2017 Supreme(Bom) 1850
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
R.D. DHANUKA, J.
Bottero S.P.A. - Petitioner
Versus
Euro Glass Limited and Ors. - Respondent
ARBITRATION PETITION NO. 279 OF 2011
Decided On : 30-11-2017
Important Points
Subject
Arbitration Law - Enforcement of Arbitration Agreements
Act Referred
ARBITRATION AND CONCILIATION RULES : R.23, R.4, R.8, R.9, R.10, R.3(1), R.19, R.4(2)
CIVIL PROCEDURE CODE : O.7 R.11
ICC RULES : R.4
Headnote
Arbitration Act - Disputes arising from contract - Section 27.2 of the Arbitration Agreement - Summary of Acts and Sections: Arbitration and Conciliation Act, 1996, Section 45; Code of Civil Procedure, 1908, Order VII Rule 11; International Chamber of Commerce Rules of Arbitration, Article 4 and 23 - The court analyzed the arbitration agreement, waiver, and abandonment of the right to invoke arbitration agreement, and found that the arbitration agreement was inoperative due to the petitioner's abandonment and waiver of its right to invoke the agreement. The court dismissed the Arbitration Petition No.279 of 2011.
Fact of the Case:
The petitioner sought an order to refer disputes raised in Suit No. 1846 of 2009 to arbitration in accordance with the Arbitration Agreement. The respondent filed a suit against the petitioner, praying for recovery of a sum alleged to have been paid as an advance payment.
Finding of the Court:
The court found that the arbitration agreement was inoperative due to the petitioner's abandonment and waiver of its right to invoke the agreement. The court dismissed the Arbitration Petition No.279 of 2011.
Issues: The issues included the applicability of the arbitration agreement, waiver, and abandonment of the right to invoke the arbitration agreement, and the satisfaction of conditions under Section 45 of the Arbitration Act.
Ratio Decidendi: The court held that the petitioner's inaction and delay in invoking the arbitration agreement amounted to abandonment and waiver, rendering the arbitration agreement inoperative. The court also considered the limited jurisdiction under Section 45 of the Arbitration Act and the mandatory conditions for invoking arbitration.
Final Decision: The court dismissed the Arbitration Petition No.279 of 2011, as the arbitration agreement was found to be inoperative due to the petitioner's abandonment and waiver of its right to invoke the agreement.
For the Petitioner: Mr. Rohan Rajadhakshya, Mr. Shahen Pradhan
For the Respondents: Mr. Ashutosh Thipsay, Ms. Neha Karnik, Mr. Vinod Juwale
By this petition filed under Section 45 of the Arbitration and Conciliation Act, 1996 (for short “the Arbitration Act”), the petitioner seeks an order and direction to refer the disputes raised in Suit No. 1846 of 2009 to arbitration in accordance with Clause 27.2 of the Arbitration Agreement dated 14th April 2008 and seeks dismissal of the said suit. Some of the relevant facts for the purpose of the deciding this petition are as under :-
2. The petitioner herein is the original defendant no.2 in Suit 1846 of 2009 which was filed by the respondent no.1 herein (original plaintiff) against Gutal Trading (India) the respondent no.2 herein (for the sake of convenience, the said Suit No.1846 of 2009 is referred to as “the said suit”). The said suit was filed by the respondent no.1 herein inter alia praying for recovery of Euro 4,25,100 alleged to have been paid by the respondent no.1 as an advance payment on account of the petitioner herein failing to fulfill the terms and conditions of the contract agreement despite the advance payment being released by the respondent no.1 in favour of the petitioner herein.
3. In the said suit, the respondent no.1 had prayed for an order and decree against the petitioner herein and Gutal Trading (India) in the sum of Euro 8,50,200 equivalent to Indian Rs.5,60,79,192/-. The petitioner herein appeared in the said suit. No written statement has been filed by the petitioner herein till date. In the said suit, the defendant no.1-Gutal Trading (India) filed Notion of Motion No.9 of 2011 under Order VII Rule 11 of the Code of Civil Procedure, 1908 inter alia praying for dismissal of the said suit, in so far as the defendant no.1-Gutal Trading (India) is concerned, on the ground that there was no privity of contract whatsoever nature between the plaintiff and the defendant no.1 and on various other grounds.
4. By an order dated 29th October 2015 passed by this Court, the said Notice of Motion No.9 of 2011 filed by the said Gutal Trading (India) came to be allowed. This Court held that there was no cause of action against the said Gutal Trading (India) in the said suit. The plaintiff i.e. Euro Glass Limited preferred an appeal against the said order dated 29th October 2015. The Division Bench of this Court has condoned the delay in filing the said appeal. The said appeal is still pending. During the pendency of the said appeal, hearing of this arbitration petition was adjourned for sometime. Since the said order dated 29th October 2015 was admittedly not stayed by the Division Bench of this Court, in the said appeal filed by the petitioner herein, this Court therefore proceeded with hearing of this Arbitration Petition No. 279 of 2011.
5. Mr. Rajadhakshya, learned counsel appearing for the petitioner invited my attention to the agreement entered into between the petitioner and the respondent no.1 dated 14th April 2008 annexed at Exhibit-A to the petition and more particularly the arbitration agreement recorded in Clause 27 of the said agreement which is extracted as under :-
27. DISPUTES AND ARBITRATIONS
27.1 Friendly Consultations
Any dispute arising from, out of or in connection with the contract shall be settled through friendly consultations between the parties. Such consultations shall begin immediately after one party has delivered to the other party a written request for such consultation.
Following such written request the Project Managers of each party shall meet and try to reach a settlement.
If the Project Managers are unable to reach a settlement within one month, they shall draft within two further weeks a joint report stating the exact subject of the dispute, the facts on which they agree, the points of disagreement and the reasons of such disagreement.
This report shall be handed over to the management of both parties. The management of both parties shall then try to reach a settlement.
27.2 Continued Implementation of Contract
During the period when a dispute is being resolved, the parties s