BOMBAY HIGH COURT
S.J.VAZIFDAR, MRIDULA BHATKAR, JJ.
M/s. Hi Tech India Construction
Versus
The CEO, Slum Rehabiliation Authority & Ors.
Decided on : 1/3/2013
Where draft of show-cause notice was approved by CEO and notice was issued by Dy. Chief Engineer and pursuant to notice, CEO after hearing matter passed impugned order therefore show clause notice not suffers from any technical infirmity. - It is clear that the show-cause notice was only issued "under the signature of" the Deputy Chief Engineer, SRA. The draft thereof was referred to in the submission. The Chief Executive Officer, therefore, approved the draft and directed that the show-cause notice to be issued under the signature of the Deputy Chief Engineer. Pursuant to the show-cause notice, it is the Chief Executive Officer who heard the matter and passed the impugned order dated 28th September, 2010. There is, therefore, no technical infirmity in respect of the show-cause notice.
Maharashtra Slum Areas (Improvement Clearance and Re- development) Act, 1971 - Section 13(2) - Termination of appointment as Developer.
Where failure of developers to pay premium amount in accordance therewith resulted in a delay in implementation of project therefore their termination not improper. - Apart from the general delay, it is important to note that the petitioners did not pay the premium which admittedly was to be paid in view of the circular dated 12th June, 2008, read with the circular dated 16th April, 2008. The petitioners had sought a clarification from the authorities as to where and as to whom the premium should be paid has been held to be a devise for avoiding payment. Court is unable to state that this conclusion is perverse or mala fide. The circulars are clear. The petitioners ought to have tendered the payment in accordance therewith. Their failure to do so resulted in their not having been granted the letter of intent leading to a delay in the implementation of the scheme. Even assuming that the authorities did not respond to the petitioners queries, it would make no difference. The petitioners were not entitled to delay the implementation of the project on that ground. The slum dwellers are not concerned with the same in any event. Their project has now been delayed considerably.
S. J. VAZIFDAR, J. :-
1. Respondent No. 1 is the Chief Executive Officer of the Slum Rehabilitation Authority (hereinafter referred to as "SRA"), respondent No. 2 is the Assistant Registrar, Co-operative Societies, SRA, respondent No.3 is the Maharashtra Housing and Area Development Authority (hereinafter referred to as "MHADA"), respondent No.4 is Aman (Kurla) SRA Co-operative Housing Society (Proposed), respondent No. 5 is a firm of developers M/s. Dani Builders and Developers and respondent No. 6 is the Vinoba Bhavc Cooperative Housing Society (Proposed).
2. The petitioners have challenged a show cause-notice dated 7th June, 2010. an order dated 28th September, 2010 passed by the SRA and an order dated 21st May, 2011. passed by the High Power Committee (hereinafter referred to as "HPC"). By the order dated 28th September, 2010, passed under section 13(2) of the Maharashtra Slum Areas (Improvement, Clearance and Redevelopment) Act, 1971 , the SRA terminated the petitioners appointment as the developer and granted respondent No.4 - Aman (Kurla) SRA Cooperative Housing Society (hereinafter referred to as "the society'1), liberty to appoint a new developer by determining the expenses incurred by the petitioners for implementation of the scheme. The HPC, by the order dated 2 1 st May, 201 1, dismissed the petitioners' appeal against the order of the SRA dated 28th September, 2010.
3. On 23rd February, 2006, the petitioners had submitted a proposal for the implementation of a slum rehabilitation scheme, The competent authority issued Annexure-11 on 21st June, 2006. The scheme was approved on 20th May, 2009. The SRA, by a report dated 20th May, 2009, recommended approval to process the petitioners proposal. The approval of the letter of intent stated that 93 out of 105 i.e. 88.57 percent of the eligible slum dwellers had consented to the scheme by passing resolution for the implementation thereof. These eligible slum dwellers had formed respondent No.4 -Aman (Kurla) SRA Co-operative Housing Society (Proposed). The approval of the letter of intent also referred to an access to be provided. It referred to the Chief Promoter of the society having applied to MHADA for the right of access to the scheme plot from a proposed DP road and to allow the right of access for ten years on certain terms and conditions. Accordingly, the approval of the letter of intent recommended the petitioners scheme being approved subject to the condition that a lease agreement for a right of access should be insisted upon before development permission of the rehabilitation building. It was also recommended that a condition ought also to be incorporated in the draft letter of intent to obtain an extension for the lease beyond ten years after its expiry. Clause 19 of the approval of letter of intent stipulated that the premium would be recovered as per the office circular No.88 as the land belonged to MHADA,
4. Prima facie, there was, in the first instance itself therefore, considerable delay from the time when the petitioners submitted the proposal on 23rd February, 2006, to the approval of the letter of intent on 20th May, 2009. The petitioners explanation for this is that the Annexure-II was issued only on 14th August, -2006. Ms. Iyer, the learned senior counsel appearing on behalf of the petitioners relied upon a letter dated 15th May, 2008 to explain the delay in the payment of premium which was also expressly referred to in the approval of the letter of intent. It appears that the Deputy Engineer of the SRA had, by a letter dated 8th May, 2008, cal led upon the petitioners to pay the premium. The petitioners replied to the same by its letter dated 15th May, 2008. The petitioners agreed to the payment of the premium and requested SRA to inform them as to how the payment was to be released and whether it could be released in installments.
5. The mere issuance of the letter dated 15th May, 2008, would not indicate that there was no delay on the p
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.