2015 Supreme(Bom) 55

IN THE HIGH COURT OF BOMBAY AT AURANGABAD
A.I.S. CHEEMA, J.
M/s Ambarwadikar & Co. – Appellant
Versus
The State of Maharashtra & Ors. – Respondents
Appeal From Order Nos. 82 of 2014, 86 of 2014 with Civil Application Nos. 9683 of 2014, 9855 of 2014
Decided on: 22-01-2015

Important Points

The main legal point established in the judgment is that the transferee court, even if lacking territorial jurisdiction, can dispose of the suit and cannot return the plaint based on territorial jurisdiction.

Subject

Civil Law - Jurisdiction

Act Referred

CIVIL PROCEDURE CODE : S.24, O.7 R.10, S.20, S.24(1)(a), S.24(1)(b)

Headnote

Jurisdiction - Territorial Jurisdiction - Code of Civil Procedure, 1908 - Section 24 - Special Civil Suit No.18/2012, Special Civil Suit No.23/2012 - [Section 24 of CPC] - The court discussed the territorial jurisdiction under Section 24 of the CPC and the implications of transferring suits to a competent court. The court emphasized that the transferee court, even if lacking territorial jurisdiction, can dispose of the suit and cannot return the plaint based on territorial jurisdiction. The court highlighted the importance of following the orders passed for simultaneous hearing and disposal of suits and recording common evidence.

Fact of the Case:

The appellant challenged the orders directing the return of the plaints to be filed in a different court due to lack of territorial jurisdiction. The appellant argued that despite previous orders for simultaneous hearing and disposal of suits and recording common evidence, the impugned orders were passed.

Finding of the Court:

The court found that the impugned orders were not maintainable and illegal, as they violated the orders for simultaneous hearing and disposal of suits and recording common evidence.

Issues: The issues revolved around the territorial jurisdiction of the court, the implications of previous orders for simultaneous hearing and disposal of suits, and the legality of the impugned orders.

Ratio Decidendi: The court emphasized that the transferee court, even if lacking territorial jurisdiction, can dispose of the suit and cannot return the plaint based on territorial jurisdiction. The court highlighted the importance of following the orders passed for simultaneous hearing and disposal of suits and recording common evidence.

Final Decision: The appeals were allowed, and the impugned orders were quashed and set aside.

Advocates:
Advocate Appeared
For the Appellant:A.K. Gawali, Advocate.
For the Respondents:R1, S.D. Shelke, A.G.P., R2, S.G. Bhalerao, Advocate.

JUDGMENT

1. These appeals were admitted and taken up for final hearing on 13th January 2015. Both the appeals are between same parties.

2. Appellant (original plaintiff) in Appeal from Order No.82/2014 is challenging the order dated 7.8.2014, passed by Civil Judge, Senior Division, Latur, below Exhibit 35 in Special Civil Suit No.18/2012, thereby holding that Latur Court does not have territorial jurisdiction to entertain the Special Civil Suit No.18/2012 filed by the appellant and directing that the plaint should be returned to be filed in proper and competent Court at Nilanga, District Latur.

3. In Appeal from Order No.86/2014, same appellant-plaintiff has filed Appeal from Order, challenging the order dated 20.8.2014, passed by Civil Judge, Senior Division, Latur below Exhibit 29 in Special Civil Suit No.23/2012, thereby holding that Latur Court does not have territorial jurisdiction to entertain the suit and directing that the plaint should be returned for being filed to the proper and competent Court at Nilanga, District Latur.

4. Special Civil Suit No.18/2012 relates to contract which was awarded to the plaintiff for Balance Earth Work C.C. Lining and Structures in K.M. 18 to 22 by virtue of agreement No.B-1/6 of 1988-89. He was also awarded such work with reference to K.M. 23 to 28 under agreement N.B-1/7 of 1988-89. These works related to Lower Terna Left Bank Canal Special Civil Suit No.23/2012 related to contract of Balance Earth Work C.C. Lining and Structures in K.M. 22 to 25 as per Agreement No.B-1/3 of 1988-89 of Lower Terna Right Bank Canal.

5. According to the appellant, respondents filed Special Civil Suit No.32/2001 for recovery of Rs.73,74,054/- against appellant regarding loss incurred for getting unexecuted work done with reference to works which are subject matter of Special Civil Suit No.18/2012. That suit is pending before Civil Judge, Senior Division, Latur as the contract was entered at Latur. As per the appellant, after rejection of its claim before Principal Secretary, Irrigation Department, the Special Civil Suit No.18/2012 came to be filed. Similarly, Special Civil Suit No.23/2012 came to be filed regarding the works of Lower Terna Right Bank Canal.

According to the appellant, under Section 24 of the Code of Civil Procedure, 1908 (C.P.C. in brief), the MARJE No.60/2012 was filed by the appellant – original plaintiff for transfer and joint trial of Special Civil Suit No.32/2001, Special Civil Suit No.23/2012 and Special Civil Suit No.18/2012 as at that time they were pending before different Civil Judges, Senior Division at Latur. It was claimed that, Special Civil Suit No.23/2012 related to agreement of Lower Terna Right Bank Canal, Special Civil Suit No.18/2012 related to agreement of Lower Terna Left Bank Canal and that Special Civil Suit No.32/2001 was in respect of work done in view of the above mentioned tenders. Claim was made that, issues in both the suits were in respect of same nature of dispute and evidence required to be adduced would be similar in all the three suits and witnesses would also be the same and so, all the three suits should be clubbed and heard jointly. Principal District Judge, Latur, vide orders dated 23.6.2012, withdrew Special Civil Suit No.32/2001 from Extra Jt. Civil Judge, Senior Division, Latur and Special Civil Suit No.18/2012 from 3rd Jt. Civil Judge, Senior Division, Latur and transferred them to the Court of Principal Civil Judge, Senior Division, Latur, where Special Civil Suit No.23/2012 was pending “for the simultaneous hearing and disposal of the three suits”. It is pointed out by the appellant that, the appellant had filed Writ Petition No.935/2013 before the High Court and High Court had, vide orders dated 6.3.2013, directed that, in Special Civil Suit No.32/2001 and Special Civil Suit No.18/2012, parties shall lead common evidence and trial Court may consolidate the issues of both the suits.

6. Grievance of appellant is that, in spite of these orders of the Pr