2013 Supreme(Bom) 2333
High Court of Judicature at Bombay
ROSHAN DALVI, J.
Jawaharlal Nehru Port Trust
Versus
Afcons Infrastructure Ltd.
Arbitration Petition No. 494 of 2007 Alongwith Arbitration Petition No. 105 of 2008
Decided on : 27-11-2013
For the Petitioner:Pradeep Sancheti, Sr. Adv., a/w. Bhalerao, a/w. Ms. Hemali Kurne, a/w. Darshit Jain, Adv. i/b. Vyas & Bhalwal, Advocates.
For the Respondent:Chirag Balsara, a/w. Dhiraj Mhetra, i/b. Desai & Diwanji, Advocates.
The main legal point established in the judgment is that claims exceeding the contractual limits are not permissible, and interest grant is in accordance with statutory provisions.
Headnote:
Arbitration and Conciliation Act, 1996 - Setting Aside Award - Contracts for Construction of Port Craft Berth - Rajasthan State Mines & Minerals Ltd. Vs. Eastern Engineering Enterprises & Anr., AIR 1999 Supreme Court 3627 - Claims for Boring, Guide Wall Construction, Extra Rate for Diaphragm Wall, Core Drilling, and Steel Cost - Interest Grant
Fact of the Case:
The case involves two petitions filed under Section 34 of the Arbitration and Conciliation Act, 1996, seeking to set aside an award related to contracts for the construction of the extension of Port Craft Berth. The contracts included clauses for dispute resolution through arbitration. The disputes raised for the execution of the work until its completion were referred to arbitration, and the award was challenged on the grounds of exceeding the jurisdiction and rewriting the contract terms.
Finding of the Court:
The court found that the arbitrators correctly considered the claims related to boring, guide wall construction, extra rate for diaphragm wall, core drilling, and steel cost. However, the court set aside the award for claims related to extra rate for diaphragm wall and core drilling as they exceeded the contractual limits. The court confirmed the interest granted under the awards.
Issues: The issues involved the interpretation of contract clauses, determination of claim entitlement, and the legality of interest grant.
Ratio Decidendi: The court held that claims exceeding the contractual limits were not permissible and set aside the corresponding award. The court confirmed the interest grant as per the statutory provisions.
Final Decision: The court confirmed and maintained the awards, except for claims related to extra rate for diaphragm wall and core drilling. The interest granted under the awards was also confirmed.
1. These two Petitions are filed U/s.34 of the Arbitration and Conciliation Act, 1996 for setting aside the award dated 17th September, 2007 under two contracts entered by and between the parties for construction of the extension of Port Craft Berth at the B premises of the Petitioner.
2. Both contracts are contained in the letter of the Petitioner dated 25th February, 1999, 1st March, 1999 and the tender submitted by the Respondent dated 15th March, 1999 and 17th March, 1999 and further correspondence between the parties as set out in the letter of the Petitioner dated 1st September, 1999.
3. Under clause 17 of the contract between the parties they agreed to refer their dispute to two arbitrators, one to be nominated by each of them and the third to be nominated by the arbitrators. Under the arbitration clause the parties agreed that only the questions and disputes raised for the execution of the work until its completion would be referred to arbitration. The disputes arising thereafter would not be referred to arbitration except those relating to maintenance of the construction during the maintenance period. The disputes having arisen, an arbitration has been invoked and undertaken. The award is challenged essentially upon the ground that it travels beyond the contract between the parties.
4. In that regard the Court would be bound and completely governed by the law laid down in the case of Rajasthan State Mines & Minerals Ltd. Vs. Eastern Engineering Enterprises & Anr., AIR 1999 Supreme Court 3627.
5. The parties have referred to various clauses of the contract in paragraph 1 contained in part II with regard to claims of the Respondent herein which have been granted and the grant of which has been challenged.
6. It need not be even be mentioned that this Court, which is not an appellate Court, cannot go into the intrinsic calculations of the various specified amounts so granted. The main aspect to be seen is whether the arbitrators have exceeded the jurisdiction in going beyond the terms of the contract such as to rewrite the contract between the parties. Consequently it will be appropriate to take up the contentions of all the parties with regard to the grant of each of the claims and the challenge to each of the grants to determine the extent of the exercise of jurisdiction by the arbitrators.
7. Claim No.1 :
This relates to payment for boring in diaphragm wall from RL + 6.8 meters (m) to 5.125 m at which level the diaphragm wall begins as shown in the claim diagram relied upon by the Petitioner.
8. Under clause 4.1.20 of the tender specification the boring was to be in clay, mud, boulders, gravel, but not basalt which was separately considered.
9. The Petitioner has explained by diagram how the boring in the diaphragm wall was to be done by the Respondent. There are guide walls on the either side of a berth. The Respondent was to construct guide wall and diaphragm wall. The boring of the diaphragm is specified in clause 4.9 of the contract. It would be from the level + 5.125 m. It is contended by the Petitioner that the Respondent could not claim the expenses of boring wall from any higher level. Under clause 4.9A the measurement for boring was to be downward from the level where the boring was to encounter the soil. Under clause 4.9 B the concrete used for this purpose would be the actual consumption being under, as shown in the drawings and ordered by the Engineer-in-charge of the Petitioner. Under that clause it was agreed that the construction actually consumed up to the limit of theoretical volume shown in the drawings would be paid. Hence it is argued that it would be actual consumption until the limit of the height of digging is reached. This is admittedly paid.
10. Bill of Quantity (BOQ) in the contract under clause 4b shows the quantity of the boring required. This would be boring into weathered basalt rock or sand but not basalt. The quantity agreed between the parties for such boring was 2280. It is