2015 Supreme(Bom) 693
HIGH COURT OF JUDICATURE AT BOMBAY
ROSHAN DALVI, J.
Swarup Group of Industries & Others – Appellant
Versus
Swarup Group of Industries & Another – Respondent
Chamber Summons (L) No. 875 of 2014, 236 of 2015, 492 of 2015 In Execution Application No. 581 of 2010
Decided On : 30-04-2015
Important Points
Subject
Arbitration Law - Challenge to Execution
Act Referred
Headnote
Arbitration Award - Challenge to Execution - Arbitration and Conciliation Act, 1996 (Sections 34, 36) - The court dismissed the chamber summonses seeking to stay the execution of an interim award and final award, as the challenge to the interim award was made after the statutory period of limitation and the execution had already commenced. The court held that under Section 36 of the Act, an award must be enforced if not challenged within the specified time, and the mere filing of a challenge does not automatically stay the execution.
Fact of the Case:
The defendants sought to stay the execution of an interim award and final award, challenging them after the statutory period of limitation had expired and the execution had commenced. The court dismissed the chamber summonses seeking to stay the execution.
Finding of the Court:
The court found that the challenge to the interim award was made after the statutory period of limitation and the execution had already commenced, therefore the execution must proceed.
Issues: The main issue was whether the challenge to the interim award, made after the statutory period of limitation and after the execution had commenced, should automatically stay the execution.
Ratio Decidendi: The court held that under Section 36 of the Arbitration and Conciliation Act, an award must be enforced if not challenged within the specified time, and the mere filing of a challenge does not automatically stay the execution.
Final Decision: The court dismissed the chamber summonses seeking to stay the execution and ordered that the execution must proceed.
For the Applicants:Y.K. Tiwari a/w. Shashipal Shankar for Judgment Creditor, Dinyar Madon, Sr. Advocate a/w. Ashish Mehta, Trishla Yelve, Nikhil Mallelwar i/b. Ashish Mehta, Advocates.
For the Interveners:Cherag Balsara a/w. Parimal K. Shroff, D.V. Deokar, Pinakin Modi, Subodh Joshi, Salim Sayed i/b. Salim Sayed, Advocates.
1. The above chamber summonses have been taken out by the award debtors (defendants) in the suit essentially for staying the execution of the above award which is an interim award passed by consent of the parties and for other ancillary reliefs.
2. The interim award was passed on 3rd December, 2008.
3. The above execution application has been taken out in this Court on 16th July, 2009 since the consent award (which could not be challenged) was not challenged.
4. Another application was also taken out for raising the attachment levied in the above execution proceeding and an order has been passed to facilitate and direct execution of the above interim consent award.
5. The attachment sought to be raised, was not raised (except on one unit with which the parties have no dispute).
6. Since the attachment was not raised, it continued and would culminate into sale of the attached properties, both movable and immovable. The execution would accordingly proceed.
7. Thereafter the final award came to be passed on 31st December 2013. That final award has been challenged on 31st March, 2014. Such challenge would be within the statutory period of limitation under Section 34(3) of the Arbitration and Conciliation Act, 1996 (the Act).
8. However the challenge is stated to be not only to the final award, but also to the interim award passed 6 years before on 3rd December 2008. Accordingly the Interim Consent Award is now stated to be challenged after it was accepted by the parties and after execution had proceeded and was not challenged by the award debtor.
9. The petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 was to challenge the interim consent award passed 8 years prior to such challenge and the final award passed 3 months prior thereto.
10. The petition under Section 34 of the Act was filed in the High Court in Delhi after the execution thus proceeded and the aforesaid applications were made by both the award holder and the award debtor in this Court. The filing of the petition for challenging the award in the Court at Delhi is in a Court without jurisdiction. Under Section 42 of the Arbitration and Conciliation Act, 1996 an application challenging the award after the execution of the award has commenced would have to be made as a subsequent application arising out of arbitral proceedings only in the Court in which the execution application is made and in no other Court (See in the case of State of West Bengal & Ors. Vs. Associated Contractors (2015) 1 SCC 32). Consequently the order of the Delhi High Court be it only an order of the admission of the petition, is without jurisdiction.
11. The challenge came to be admitted by that Court on 5th February, 2015. It has been kept for hearing on 25th August, 2015 under the order dated 5th February 2015. The order of the Delhi High Court does not show that it was present to the mind of the Court that the interim consent award has been passed 6 years prior thereto. No reasons for admitting are shown. The order only shows that the plaintiff was represented in “the previous hearings”.
12. On which date there were previous hearings is not shown by the award debtor / applicant herein.
13. It is argued by Mr. Madon that the award debtor was heard in 2014 (it is not known on which date) and that the petition was kept for hearing of the plaintiff/award holder on 11th July 2014. It is 7 months after such hearing / hearings that the petition came to be admitted as aforesaid and the hearing date is given after another 7 months.
14. Pending such challenge the above chamber summons have been taken out by the award debtor. The earliest of the chamber summonses is the above chamber summons No. 875 of 2014 filed on 16th June 2014 followed by chamber summons No.236 of 2015 filed on 9th February, 2015 and chamber summons No.492 of 2015 filed on 4th April 2015 for essentially the same reliefs of stalling and staying the execution.
15. In the first of the aforesaid chamber summons an a