1983 Supreme(Bom) 4

Bombay High Court
S.P.BHARUCHA
Majas Land Development Corporation - Appellant
Versus
State of Maharashtra - Respondent
Decided On : 01/12/1983

Advocates:
D.R. Dhanuka with M.B. Rele, for Petitioners; S.S. Parkar, for respondents.

The withdrawal of land from acquisition under the Land Acquisition Act is not effective until it is communicated to the owner of the land.

Headnote:

LAND ACQUISITION ACT - SECTION 4, 6, 9, 11, 21, 48 - URBAN LAND CEILING ACT - SECTION 8, 9 - WITHDRAWAL OF LAND FROM ACQUISITION - COMPENSATION - DELAY IN PAYMENT - INJUNCTION - SUMMARY

Fact of the Case:

The petitioners' land was acquired in 1972 under the Land Acquisition Act for the use of the Maharashtra Housing and Area Development Authority. However, the Authority later decided not to use the land and obtained sanction to withdraw it from acquisition in 1981. The petitioners were not informed of this decision and the compensation for the land was not paid. The petitioners filed a petition seeking a direction to the State to forbear from applying the provisions of the Urban Land Ceiling Act to the land and to forthwith publish an award determining the compensation payable to them.

Finding of the Court:

The court held that the Land Acquisition Act continued to apply to the land as there was no final statement under Section 9 of the Urban Land Ceiling Act in which the land was included. The court also held that the withdrawal of the land from acquisition was not effective until it was communicated to the petitioners. The court directed the respondents to make and publish an award under Section 11 in respect of the land on or before 1st April, 1983 and to make payment of the compensation so awarded on or before 1st May, 1983. The court also injuncted the respondents from further applying to the land the provisions of the Urban Land Ceiling Act.

Issues: 1. Whether the Land Acquisition Act or the Urban Land Ceiling Act applied to the land. 2. Whether the withdrawal of the land from acquisition was effective. 3. Whether the petitioners were entitled to compensation for the land.

Ratio Decidendi: 1. The Land Acquisition Act continued to apply to the land as there was no final statement under Section 9 of the Urban Land Ceiling Act in which the land was included. 2. The withdrawal of the land from acquisition was not effective until it was communicated to the petitioners. 3. The petitioners were entitled to compensation for the land.

Final Decision: The court allowed the petition and directed the respondents to make and publish an award under Section 11 in respect of the land on or before 1st April, 1983 and to make payment of the compensation so awarded on or before 1st May, 1983. The court also injuncted the respondents from further applying to the land the provisions of the Urban Land Ceiling Act.

ORDER :- The facts of this petition disclose a scant regard for the citizen's property.

2. On 15th Jan. 1969 a notification was issued under S.4 of the Land Acquisition Act stating that 95,957 sq. yds. of land near Jogeshwari, of the petitioners' ownership, was likely to be needed for a public purpose, namely, for the use by the Maharashtra Housing and Area Development Authority, the 4th respondent. On 13th Jan. 1972 the land was acquired, a notification under S.6 being issued. In Aug. and Oct. 1974 notices were issued under S.9 (3) and (4) of the Act. Hearings commenced in Mar. 1975 and, according to the affidavit of the respondents, the last date of hearing was 6th May 1977. On 12th Nov. 1979 the petitioners filed this petition asking that the State of Maharashtra, the 1st respondent, should be directed to forbear from applying the provisions of the Urban Land Ceiling Act to the land and to forthwith publish an award determining the compensation payable to the petitioners for the land.

3. On 18th December 1979, an affidavit was filed on behalf of the respondents to oppose admission wherein it was stated that "...respondent No 4 has not finally communicated their firm decision to take up these lands and hence the question of compensation after declaration and publishing of the award becomes problematical." On 5th September, 1980, an affidavit in reply to the petition was filed in which it was stated that the 4th respondent was "in the process of reconsidering its need for the land in question and there is a possibility of the said land being withdrawn from acquisition".

4. During the course of the hearing before me today Mr. Parkar, learned Assistant Government Pleader, appearing for the respondents, stated that the land had already been released from acquisition and he relied in this context upon a document produced from the files of those instructing him. The document is dated 12th June, 1981. It is signed by the Additional Commissioner, Konkan Division. By it the Additional Commissioner has accorded sanction under Section 48(1) of the Act to the withdrawal of the land from acquisition.

5. It is an admitted position that no action has been taken pursuant to this sanction and that the petitioners have not been informed that the land has been withdrawn from acquisition.

6. It is also an admitted position that the proceedings under the Urban Land Ceiling Act in respect of the land have not proceeded beyond the stage of Section 8 thereof. The judgment of the Division Bench of this Court is Ganesh Rangnath Dhadpale v. Special Land Acquisition Officer (I), Pune, 1979 Mah LJ 786, lays down that an inconsistency between the provisions of the Urban Land ceiling Act and the Land Acquisition Act arises only after the competent authority prepares a final statement under Section 9 of the Urban Land Ceiling Act and includes the particular land therein. It lays down that, notwithstanding enquiries under S.8 of the Urban Land Ceiling Act, the Land Acquisition Act continues to apply to the particular land. Having regard to this position in law and the admitted position that there is no final statement under Section 9 of the Urban Land Ceiling Act in which the land is included, it must be held that the Land Acquisition Act continues to apply to it.

7. It was contended by Mr. Dhanuka that under the provisions of Section 21 of the General Clauses Act the rescinding of a notification under Sec.6 of the Land Acquisition Act must take place in the same manner as its original promulgation. In other words, the land could not be withdrawn from acquisition until and unless a notification to that effect was published in the Government Gazette. The Manual of Land Acquisition for State of Maharashtra States (in para. 303-B). "As the land Acquisition Act does not prescribe any formality for withdrawing from acquisition under Section 48, mere cessation of proceedings is sufficient. When Government/Commissioner decides to withdraw, and the decision is communicat



Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top