IN THE HIGH COURT OF BOMBAY
B. P. Dharmadhikari, J.
TULIP HOTELS PVT. LTD., MUMBAI and another – Appellants .
vs.
TRADE WINGS LTD., MUMBAI and others - Respondents.
The matter is being argued in the background of earlier adjudication in Arbitration Application No.4 of 2007 on 19-3-2008 by this Court holding that said application filed before it by the present applicants was premature because as per agreement between parties the arbitration was contemplated only after failure of conciliation held in terms of section 62 of Indian Arbitration and Conciliation Act, 1996, hereinafter referred to as 1996 Act or Arbitration Act. This Court then left present applicants i.e. M/s Tulip free to invoke said proceedings and all other contentions raised before it open. The two appeals against orders under section 9 of 1996 Act earlier ordered to be heard with this application have been separated with consent of parties on 17-7-2009. The respective Senior Advocates have completed their arguments after this order.
2. In view of this position and as contesting parties are before this Court through their respective learned Senior Advocates and existence of the arbitration clause vide clause No. 19 in the agreement is not in dispute, I have tried to find out the areas ~n dispute so as to curtail unnecessary lengthy arguments. It appears that the respondents claim a right in them to refuse to conciliate and thereby the frustration of arbitration clause itself and bar of limitation as also the nonreferrability of disputes to arbitration i.e. absence of arbitrable disputes in/as their defence. In the alternative, a Civil Suit filed by them in the matter claiming reliefs against the applicants and strangers is also being pointed out stating that strangers who are necessary parties to that Suit, being not parties to arbitration agreement, cannot be subjected to the arbitration. Accordingly, I have heard both the Senior Advocates. It cannot be disputed that the earlier conciliation conducted by one Mr. Om Navani is already declared to be not in terms of clause 19 of the agreement.
3. Shri Dessai, Senior Advocate for Tulips has pointed out that clause 19 envisaged completion of the conciliation proceedings within one month and failing it, the agreement presumed failure thereof leaving parties to take recourse to the arbitration. After judgment dated 19-3-2008 of this Court, the applicants issued a notice dated 21-6-2008 calling upon the respondents to conciliate before either of two retired Hon'ble Judges named therein and to communicate their acceptance within 10 days. Respondents replied to it on 21-6-2008 pointing out section 62 required 30 days notice and that there were no hopes from conciliation. They also did not agree to any of the names suggested by the applicants. The applicants then sent their rejoinder notice on 9-7-2008 agreeing to wait for 30 days. However, on 10-7-2008 respondents sent their negative response thereby making it clear that conciliation between the parties was not possible. Hence, after this failure of conciliation, applicants again sought appointment of Arbitrators under said clause 19 and approached this Court.
4. After inviting attention to the points of disputes and in order to show that the same are covered by the agreement our attention is invited to the memorandum of understanding i.e. MOU dated 26-4-2000 and Share Holding Agreement i.e. SHA dated 24-6-2000 between the parties. Senior Counsel Shri Dessai states that the applicants were supposed to purchase 50% share capital of M/s Trade Wings Hotels Ltd. i.e. TWHL before completion date as contemplated by the agreement between parties. He states this purchase was scheduled after paying 13.50 Crores to TWHL and against physical delivery of the shares. However, as 100% share holding and equipment of TWHL were then mortgaged/pledged with Tourism and Finance Corporation Of India i.e. TFCI the sale itself was not possible. Because of efforts made by the applicants, OTS i.e. one time settlement of loan amount was reached between TWHL and TFCI and out of amount of Rs. 16.50 Crores paid by the applicants, OTS amount of Rs. 12 C
State of U. P. vs. Lalji Tandon
India Household and Health Care Ltd. vs. LG Household and Health Care Ltd.
National Agricultural Corporation Marketing Federation of India Ltd. vs. Gains Trading Ltd.
Visa International Ltd. vs. Continental Resources (USA) Ltd.
DHV BV vs. Tahal Consulting Engineers Ltd.
Bharat Petroleum Corporation Ltd. vs. Great Eastern Shipping Company Ltd.
You One Engineering and Construction Company Ltd. vs. National Highway Authority of India
Iron and Steel Company Ltd. vs. Tiwari Road Lines
Sukanya Holdings (P) Ltd. vs. Jayesh H. Pandya
Shree Subhlaxmi Fabrics Pvt. Ltd. vs. Chand Mal Baradia and others
Shin-Etsu Chemical Co. Ltd. vs. Mis Aksh Optifibre Ltd.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.