IN THE HIGH COURT OF JUDICATURE AT BOMBAY
O. O. C. J.
DR. D.Y. CHANDRACHUD, J.
Mumbai Metropolitan Region Development Authority - Petitioner
Versus
M/s. Unity Infraproject Ltd. - Respondent
ARBITRATION PETITION NO.287 OF 2007
WITH
ARBITRATION PETITON NO.288 OF 2007
Decided on : February 15, 2008.
Arbitration and Conciliation Act, 1996 - Section 36-Award-Setting aside of.-An Arbitrator appointed by parties to a contract to adjudicate upon a dispute is bound by legal precept to adjudicate in accordance with the contract. An Arbitrator cannot ignore the conditions of contract or award a head of claim which is prohibited by the contract. An Arbitrator derives his authority under contract pursuant to which his jurisdiction is created. An award which is passed in manifest disregard of the contract is liable to be set aside.
On 20th July 2003, the Petitioner invited tenders for the construction of 1648 tenements for the rehabilitation of project affected households at Kanjur Marg. This was a World Bank Project. The work was to be carried out in two phases. Phase I envisaged the completion of 384 tenements. Phase II involved the completion of the balance. The area where residential premises were to be constructed was densely populated and was congested with dwelling units of an informal nature. The two phase programme of work was to be in accordance with the availability of vacant space for the construction of buildings. The contractor was to initially complete three or four buildings and upon the shifting of project affected families in the space which would be vacated, other buildings were to be constructed. The contractor was on notice that he would have to coordinate the work in such a manner as would avoid any hindrance in progress of the work “for which he would not be paid any additional sum”. The contention of the Petitioner is that offers were invited on a lump sum basis for the entire work without adjustments.
2. The offer submitted by the Respondent was the lowest responsive offer and a letter of acceptance was issued on 3rd November 2003. During the course of the work, the Respondent raised claims inter alia towards loss of overheads, increases in costs, underutilization of machinery, refund of excise duties, increase in steel and cement prices and compound interest. The Engineer appointed under the contract refused to certify the claims of the Respondent by a letter dated 13th July 2004. Clause 24 of the agreement stipulated that in the event that a decision taken by the Engineer was outside the authority conferred by the contract or was wrong, the decision was to be referred to an adjudicator. In the meantime, the Respondent continued to raise bills including claims for the aforesaid amount, a practice which was followed from R.A. Bill 3 which was submitted on 24th August 2004 upto R.A. Bill 9 submitted on 24th February 2005. The Adjudicator was required to take a decision within 28 days. The Respondent referred the dispute to the Adjudicator on 3rd September 2004. On 27th October 2004, the Respondent invoked arbitration under the arbitral provisions contained in clause 25.2 of the contract, principally on the basis that the Adjudicator had failed to render a decision within the stipulated period. The Adjudicator was thereupon informed in a meeting held on 16th March 2005 that the Respondent did not desire to continue with adjudication for those claims which were referred to arbitration. Subsequent claims were referred by the Respondent to the Adjudicator on 7th March 2005. The Adjudicator held that the Respondent was entitled to an extension of time without levy of liquidated damages until 26th April 2005. The Engineer had by a letter dated 27th December 2004 imposed liquidated damages on the Respondent on account of delay in the completion of work under Phase I and declined to grant an extension of time. On 10th January 2005, the Respondent addressed a communication to the Petitioner recording therein that the Petitioner was not responsible for the delay in the completion of work under what was described as Mile StoneI and sought an extension of time for completion without levy of liquidated damages. The Respondent undertook that on account of a revision of the date for the first milestone until 31st March 2005, the Respondent “shall not stake any extra claim whatsoever on any of the above account” against the Petitioner and the Petitioner is not responsible in respect thereof. By a letter dated 25th January 2005, the Petitioner agreed to waive liquidated damages.
3. The contention of the Respondent in a letter dated 7th March 2005 and in a subsequent letter dated 18th March 2005 was that while it had waived all its claims by its letter dated 10th January 2005, that letter was written under duress. The Petitioner declined
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.