SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2012 Supreme(Bom) 1307

HIGH COURT OF JUDICATURE AT BOMBAY
D.Y. CHANDRACHUD & R.D. DHANUKA, JJ.
Nusli Neville Wadia
Versus
Ferani Hotels Private Limited & Others
APPEAL NO.817 OF 2010 IN NOTICE OF MOTION NO.1863 OF 2008 IN SUIT NO.1628 OF 2008 WITH APPEAL NO.806 OF 2010
Decided On : 19-07-2012

Advocates Appeared:
For the Appellant:Abhishek Singhvi, Senior Advocate with Parag Tripathi, Senior Advocate, Zubin Behramkamdin, Vivek A. Vashi, Ms. Kanika Sharma, Abhimanyu Bhandari, Mike Desai, Kunal Bahri & Rook Ray i/b M/s. Bharucha & Partners, Advocates. For the Respondents:R1, F.S. Nariman, Senior Advocate with N.H. Seervai, Senior Advocate, R.M. Kadam, Senior Advocate, V.R. Dhond, Senior Advocate, Rohan Kelkar, Shrikant Doijode & Ms. Falguni Thakkar i/b Doijode Associates, R3, Vineet B. Naik i/b Mahimtura & Co., R5 & R6, Ms. Kashmira Bharucha i/b K.D. Abhichandani, R8, R9, R11, R14, R15, R17, R18, R23, R28, R29, R30, R34 to R37 & R49, Simil Purohit with Rahul Totala & Hiren G. Shah i/b Prakash & Co., R10, R13, R19 to R24 & R31, N.K. Mudnaney, R12, R16, R25, R26, R27, R38 to R48, S.U. Kamdar, Senior Advocate with Rajesh Vaidya i/b A.R. Vaidya & Co., R32 & R33, Ameya Malkan i/b Wadia Ghandy & Co., Advocates.

Headnote:

Section 9A of the Code of Civil Procedure, 1908 - Preliminary issue - Limitation - Maintainability of suit - Ad interim relief - Delay - Fraud - Genuine third party - Construction of agreement - Equities - Injunction - Accounts - Commissioner for recording evidence.

Fact of the Case:

Plaintiff, as administrator of the estate of E.F. Dinshaw, instituted a suit against Defendant Ferani Hotels Private Limited for a declaration that an agreement entered into between them stood vitiated by fraud and had been duly determined. Plaintiff sought consequential reliefs, including the revocation of powers of attorney executed in favor of Defendants and the demolition of constructions put up by Defendant. Plaintiff also sought an injunction restraining Defendant from carrying out further construction and damages. Defendant raised an objection to the maintainability of the suit on the ground that the claim was barred by limitation. The Learned Single Judge held that a preliminary issue under Section 9A would have to be raised and disposed of the Motion for interim relief.

Finding of the Court:

The Court held that Section 9A of the Code of Civil Procedure, 1908 mandates that when an objection on the ground of jurisdiction is raised, that must be addressed first before an application for interlocutory relief is finally disposed of. The Court also held that the Learned Single Judge was justified in raising the issue of limitation as a preliminary issue. However, the Court found that the Learned Single Judge erred in disposing of the Motion for interim relief finally without the issue of jurisdiction being resolved.

Issues: 1. Whether the objection as to jurisdiction could result in the complete disposal of the suit, in the event that it is upheld? 2. Whether the Trial Judge has the authority to consider as to whether the objection as to jurisdiction arises bonafide or whether it is wholly frivolous? 3. Whether an objection to jurisdiction may in a certain conceivable situation be to the jurisdiction of the Court to entertain the suit in its entirety? 4. Whether the Learned Single Judge was justified in raising the issue of limitation as a preliminary issue? 5. Whether the Learned Single Judge erred in disposing of the Motion for interim relief finally without the issue of jurisdiction being resolved?

Ratio Decidendi: 1. An objection to the jurisdiction of the Court must bear its natural and ordinary connotation which would mean an objection to the jurisdiction of a Court to entertain even a part of the cause of action raised in a suit. 2. The Trial Judge has the authority to consider as to whether the objection as to jurisdiction arises bonafide or whether it is wholly frivolous. 3. An objection to jurisdiction may in a certain conceivable situation be to the jurisdiction of the Court to entertain the suit in its entirety as for instance, where the Court lacks the jurisdiction to entertain the subject matter of the suit on the ground that properly construed the suit relates to the relationship of a lessor and lessee falling within the exclusive domain of the Small Causes Court in the city of Mumbai. 4. The Learned Single Judge was justified in raising the issue of limitation as a preliminary issue. 5. The Learned Single Judge erred in disposing of the Motion for interim relief finally without the issue of jurisdiction being resolved.

Final Decision: The Court allowed the appeal filed by Defendant and set aside the impugned order of the Learned Single Judge. The Court directed that the issue of limitation be tried as a preliminary issue. The Court also directed Defendant to maintain accounts and to continue depositing an amount equivalent to 12% of the gross sale consideration in a designated bank account. The Court appointed a Commissioner for recording evidence and requested the Learned Single Judge to endeavor an expeditious disposal of the preliminary issue.

JUDGMENT:

Dr. D.Y. Chandrachud, J.

These Appeals arise from a judgment dated 19 July 2010 of a Learned Single Judge on a Motion for interim relief in a suit. When an application for ad interim relief came up for hearing before the Learned Single Judge, an objection to the maintainability of the suit was raised on behalf of the First Defendant on the ground that the claim was barred by limitation. The Learned Single Judge was requested to raise a preliminary issue under Section 9A of the Code of Civil Procedure, 1908. The Learned Judge accepted the contention that an issue under Section 9A would have to be raised. The Court held that no case for the grant of ad interim relief, within the meaning of Section 9A(2) was made out on the ground of delay. However, the Learned Single Judge proceeded to dispose of the Motion for interim relief on the ground that since affidavits have been filed and parties were heard at length, it would not be appropriate or proper to have a hearing confined only to the disposal of the application for ad interim relief. Two appeals have been filed in these proceedings. The first appeal is by Mr. Nusli Neville Wadia, the Plaintiff; while the second appeal is by Ferani Hotels Private Limited, the First Defendant. The suit has been instituted by the Plaintiff in his capacity as the administrator of the estate of Late E.F. Dinshaw. For convenience of reference and since there are two appeals, it would be appropriate to refer to the parties as the administrator and Ferani. Reference to the other Defendants would be made appropriately, as and when necessary. \

2. The suit has been instituted, inter alia, to seek a declaration that an agreement entered into between the administrator and Ferani on 2 January 1995 stands vitiated by fraud and has been duly determined with effect from 12 May 2008. Consequential reliefs have also been claimed to the effect that the powers of attorney executed by the Plaintiff stand validly revoked and that certain agreements entered into between Ferani and the other Defendants, including among them agreements which date back to 2001, 2002, 2003, 2004 and 2005, have been validly revoked. An injunction has been sought, restraining Ferani from carrying out any further construction on the lands which form the subject matter of the suit and to demolish the constructions which have been put up. There is a claim for damages in the amount of Rs.1,370.06 Crores. The lands which form the subject matter of the dispute aggregate to about 350 acres and are situated principally in Malad.

3. On 2 January 1995 an agreement was entered into between the administrator (representing the estate of E.F. Dinshaw) and Ferani, under which Ferani undertook the development of the land and the sale of constructed areas thereon subject to certain terms and conditions. The agreement envisaged that Ferani would develop the land by constructing buildings thereon. The administrator was to grant, in favour of Ferani, a lease in respect of the land. Clause 8 of the agreement stipulated thus:

“8. The Development Project contemplated by this Agreement, is the following:-

(a) Sale, or transfer by any other format, by the Company to third parties (hereinafter referred to as “the Purchasers” or prospective purchasers or Unit holders / flat holders, as the case maybe) either on outright sale basis or on “ownership basis”, or otherwise, the different building/s to be so put up by the Company on the respective segments (being building/s belonging to the Company) and/or of the flats/ shops/offices and/or other portions of and/or Units in such buildings/s, so that ultimately the building/s that would be so constructed by the Company would be conveyed and transferred by the Company in favour of the respective purchaser/s or a Co-operative Society or Limited Company or a Condominium (as may be decided upon by the Company) to be formed of such prospective purchasers or Unit holders/ Flat holders/co-operative society or limited




















































































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top