SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2018 Supreme(Bom) 1358

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
SHALINI PHANSALKAR JOSHI, J.
Lavasa Corporation Limited – Appellant
Versus
Jitendra Jagdish Tulsiani – Respondent
Second Appeal (Stamp) Nos. 9717, 18465, 18467 of 2018 with Civil Application Nos. 683, 791, 792 of 2018
Decided On : 07-08-2018

Advocates Appeared:
For the Appellants : Mr. Raj Patel, Mr. Ruturaj Bankar, Mr. Kaustav Talukdar.
For the Respondents: Mr. Mayur Khandeparkar, Mr. Tushar Gujjar, Ms. Shweta Merchant, Mr. Deepak Singh.

Headnote:

Real Estate (Regulation and Development) Act, 2016 - Section 58 - Agreement to Lease - Promoter - Sale of apartments Construct - Appellants are aggrieved by three separate orders passed by Maharashtra Real Estate Appellate Tribunal in three separate Appeals filed by Respondents Section of RERA against orders passed by Adjudicating Authority under Section of Act - By impugned orders Appellate Tribunal has set aside orders passed by Adjudicating Authority and that provisions of RERA are applicable even in case of Agreement of Lease in present case and Adjudicating Member of Maharashtra Real Estate Regulatory Authority has jurisdiction to entertain complaints filed by Respondents - It was held so despite fact that according to Appellant relationship between Appellant and Respondents is of and Lessee and re is no sale and/or absolute transfer of right title and interest in favour Respondents with respect to respective apartments – Held, It is pertinent note that if according to Appellant also project undertaken was not of development and sale of apartments constructed rein n Appellant was not bound to register same and would not have registered same under Section of RERA - If Appellant has also understood Agreements executed with Respondents as only Agreements of Lease n Appellant could have very well avoided registration under RERA because in that case Appellant could have contended that it is not bound by Section of RERA as project was not undertaken for sale of flats or apartments but only for purpose of giving apartments on rent - Very fact that Appellant has got itself registered RERA makes it necessary to infer that Appellant was very well aware that this project was for sale of apartments constructed in project and that is why it was bound by provisions of RERA - Moreover here re is no question of applying logic that if project is not registered RERA will not be applicable even if it is proved to be project of development because as per mandate of RERA all real estate projects are now required to be registered if apartments rein are constructed for purpose of sale - fact that Appellant has registered project also makes it necessary to infer that Appellant has invited upon itself applicability of provisions of RERA as Appellant is also fully aware that whatever Agreements executed by it with Respondents are in nature of sale though y are titled as Agreements of Lease – Appeal dismissed

JUDGMENT :

SHALINI PHANSALKAR JOSHI, J.

1. Heard finally, at the stage of admission itself, with the consent of learned counsel for the Appellant and Respondents.

2. Admit.

3. These three Appeals are preferred, under Section 58 of the Real Estate (Regulation and Development) Act, 2016, (for short “RERA”), by Lavasa Corporation, which is developing a Township Project to construct Lake Views and which is registered under the RERA.

4. These Appeals are raising the common questions of law as to whether the provisions of the RERA would apply in case of an Agreement to Lease - particularly in the facts of the present case, whether the definition of the term Promoter as provided under Section 2(zk) in the RERA, would include a Lessor and whether the remedy provided to the Allottees under Section 18 of the RERA can be available only against the Promoter, or in that sense, also against a Lessor?

5. The Appellants are aggrieved by the three separate orders passed by the Maharashtra Real Estate Appellate Tribunal in three separate Appeals filed by the Respondents, under Section 43(5) of the RERA, against the orders passed by the Adjudicating Authority, under Section 18 of the said Act. By the impugned orders, the Appellate Tribunal has set aside the orders passed by the Adjudicating Authority and held that, the provisions of the RERA are applicable even in case of Agreement of Lease in the present case and, therefore, the Adjudicating Member of the Maharashtra Real Estate Regulatory Authority has jurisdiction to entertain the complaints filed by the Respondents. It was held so, despite the fact that, according to the Appellant, relationship between the Appellant and Respondents is of Lessor and Lessee and there is no sale and/or absolute transfer of right, title and interest in favour of the Respondents with respect to their respective apartments.

6. The factual matrix of the case, in which these questions are raised, can be depicted as follows:-

Respondents claim themselves to be the bona-fide purchasers of their respective apartments in the projects/buildings known as “Brook View” which is being constructed at Village Dasve, Taluka Mulshi, “Belshore” which is being constructed at Bhugaon Taluka; and “Lake View” which is being constructed at Mulshi Taluka, respectively in Pune District by the Appellant herein. In pursuance of the negotiations between the parties, the Agreements of Lease came to be executed between them on various dates in the years 2014, 2013 and 2010, respectively. As per the said Agreements, the Respondents have booked the apartments on the basis of lease for the period of 999 years in the Township Scheme of the Appellant. They had paid most of the consideration amount, which is, approximately, to the extent of 80% of the sale price. They have also paid substantial amount towards the stamp-duty and the registration charges.

7. As per the Agreements of Lease executed between the parties, the project was to be completed and the possession of the apartments was to be handed over to the Respondents within a period of 24 months. After waiting bonafidely for all these six to seven years for getting the project completed and after making several enquiries with the Appellant about the progress of the said project, the Respondents found that there are no chances of the project being completed in a near future. Hence, after the Appellant registered itself with the RERA, Respondents approached the Adjudicating Authority under the Maha-RERA with an application, under Section 18 of the RERA, for compensation with interest for every month of the delay in handing over possession of the apartments and for various other reliefs, to which they are entitled under the RERA.

8. Appellant, however, on its appearance before the Adjudicating Authority, challenged the very applicability of the provisions of the RERA to the Agreements of Lease entered into by the parties contending inter-alia that, the Respondents are the Lessees, as the Agreements ente






























































































































Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top