2009 Supreme(Bom) 1522
High Court of Judicature at Bombay
THE HONOURABLE MR. JUSTICE ANOOP V. MOHTA
Milan Commercial Pvt. Ltd.
Versus
Asian Healthcare Services Limited & Others
Notice of Motion No.1691 of 2008 in Suit No.1452 of 2008
Decided on : 16-11-2009
For the Plaintiff:S.H. Doctor, Sr.Counsel with Siddharth Mitra, Zal Andhyarujina, Ms. Rupa Mitra and Ms. Nandini Khaitan, Chakrapani Misra, Devesh Juvekar, Vishal Maheshwari and Mr.Ameya Gokhale, i/b. M/s.Khaitan & Co., Advocates. For the Defendants:D1, Harish Pandya i/b. Aditya Khanna, D3, D4, D5 to D8, D16 to D21, Rahul Chitnis i/b. Mustafa Banatwala, D2, D9 to D15, Fredum Divetre, Sr.Counsel with Akshay Patil, Vikram Trivedi, Rohan Cama, Faisal Sayyed and Ms. S. Dadachanji i/b. M/s. Manilal Kher Ambalal & Co., D22, Narendra Walawalkar, Sr. Counsel and Gaurav Joshi with Ms. Anisha Shroff i/b. M/s.A.T. Agarwal, D23, E. P. Bharucha, Sr. Counsel i/b. M/s. Vimadalal & Co., Advocates.
Headnote:Specific Relief Act, 1963 - Sections 10 and 12 - Civil Procedure Code, 1908, Order XXXIX, Rules 1 and 2 - Suit for specific performance of agreement - Praying for grant of interim relief - Plaintiff shareholder of defendant-1 seeking injunction against defendants 2 to 4, a joint venture company for construction of a Hospital - Notice of termination of joint venture agreement given by defendant-2 - Held - Defendant-1 not seeking specific performance - Joint venture agreement to go by clauses of association - Defendant-2, lessee-owner of land throughout - Unless notice of termination of contract declared invalid, no relief can be granted to plaintiff - Plaintiff not party to any agreement between defendants - Not entitled to claim specific performance or interim reliefs - Notice of motion dismissed. - The above principles will apply here also. The fact remains that JVA is in existence even after incorporation of the company. All the basic elements and clauses pertaining to the plot/land of defendant No. 2 are incorporated in detail. Both the parties are aware of the same. The isolated reading only of Articles will frustrate the whole scheme and the object. It is not possible to overlook the purpose and formation of the company. It was intended to construct and build the hospital. There is substantial material on record to show that defendant No. 2 has title and right over the land through out. It was never transferred or intended to transfer and basically in view of grant of land conditions itself. There is also no statutory permission or consent on record to show that any such transfer of title or right. The land just cannot be utilised but only as per the original grants and agreements even by the company. Defendant No. 2 in view of those terms and conditions cannot transfer the tile owner ship without prior due permission from the Department/ Authorities. It is difficult to accept the contention on behalf of the plaintiff that the ownership/title of the land and has been transferred by the agreement.
If the company is established for a particular project, it need to be respected throughout. The document/agreements main object and purpose just cannot be overlooked. If the defendant/company or concerned parties though agreed but was not in a position to complete the project and in fact committed various defaults and suffering from Departmental notices for inaction or defaults, besides no consistent financial support and unless all these ingredients are answered in favour of the company or in favour of the plaintiff and unless the main prayers so raised in the suit are granted including the declaration of these two agreements being null and void at this stage, Court is not accepting the case of the plaintiffs who is seeking such reliefs in favour of defendant No. 1 stating it to be the permissible derivative action.
Besides, the suit is for specific performance of contract and for declaration and related reliefs/injunction. The relief of specific performance is a discretionary. The injunction or such interim reliefs in aid of specific purpose and/or declaration read with compensation/damages are two other important facets in such matters. It also depends upon the facts and circumstances of each case. The injunction or interim reliefs, in such situation, need to be based upon the various elements of Order 39, Rule 1 and 2 and Order XL, Rule 1 and 2 and Specific Relief Act. Admittedly there was no concluded contract between the plaintiff and the other defendants. The plaintiffs being not a party to such agreement cannot claim the specific performance in such fashion. The company’s readiness and willingness to perform its part of the obligation just cannot be answered or defended by the plaintiff in such proceedings. The company has its own remedy available as per the agreement itself. The plaintiff cannot seek specific performance on behalf of third party like the company or defendants 3 and 4, even it is accepted that it is derivative action on belay of the company still in the present facts and circumstances of the case specially when there is a specific clause of arbitration agreement. In Court view the suit is not bona fide, specially when the material and evidence and the proof in support of the submissions as noted above, are unclear and unanswered.
In view of the above, Court is not inclined to grant any relief. The Notice of Motion is accordingly dismissed.
1. This Notice of Motion dated 30.04.2008 is taken out by the plaintiff in a pending Suit for declaration & specific performance & various interim reliefs/injunction.
2. It is necessary to note the basic prayers of the Suit, covering prayers for interim reliefs also, which are as under:
(a) that this Hon’ble Court be pleased to pass an order of declaration that the Defendant No.1 is lawfully entitled to remain in possession of the said land mentioned in paragraph 14 hereof and to develop and construct the said hospital on the said land and to use the said land for the purpose of building a super specialty hospital.
(b) that this Hon’ble Court be pleased to pass an order of Declaration that the purported letter of termination dated February 1, 2008 addressed by the Defendant No.2 to Defendant Nos. 3 & 4 is wrongful, illegal and not binding on the Defendant No.1 Company and its shareholders including the plaintiff.
(c) that this Hon’ble Court be pleased to pass an order of Specific performance of the agreement dated April 23, 2007 (Ex. `H’ hereto) in favour of the Defendant No.1 by other Defendants and all ancillary orders and directions for the implementation thereof.
(C1) that this Hon’ble Court be pleased to order & restrain the Defendant Nos. 2, 9 to 15 by themselves, their servants, agents or assigns or otherwise whatsoever from disturbing or interfacing with the possession of the Defendant No.1 of the said land situated at Worli, Mumbai and from in any manner interfering with the right of the Defendant No.1 from using the said land.
(c5) that this Hon’ble Court be pleased to order and declare
(i) that the said Memorandum of Understanding dated 14 April 2008 (Exhibit “Z1”) hereto) is not a valid Agreement and creates no rights whatsoever in favour of the Defendant No.2, 22 and 23 and is null and void and is void ab-initio;
(ii) that the said Memorandum of Understanding dated 14 April, 2008 (exhibit Z1) hereto) does not in any manner whatsoever create any right or interest of whatsoever nature in favour of Defendant Nos. 2, 9 to 15 and/or Defendant Nos. 22 and/or Defendant No.23 in or over the suit land or any part thereof; and
(iii) that the said Memorandum of Understanding dated 14th April, 2008 (Exhibit Z hereto) is liable to be delivered up and cancelled and the Defendant Nos.2, 9 to 15, Defendant Nos.22 and 23 are jointly and severally liable to deliver the said Memorandum of Understanding dated 14th April, 2008 to the office of the Prothonotary and Senior Master, High Court, Bombay for the purposes of cancellation.
(c6) that this Hon’ble Court be pleased to order and direct that the said Memorandum of Understanding dated 14th April, 2008 (Exhibit “Z1” hereto) be forthwith delivered up and cancelled and by the Defendants No.2, 33 and 23 to the Prothonotary & Senior Master, High Court, Bombay for the purposes of cancellation and that the Prothonotary & Senior Master do cancel and destroy the same.
(c7) that this Hon’ble Court be pleased to pass an order of injunction restraining Defendant Nos. 2, 9 to 15, 22 and 23 jointly and/or severally by themselves, their servants, agents and assigns or otherwise whatsoever from in any manner creating any further third party rights and/or encumbrances of whatsoever nature by whatsoever named called pursuant to and/or in furtherance of and/or in implementation of the said Memorandum of Understanding dated 14 April 2008 (Exhibit “Z1” hereto) and/or from acting in accordance with and/or in furtherance of the said Memorandum of Understanding dated 14 April 2008, or from in any manner implementing the terms of the said Memorandum of Understanding.”
(c8) that this Hon’ble Court be pleased to pass an order of injunction restraining Defendant Nos. 2, 9 to 15, 22 and 23 jointly and/or severally by themselves, their servants, agents and assigns or otherwise whatsoever from in any manner creating any further and/or any other third party rights and/or encumbrances of whatsoev