HIGH COURT OF JUDICATURE AT BOMBAY
R.D. DHANUKA, J.
Union of India, Through Dy. Chief Engineer (Con)/ Works – Petitioner
Versus
M/s. Vinay Agarwal – Respondent
Arbitration Petition No. 922 of 2012
Decided On : 06-05-2015
Arbitration - Award - Challenge - Grounds - Contractual Prohibition - Interest - Price Escalation - Material at Site - Arbitrator's Jurisdiction - Public Policy.
Fact of the Case:
Petitioner challenged the majority award dated 14th September, 2010 rendered by the arbitral tribunal thereby allowing five claims made by the respondents and rejecting the counter claims made by the petitioner. The petitioner had also made counter claims in the arbitral proceedings. The respondent had claimed a sum of Rs.13,12,974/- towards increase in cost of petroleum products and spare parts which was allowed by the learned arbitrators at Rs.13,12,974/-. The petitioner submitted that under clause 17 of the General Condition of Contract, 1956 even if there was any delay on the part of the petitioner in handing over to the contractor the possession of the lands necessary for execution of the work or for various other reasons mentioned therein or any other cause whatsoever, it would not affect or vitiate the contract or entitle the contractor to the damages or compensation therein but the petitioner could grant only extension of the completion date. The respondent had stopped the work w.e.f. 1st June, 2000 and had removed all men, materials, machinery and labour camp etc. from the site of work and had failed to resume the work. There was no material lying at the site belonging to the respondent. The learned arbitrators have allowed the said claim applying a thumb rule by allowing 60% of the claim. The learned arbitrators have awarded simple interest at the rate of 12% per annum from 3rd November, 2001.
Finding of the Court:
The court held that the impugned award insofar as claim no.5 i.e. 'increase in cost of petroleum products and spare parts' is concerned, the respondent had originally claimed a sum of Rs.13,12,974/- and revised the said claim before the learned arbitrators at Rs.13,18,293.44. The learned arbitrators have allowed the said claim at Rs.13,12,974/-. The court found that under clause 17(3) of the General Conditions of Contract, in the event of any failure or delay by the Railway to hand over to the Contractor possession of the lands necessary for the execution of the works or to give the necessary notice to commence the works or to provide the necessary drawings or instructions or any other delay caused by the Railway due to any other cause whatsoever, then such failure or delay shall in no way affect or vitiate the contract or alter the character thereof or entitle the Contractor to damages or compensation therefor but in any such case, the Railway may grant such extention or extentions of the completion date as may be considered reasonable. The court held that the learned arbitrators have exceeded their jurisdiction by allowing the said claim contrary to the said clause of the contract. The court also held that the impugned award insofar as claim no.7 i.e. for the 'cost of material at site' is concerned, the respondent had claimed 5,87,637/-. The learned arbitrators have allowed the said claim at Rs.2,30,520/-. The court found that the learned arbitrators have allowed the said claim based on no evidence and has applied the thumb rule by taking a imaginary figure of 60% of the claim and has awarded a sum of Rs.2,30,520/- without any basis, which is not permissible. The court also held that the impugned award insofar as claim no.13 i.e. claim for interest is concerned, in the majority award, the learned arbitrators have allowed simple interest at the rate of 12% per annum from 3rd November, 2001. The court found that though the learned arbitrators have referred to clause 16(2) of the General Conditions of Contract, however have allowed the said claim contrary to the said clause 16(2) of the General Conditions of Contract.
Issues: Whether the arbitral tribunal exceeded its jurisdiction by allowing the claim for increase in cost of petroleum products and spare parts contrary to the contractual prohibition under clause 17(3) of the General Conditions of Contract? Whether the arbitral tribunal erred in allowing the claim for cost of material at site based on no evidence and by applying a thumb rule? Whether the arbitral tribunal erred in allowing the claim for interest contrary to the contractual prohibition under clause 16(2) of the General Conditions of Contract?
Ratio Decidendi: The court held that the award of the learned arbitrators allowing the interest is contrary to the terms of the contract and contrary to section 31(7)(a) of the Arbitration and Conciliation Act, 1996 and deserves to be set aside. The court relied on the judgment of Supreme Court in case of Union of India vs. Concrete Products and Construction Company and others (2014) 4 SCC 416 and in particular paragraph (10) and would submit that the award of the learned arbitrators allowing the interest is contrary to the terms of the contract and contrary to section 31(7)(a) of the Arbitration and Conciliation Act, 1996 and deserves to be set aside.
Final Decision: The court set aside the impugned award insofar as claim nos. 5, 7 and 13. Rest of the award was upheld.
1. By this petition filed under section 34 of the Arbitration and Conciliation Act, 1996 (for short the said 'Arbitration Act') the petitioner has impugned the majority award dated 14th September, 2010 rendered by the arbitral tribunal thereby allowing five claims made by the respondents and rejecting the counter claims made by the petitioner. Some of the relevant facts for the purpose of deciding this petition are as under:-
2. The respondent herein was the original claimant whereas the petitioner herein was the original respondent in the arbitral proceedings. The petitioner had also made counter claims in the arbitral proceedings.
3. Sometime in the year 1996, the petitioner had invited tenders regarding the work of Narkhed-Amravati New BG line – Earthwork in embankment, cutting and bridge approaches in Section XXIII from Ch.98000 to Ch.108000 between Chandurbazar and Walgaon Station. The respondent submitted the tender in response to the said notice. The tender of the respondent was accepted by the petitioner. On 11th July, 1996 the parties entered into a contract agreement. The contract was awarded at Rs.67,21,043/- with completion period of 12 months including monsoon period. The contract was governed by the General Condition of Contract. The said contract was extended from time to time. The dispute arose between the parties. On or about 14th January, 2002, the respondent invoked the arbitration clause and requested the General Manager of the petitioner to appoint arbitral tribunal.
4. By an order dated 11th February, 2005, the learned Judge designated by the Hon'ble Chief Justice directed the General Manager of the petitioner to appoint arbitral tribunal as per clause 64 of the General Condition of Contract in Arbitration Application No.182 of 2004 filed by the respondent. Pursuant to the liberty granted by the arbitral tribunal, the respondent herein filed statement of claim and made 14 claims in the sum of Rs.3,79,24,214/- with further interest thereon. The petitioner resisted the said claim by filing written statement and also simultaneously filed a counter claims thereby making five claims with interest. None of the parties led any oral evidence. By an majority award dated 14th September, 2010 the learned arbitrators allowed claim nos. 1, 4, 5, 7 and 13 in favour of the respondent and rejected the counter claims made by the petitioner. The petitioner has impugned that part of the award allowing five claims in favour of the respondent and rejecting the counter claims made by the petitioner. The respondent has not impugned the arbitral award rejecting the other claims made by the respondent.
5. Mr.Suresh Kumar, learned counsel appearing for the petitioner fairly submits that though in the prayer clause, the petitioner has applied for setting aside the entire award, the petitioner has not raised any grounds in respect of claim nos. 1 and 4.
6. Insofar as claim no.5 i.e. 'increase in cost of petroleum products and spare parts' is concerned, the respondent had originally claimed a sum of Rs.13,12,974/- and revised the said claim before the learned arbitrators at Rs.13,18,293.44. The learned arbitrators have allowed the said claim at Rs.13,12,974/-. He submits that under clause 17 of the General Conditions of Contract, 1956 even if there was any delay on the part of the petitioner in handing over to the contractor the possession of the lands necessary for execution of the work or for various other reasons mentioned therein or any other cause whatsoever, it would not affect or vitiate the contract or entitle the contractor to the damages or compensation therein but the petitioner could grant only extension of the completion date. Reliance is placed on clause 17(3) of the General Conditions of Contract which is extracted as under:-
Extension of time on Railway Accounts
(3) In the event of any failure or delay by the Railway to hand over to the Contractor possession of the lands necessary for the execution of the works o
RamnathInternational Construction Private Limited vs. Union of India AIR 2007 SC 509
Hyder Consulting (UK) Limited vs. Governor, State of Orissa
Sayeed Ahmed & Co. vs. State of U.P. (2009) 12 SCC 26
Port of Calcutta vs. Engineers-De-Space-Age (1996) 1 SCC 516
Ramnath International Construction Private Limited v. Union of India AIR 2007 SC 509
Union of India vs. Concrete Products and Construction Company and others (2014) 4 SCC 416
Sree Kamatchi Amman Constructions vs. Divisional Railway Manager (Works)
Asian Techs Limited vs. Union of India and others
Madnani Construction Corporation Private Limited vs. Union of India and others
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.