2013 Supreme(Bom) 2536

HIGH COURT OF JUDICATURE AT BOMBAY
R.D. DHANUKA, J.

L & T Finance Limited
Versus
Damodar Bandekar (Borrower) & Another
Arbitration Petition No.529 of 2013
Decided on: 18-12-2013

Important Points

The main legal point established in the judgment is the court's authority to appoint a Court Receiver under section 9 of the Arbitration and Conciliation Act, 1996, to secure the claim in cases of default and the obligation of the parties to pay stamp duty on relevant documents.

Subject

Arbitration Law - Interim Measures

Act Referred

ARBITRATION AND CONCILIATION ACT : S.9
BOMBAY STAMP ACT : Art.5(g)(a), S.33(1)
CIVIL PROCEDURE CODE : O.40 R.1
STAMP ACT : S.35, S.33, S.38, S.40

Headnote

Arbitration and Conciliation Act - Interim Measures - 1996 - Clause 12 and 13 of the loan agreement provides for events of default and consequences in the event of default. The judgment of Supreme Court in SMS Tea Estates Pvt. Ltd. vs. Chandmari Tea Co. Pvt. Ltd. and the unreported judgment of the Division Bench of the court in case of Lakdawala Developers Pvt. Ltd. vs. Badal Mittal & Others were discussed in relation to the stamp duty on the loan agreement and deed of guarantee. The court held that the documents executed out of Maharashtra and stamp duty already paid in that state can be relied upon in proceedings under section 9. The court also discussed the jurisdiction issue and the requirement for appointment of a Court Receiver under section 9 of the Arbitration and Conciliation Act, 1996.

Fact of the Case:

The petitioner sought interim measures under section 9 of the Arbitration and Conciliation Act, 1996, due to default in loan repayment by the respondents. The petitioner invoked the arbitration agreement and appointed an arbitrator. The respondents did not respond to the demand notice and did not file an affidavit in reply.

Finding of the Court:

The court found that the respondents had committed default in making repayment, and their whereabouts and the condition of the hypothecated assets were unknown. The court held that the petitioner had good chances of succeeding in arbitration and thus appointed a Court Receiver to secure the claim.

Issues: The issues included the default in loan repayment, stamp duty on the loan agreement and deed of guarantee, and the jurisdiction of the court to entertain the petition.

Ratio Decidendi: The court's decision was based on the default committed by the respondents, the obligation of the respondents to pay stamp duty, and the jurisdiction of the court to entertain the petition under section 9 of the Arbitration and Conciliation Act, 1996.

Final Decision: The court appointed the Court Receiver to secure the claim and issued directions for the enforcement of the order.

Advocate Appeared
For the Petitioner:Anand Poojari, a/w. Nilesh Gala, Ankit Shah, i/b. M/s S.I. Joshi & Co., Advocates.
For the Respondents:Rohan Sawant, a/w. Nikhil Rajani, i/b. V.Deshpande & Co., Advocates.

JUDGMENT

P.C.

By this petition filed under section 9 of the Arbitration and Conciliation Act, 1996, petitioner seeks interim measures. Some of the relevant facts for the purpose of deciding this petition are as under:-

2. On 5th October, 2011, petitioner and respondent no.1 entered into a loan cum hypothecation agreement by which petitioner sanctioned loan to the tune of Rs.70,52,000/- to the 1st respondent. Respondent executed demand promissory note in favour of the petitioner. Respondent no.2 executed deed of guarantee on 5th October, 2011.

3. It is the case of the petitioner that since the respondent committed default in making repayment of installments, petitioner issued demand cum termination notice on 21st January, 2013 and called upon the respondents to pay a sum of Rs.72,34,403/- outstanding as on 4th December, 2012 with further overdue compensation @ 36 % per annum from 5th December, 2012. There was no response to the said notice of demand. Petitioner invoked arbitration agreement and has appointed an arbitrator.

4. Learned counsel appearing for the petitioner invited my attention to the loan cum termination agreement and also deed of guarantee. Clause 12 of the loan agreement provides for events of default. If the borrower fails to pay the loan installments, interest and all other monies payable or part thereof within the stipulated time whether demanded or not or any other charge or payment required thereunder within 7 days of their becoming dues, it would amount to an event of default.

5. Clause 13 of the loan agreement provides for consequences in the event of default. It is provided that on the occurrence of any of the events specified in clause 12, without any notice to the borrower, the lender shall have right to terminate the loan agreement, recover from the borrower the arrears of moneys due and unpaid on the date of termination and such other future installments for the unexpired period, had the said agreement continued, initiate legal action as available under the applicable laws, repossess, sell or otherwise dispose off/deploy the assets in such manner, as the lender may think fit. Under clause 14 of the said agreement, lender is also entitled to repossess of the assets.

6. Learned counsel submits that since respondents have committed default in making repayment, there was no response to the notice of the demand and since respondents have not filed any affidavit in reply, averments made in the petition are deemed to have been admitted. It is submitted that whereabouts and the condition of the assets hypothecated is not known. Learned counsel submits that the petitioner have good chances of succeeding in the arbitration and thus claim of the petitioner is required to be protected and this court shall be appoint as Court Receiver under section 9 of the Arbitration and Conciliation Act, 1996.

7. Learned counsel appearing for the respondents on the other hand submits that the loan cum hypothecation agreement and deed of guarantee are required to be stamped at the rate prescribed under the provisions of Maharashtra Stamp Act whereas both these documents are stamped at Rs.100/- and thus both these documents are inadmissible in evidence and this court thus cannot appoint receiver or grant any interim measures.

8. Learned counsel in support of his submission placed reliance on the judgment of Supreme Court in case of SMS Tea Estates Pvt. Ltd. vs. Chandmari Tea Co. Pvt. Ltd. reported in 2011 (4) Arb.LR 265 (SC) and in particular paragraph (12) thereof which reads thus:-

12. We may therefore sum up the procedure to be adopted where the arbitration clause is contained in a document which is not registered (but compulsorily registrable) and which is not duly stamped:

(i) The court should, before admitting any document into evidence or acting upon such document, examine whether the instrument/document is duly stamped and whether it is an instrument which is compulsorily registrable.

(ii) If the document is found to be not duly sta


































1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top