioners that when the respondents supplied the goods it amounted to a contract which had come into force and it was governed by the provisions of the terms and conditions of the purchase order. The terms and conditions specifically provided that in case of any dispute, decision of the company shall be final and binding on the supplier. It is further contended that merely because the petitioners have signed some documents before the Arbitral Tribunal would not mean that they have submitted to jurisdiction. All throughout their contention is that the Arbitral Tribunal had no jurisdiction and conside



































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top