SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2013 Supreme(Bom) 2201

High Court of Judicature at Bombay
A.P. BHANGALE, J.
Noor Mohd. Shami Shaikh & Another
Versus
Maharashtra Housing & Development Board & Others
First Appeal No.302 of 2013 With First Appeal No.303 of 2013 With Civil Application No.1031 of 2013
Decided On : 25-10-2013

Advocates Appeared:
For the Appellants:Y.E. Mooman i/b. Manisha Gawde, Advocates.
For the Respondents:R2, Mrs. Geeta Joglekar, R4, Y.S. Naidu, Advocates.

The main legal point established in the judgment is that the mandatory provisions for pre-suit statutory notices, as required under the relevant acts, serve a public purpose and must be faithfully implemented, and their absence can lead to the rejection of the plaint.

Headnote:

Pre-suit Statutory Notices - Rejection of Plaint - Mumbai Municipal Corporation Act, 1888, Section 527; Maharashtra Co-operative Societies Act, 1960, Section 164

Fact of the Case:

The plaintiffs sought relief for the enforcement of statutory obligations against the Municipal Corporation of Greater Mumbai (MCGM) and a Co-operative Society. The court held that the plaint was bound to be rejected under Order 11 Rule 7(d) of the Code of Civil Procedure due to the failure to issue pre-suit statutory notices as mandatorily required under Section 527 of Mumbai Municipal Corporation Act, 1888, and Section 164 of the Maharashtra Co-operative Societies Act, 1960.

Finding of the Court:

The court found that the pre-suit statutory notices were mandatory and their absence led to the rejection of the plaint. The court also emphasized that the rejection of the plaint did not preclude the plaintiffs from presenting a fresh plaint after complying with the mandatory requirements.

Issues: The main issue was whether the failure to issue pre-suit statutory notices as required under the relevant acts warranted the rejection of the plaint.

Ratio Decidendi: The court held that the mandatory provisions for pre-suit statutory notices served a public purpose by providing public authorities with an opportunity to avoid unnecessary litigation and expenses. The court emphasized that the statutory requirement of notice cannot be waived by contract and must be faithfully implemented as intended by the legislature.

Final Decision: The appeals were dismissed, and the rejection of the plaint was upheld. The court also noted that the plaintiffs could present a fresh plaint after complying with the mandatory requirements.

JUDGMENT :

1. These appeals are directed against common order dated 6.2.2013 passed by learned City Civil Judge, Mumbai, in Chamber Summons No.784 of 2011 and Chamber Summons No.1317 of 2012 in L.C.Suit No.2145 of 2009, whereby, learned Judge held that the plaint in L.C.Suit No.2145 of 2009 is bound to be rejected under Order 11 Rule 7(d) of the Code of Civil Procedure on the ground that pre-suit statutory notices as mandatorily required under Section 527 of Mumbai Municipal Corporation Act, 1888, and as required under Section 164 of the Maharashtra Co-operative Societies Act, 1960, as required according to law, were not issued and served upon the Public Authorities namely Municipal Corporation of Greater Mumbai (MCGM) and Registrar of the Co-operative Societies.

2. It appears that the plaint in the L.C.Suit No.2145 of 2009 contained averments in respect of Development Control Regulations issued by the Planning Authority i.e. MCGM. According to plaintiffs, Maharashtra Housing and Area Development Authority (MHADA) is a body responsible for development of housing. According to plaintiff, defendant no.2 MCGM is owner of plot of land bearing C.T.Survey No. 1589, Byculla Division, while M/s.NAN Developers Pvt. Ltd. (defendant no.3) is a Developer and Builder, who undertook development work on the said plot of land. The plaintiff claimed possession of Room No.16, “C” Block in Afzal Chawl, Opposite Maratha Mandir, Dr.A.B.Nair Road, Mumbai Central, Mumbai – 400 008. According to plaintiffs, tenants and occupants of Afzal Chawl situated on the City Survey No.1589 of Byculla Division decided to go for redevelopment under the scheme formulated under Development Control Regulations, and therefore, association of the occupants in the chawl had called a General Body Meeting on 24.12.2001, to discuss the benefit of redevelopment. Defendant no.3 was appointed as developer to pursue redevelopment work. Tenants and occupants of Afzal chawl consented in favour of defendant no.3 and the consent was forwarded to MCGM and other authorities concerned for necessary approval and sanction. Plaintiffs and defendant no.3 had entered into an agreement with the proposed Afzal Co-operative Housing Society under Agreement dated 27.9.2006, and agreed to complete the construction. To facilitate redevelopment, defendant no.3 agreed to provide temporary transit accommodation of 110 to 120 sq.feet on the same plot or in the same area and agreed to bear all the expenses. Meeting was held in September 2006 between committee members and defendant no.3 regarding the approval of redevelopment scheme and the plan to take benefit of Regulation 33(a) of the Development Control Rules. Defendant no.3 agreed to provide larger area and more benefits to tenants / occupants of the chawl. The builder had agreed for compensation / rent to enable the plaintiffs to make arrangements for temporary transit accommodation. Thus, plaintiffs have agreed to participate in redevelopment of Afzal chawl through defendant no.3 and also agreed to shift to the alternate transit accommodation as defendant no.3 was to pay rent for transit accommodation before he could hand over permanent accommodation for the plaintiffs.

3. It is case of the plaintiffs that two buildings “A” and “B” Wings of ground plus seven storeys for rehabilitation were constructed, but occupation certificate was not obtained by defendant no.3. Under these circumstances, tenants and occupants of Afzal chawl had forcibly taken possession of different rooms of their choice without following the procedure of lottery as agreed. Defendant no.3 paid compensation towards rent for transit accommodation till 31.3.2009. Thus, according to plaintiffs, after entire development, plaintiffs were entitled to minimum area of 27.88 sq.mts. (300 sq.feet carpet) in the newly constructed building as permanent alternate accommodation in lieu of their old premises under Rule 4 of Appendix IIIA. According to plaintiffs, it was obligatory upon san

































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top