2014 Supreme(Bom) 1421

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ROSHAN DALVI, J.
Dharti Dredging & Infrastructure Ltd. - Petitioner
Vs.
Credence Logistics Ltd. - Respondent
ARBITRATION PETITION NO. 458 OF 2014
Decided on: 18th JULY, 2014

Important Points

The court emphasized the importance of upholding the terms of the contract, including the liability for payment and the limitation period for filing a counterclaim.

Subject

Arbitration Law - Contract Termination and Liability

Act Referred

CONTRACT ACT : S.55, Cl.23
LIMITATION ACT : Art.55

Headnote

Arbitration - Termination of Contract - Clause 5, Clause 12, Clause 23 - The Arbitrator granted hire charges, transportation charges, operational loss, and costs of accessories to the respondent. The counterclaim of the petitioner was dismissed as being barred by limitation.

Fact of the Case:

The petitioner challenged the money award granting 4 claims of the respondent in the arbitration. The parties entered into an agreement for the use of a dredger, and the contract was terminated prematurely by the respondent. The petitioner failed to return the dredger and did not pay hire charges during the period it kept the dredger after the termination.

Finding of the Court:

The court found that the termination of the contract was not premature as the petitioner defaulted in the payment of hire charges. The court upheld the Arbitrator's decision to grant hire charges, transportation charges, operational loss, and costs of accessories to the respondent. The counterclaim of the petitioner was dismissed as being barred by limitation.

Issues: Premature Termination, Default in Payment of Hire Charges, Liability for Transportation Costs, Operational Loss, Costs of Accessories, Limitation Period for Counterclaim

Ratio Decidendi: The termination of the contract was not premature as the petitioner defaulted in the payment of hire charges. The petitioner was liable for transportation costs as per the contract. The respondent was entitled to claim operational loss and costs of accessories as per the terms of the agreement. The counterclaim was dismissed as being barred by limitation.

Final Decision: The court upheld the Arbitrator's decision to grant hire charges, transportation charges, operational loss, and costs of accessories to the respondent. The counterclaim of the petitioner was dismissed as being barred by limitation.

Advocates:
Advocate Appeared
Mr. Mayur Khandeparkar a/w. Ms. Sneha Patil i/b K K Associates for the Petitioner.
Mr. S. M. Khaire a/w. Ms. Sheetal M. Nadkarni & Mr. M. Y. Joshi for the Respondent.

ORDER

1. The petitioner has challenged the money award dated 14th October, 2013 granting 4 claims of the respondent in the arbitration before the learned Arbitrator.

2. The parties entered into an agreement under which the petitioner herein was to use a dredger of the respondent herein for a period of 2 years from 1st November, 2006. At the time of the agreement, the dredger was already in the possession of the petitioner herein. Under the agreement the petitioner was to pay hire charges of net amount excluding the cost of operation, repairs, maintenance and renewal of spares, taxes and levies incurred by the petitioner herein to maintain the dredger in the same condition as on the date of the commencement of the hire of the dredger.

3. Under Clause 5 of the agreement on the expiration of the agreement on its termination the petitioner was to deliver back the dredger within 60 days of the expiry or the termination at his own costs at the place specified in the agreement in the same condition as on the date of commencement of hire including of the spare parts and tools provided with the dredger.

4. Under Clause 5 itself the petitioner was to obtain a certificate of an independent surveyor about the condition of the dredger and if the surveyor certified that certain repairs, renewal or replacement of the spares and machinery was required to put the dredger in working condition than the petitioner was to bear the costs of repairs, renewal or replacement.

5. Under Clause 12 of the agreement if there was any improvement of the dredger for its better and more efficient operation, it was to be discussed by the petitioner with the respondent to decide the sharing of costs and the consequent enhancement of the hire charges. Such improvement was to be effected after obtaining written approval from the respondent herein.

6. Under Clause 23 of the Contract the respondent was not to be liable for any defects in the dredger and it was recorded that the petitioner took inspection and was satisfied itself about its condition.

7. Consequently the condition of the dredger was stated to be satisfactory on the date of the agreement. The petitioner was to pay the hire charges agreed. If the petitioner required to make any repairs it may make at his own costs. If there was any improvement it had to be with the approval of the respondent. This would inter alia entail enhancement of hire charges. The petitioner agreed that the condition was satisfactory. Hence if the condition of the part of the dredger was not satisfactory or required repairs or improvement it was for the petitioner to make repairs or the improvements and the respondent was not liable for any defects in the dredger.

8. An inspection of the dredger was carried out prior to and after the agreement was entered into by the parties. A statement of stock of inventory of the dredger was initially made on 21st June, 2006. It showed that certain accessories at item Nos.99 to 102 were corroded and damaged. After the agreement was entered into another inspection was done on the statement of stock of inventory of the dredger on 18.11.2006 when the same condition has been reported for item Nos.99 to 102 which are some of the accessories. Consequently as per the terms of the contract the petitioner would be required to carry out the repairs, renewal or replacement keeping in mind that the petitioner was satisfied with the condition of the dredger and the respondent was not liable for the defects in the dredger. The dredger was, therefore, to be returned in good working conditions at the time of the expiration of the contract or upon its termination.

9. The contract was terminated by the respondent before the expiry of the contract. The notice of termination is shown to be dated 10th March, 2008. It is sent by email referring to the contract dated 27th October, 2006 which commenced from 1st November, 2006. During the period when the contract was in force, the petitioner herein is stated to have paid