SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2018 Supreme(Bom) 623

IN THE HIGH COURT OF BOMBAY AT AURANGABAD
R.D. DHANUKA, SUNIL K. KOTWAL, JJ.
City Industrial & Development Corporation Through its Administrator, CIDCO & Others - Appellant
Versus
Sunil & Others - Respondent
First Appeal No. 416 of 2000 with Civil Application Nos. 4789 of 2005, 6098 of 2015, 6925 of 2011, 13900 of 2016, 11021 of 2017, 12517 of 2017 in Cross Objection (ST.) No. 28630 of 2017
Decided On : 13-02-2018

Advocates Appeared:
For the Appellants :A.S. Bajaj, Advocate.
For the Respondents:A.B. Kale, Advocate, M.A. Deshpande, A.G.P.

Headnote:

Civil Procedure Code,1908 - Section 89 - Enhanced compensation - Appellant was appointment - Land Acquisition Act, 1894 - section 18 - MRTP Act - section 126(4) - Insofar as First Appeal is concerned same is filed against order passed in Land Reference Application before Civil Judge Senior Division at Aurangabad - It was case of respondent was original claimant that he was owner and possessor land bearing survey to extent of Hectares and equivalent to acres and gun - Claimant was Managing Partner of Land Mark Developers - Aurangabad - It was case claimant that land in question which was owned by him was forming part and parcel of CIDCO area New Aurangabad and was within local limits of Municipal Corporation Aurangabad - land in question was situated abutting Road in between old Aurangabad city – Held, Insofar as Civil Application for condo nation of delay filed by claimants in Cross Objection is concerned in our view counsel for claimant has rightly placed reliance on judgment of this Court in case State of Maharashtra supra holding that Court has to take liberal approach whole considering delay in filing cross objection and shall hear appeal on merits - Said judgment applies of this case - Court therefore condone delay in filing cross-objection - Court have heard parties on merits - Civil application for condo nation of delay in filing cross objection thus deserves to be allowed - Court are however of view that since Reference Court has passed detailed order and judgment considering oral and documentary evidence led by both parties and have taken balanced view court are not inclined to interfere with impugned order and judgment in appeals filed by appellant and also in cross objection filed by claimants - In our view there is no merit in Civil Application filed by one claimants in First Appeal for an order and direction for referring dispute for arbitration and conciliation or mediation - Since both parties have made rival submissions on merits of order passed by Reference Court this civil application has become in fructuous and thus deserves to be dismissed – Similarly Civil Application filed in First Appeal praying for four weeks time for complying order for substitute service has also become in fructuous and thus deserves to be dismissed - Insofar as Civil Application filed by claimants for substitution of claimant is concerned in our view appellant has rightly opposed reliefs prayed in this civil application - Applicant in this civil application had never applied for such reliefs before Reference Court - No case is made out for substitution of parties as prayed in said civil application and same thus deserves to be rejected – Appeal dismissed

JUDGMENT :

R.D. DHANUKA, J.

1. By consent of parties, all three appeals were heard together and are being disposed of by a common order in view of the facts being identical and there being a common order passed by the Reference Court. Some of the relevant facts for the purpose of deciding these three appeals are arising out of the reference petition filed under section 18 of the Land Acquisition Act, 1894 are as under:

2. Insofar as First Appeal No.416 of 2000 is concerned, the same is filed against the order passed in Land Reference Application No.40 of 1997 before the learned Civil Judge, Senior Division at Aurangabad. It was the case of the respondent no.1, who was the original claimant that he was the owner and possessor of the land bearing survey no.15 at Garkheda to the extent of 2 Hectares and 49 R equivalent to 6 acres and 6 gunthas. The claimant was the Managing Partner of the “Land Mark Developers. Aurangabad”. It was the case of the claimant that the land in question which was owned by him was forming part and parcel of CIDCO area (New Aurangabad) and was within the local limits of Municipal Corporation, Aurangabad. The land in question was situated abutting Jalna Road in between old Aurangabad city and Chikalthana.

3. In the year 1986, part of survey no.15 came to be acquired for the purpose of development of new Aurangabad city. It is the case of the claimant that at that time the land in question was dropped and was not acquired. The appellant was appointed as Special Planning Authority in respect of Aurangabad Municipal Corporation. The claimant had submitted an application to CIDCO Administration, Aurangabad for approving the lay out for proper and full utilization of the area on 12th October, 1989. After acquisition proceedings of the land in question were dropped in the year 1986-87 in respect of the portion of land bearing survey no.15 of Garkheda, Aurangabad, said lay out plan was not approved by CIDCO by a communication dated 7th December, 1989. The claimant was informed by CIDCO that the acquisition proceedings were already in progress with the Collector, Aurangabad and thus the lay out plan should not be approved.

4. It is the case of the claimant that on 5th December, 1991, actual notification under section 126(4) of the Maharashtra Regional Town Planning Act, 1966 (for short “MRTP Act”) was issued by the District Collector, Aurangabad. It is the case of the claimant that to the North and adjacent to this area is the new High Court building along with its campus, abutting Jalna road, the developed area is known as N-3 and N-4, which is also just adjacent to approximate vicinity and entire area of N-3 and N-4 is fully developed. It is the case of the claimant that the acquired portion of survey no.15 in 1986 is also fully developed consisting of constructed houses. Survey no.16 to the West and survey nos.20 and 22 to the South of survey no.15 are also fully developed where thousands of houses have been constructed. It was the case of the claimant that the entire adjoining area of the land under acquisition has been fully developed, thickly populated and thus nothing remains for the purpose of making any other efforts to develop the acquired area from the land survey no.15 in question.

5. The said notification under section 126(4) of the MRTP Act was published in the Maharashtra Government Gazette, Aurangabad Division, Supplement Part-I on 10th December, 1991 and was also published in local newspapers (1) Daily Ajantha, Aurangabad dated 6th January,1992 and (2) Daily Citizen, Aurangabad dated 7th January, 1992. The substance of the above notification was published on site by drawing a panchanama dated 13th February, 1993.

6. The appellant had been appointed as Special Planning Authority for New Aurangabad notified area under section 40(i)(b) of MRTP Act by Government Notification dated 30th October, 1972, amended by Notification dated 3rd February, 1973. CIDCO had carried out survey and prepared a draft plan pro



















































































































































































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top