SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Article Pause Article
judgment-img

2012 Supreme(Bom) 1573

High Court of Judicature at Bombay
ANOOP V. MOHTA
Maharashtra State Road Development Corporation Ltd.
Versus
Valecha Engineering Ltd. & Others
ARBITRATION PETITION NO. 269 OF 2008
Decided on : 17-08-2012

Advocates appeared:
For the Petitioner:D.D. Madon, Senior Counsel with P.P. Chavan & Nooruddin Dhilla i/by Amarchand Mangaldas and S.A. Shroff & Co., Advocates.
For the Respondents:K.M. Javle, Advocate.

The main legal point established in the judgment is the interpretation of contract terms, specifically Clause 14 of the Special Conditions of Contract, and the entitlement of the contractor to reimbursement of increased royalty charges.

Headnote:

Reimbursement of Royalty Charges - Construction Contract - Clause 14 of the Special Conditions of Contract - NHAI Project - Maharashtra State Border Section of NH4 - Summary of Acts and Sections: Clause 14 of the Special Conditions of Contract, The Godhra Electricity Co. Ltd. & Anr. Vs. The State of Gujarat & Anr (AIR 1975 SC 32), RashtriyaIspat Nigam Limited Vs. M/s. Dewan Chand Ram Saran,2012(3) All MR 972 (S.C.) - The court discussed the interpretation of Clause 14 of the Special Conditions of Contract, the concept of royalty charges, and the entitlement of the contractor to reimbursement of increased royalty charges. The court's decision was influenced by the interpretation of the contract terms and the intention of the parties, as well as previous legal precedents.

Fact of the Case:

The Petitioners challenged the award passed by the Sole Arbitrator regarding reimbursement of increased royalty charges and price escalation under a construction contract for a National Highways Authority of India (NHAI) project.

Finding of the Court:

The court found that the contractor was entitled to reimbursement of increased royalty charges as per the interpretation of Clause 14 of the Special Conditions of Contract and previous legal precedents. The court modified the award to reduce the interest rate from 15% to 9% but maintained the rest of the award.

Issues: Dispute over reimbursement of increased royalty charges and price escalation under the construction contract, interpretation of Clause 14 of the Special Conditions of Contract, entitlement of the contractor to reimbursement, and the appropriate interest rate for the award.

Ratio Decidendi: The court's decision was based on the interpretation of the contract terms, the concept of royalty charges, and the entitlement of the contractor to reimbursement of increased royalty charges. The court also considered previous legal precedents to support its decision.

Final Decision: The court modified the award to reduce the interest rate from 15% to 9% but maintained the rest of the award, including the reimbursement of increased royalty charges to the contractor.

Judgment :

The Petitioners, a Government of Maharashtra undertaking, have challenged the award dated 29 February 2008 passed by the Sole Arbitrator, as appointed on the basis of Arbitration clause in the agreement in question between the parties.

2. On or about December 2001, the Petitioners invited tender for Four Laning of Satara Kolhapur upto Maharashtra State Border Section of NH4 Package III from km. 639/000 to 668/000. The Petitioners awarded the work to the Respondents and issued a letter of acceptance. A formal contract was entered into between the parties. On 3 May 2002, a notice to proceed with the work was issued to the Respondents, which work was to be completed by 2 August 2004. On 1 June 2005, the work was completed by the Respondents.

3. Certain disputes arose between the parties in respect of the contract with regard to reimbursement of increase in royalty charges under the provisions of Clause 14 of the Special Conditions of Contract mentioned hereinabove and Price Escalation in respect of 32 mm MS Dowel Bars used in Pavement Quality Concrete (for short, PQC).

4. On 6 April 2006, the Respondents gave a notice under Clause 67.2 of the contract calling upon the Petitioners to refer the claims to the Steering Committee. The decision of the Petitioners on the recommendation of the Steering Committee was communicated to the Respondents. The Respondents referred the matter for Arbitration.

5. On 7 November 2006, Shri Sharad P. Upasani IAS (Retd.) Former Chief Secretary, Government of Maharashtra was appointed as a Sole Arbitrator. The learned Arbitrator issued notice of a preliminary meeting. A preliminary meeting was held. The Respondents filed their statement of claims. The Petitioners filed their statement of defence. the Respondents filed their rejoinder. On 29 February 2008, the Award was passed.

6. The Award is passed claim-wise, which reads as under:-

“19 In view of the above, I have no hesitation to conclude that the Claimant has proved his case for entitlement of reimbursement of the enhanced Royalty which comes to Rs.1,16,71,879 as per the joint calculations dated 4th February 2008 given as per the direction of the Arbitral tribunal. The contract provides for interest at the rate of 15% p.a. To be paid on unpaid sums. In the joint statement the parties have also given interest calculations at 15% from 30-9-2005 till 30-11-2007. The amount of interest comes to Rs. 32,908.95. I therefore award the payment of entire amount of Rs.1,49,62,774 plus further interest at 15% on the principle amount of Rs. 1,16,71,879 till the date of payment.”

7 The relevant clause for deciding the issue with regard to the reimbursement of increase in royalty charges is as under:

“14.0 TAXES

The rates quoted by the Contractor shall be deemed to be inclusive of Sales and other taxes on all materials that the contractor will have to purchase for performance of this Contract. Any further increase in Central or State Sales Tax or other taxes on complete items of work of this contract as may be levied and paid by the contractor shall be reimbursed by the Employer to the contractor on proof of payment. The octroi charges, if paid any, shall be reimbursed by the employer on proof of payment.”

The said Clause 14 was amended as per corrigendum/addendum to Volume-1 of Bid document SECTION-VII, SPECIAL CONDITIONS OF CONTRACT, as follows, namely:

“4 Page No. 111, Para 14.0 TAXES Line No.2 Add `including royalty charges' after `taxes'.”

8 The relevant portion of clause, after amendment, reads as under:

“The rates quoted by the contract shall be deemed to be inclusive of sales and other taxes including Royalty charges on all materials that the construction will have to purchase for performance”.

9 It is relevant to note that the National Highways Authority of India (The NHAI) constituted by the Government of India, had taken up the work of Four Laning of (National Highway) NH-4 from Mumbai to Chennai known as “Golden Quadrangle Project”. The NHAI,























Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top