2019 Supreme(Bom) 1399
IN THE HIGH COURT OF BOMBAY
S.C. GUPTE, J.
Goregaon Pearl CHSL - Appellant
Versus
Seema Mahadev Paryekar and Others - Respondents
Appeal From Order (Stamp) No. 22143 of 2019
Decided On : 14-10-2019
Mayur Khandeparkar, Adv., Tushar Gujjar, Adv., Vikram G. Adv., Deepak Singh, Adv., Darshil Shah, Adv., Amardev J. Uniyal, Adv., Rajiv Narula, Adv., Ekta Pandav, Adv.
: There is no privity of contract between a landowner society and third-party purchasers claiming through a developer, and landowners are not automatically treated as promoters under RERA or MOFA.
Headnote:Keyword - Development Agreement Subject - Real Estate Dispute Act Section List - Arbitration and Conciliation Act, 1996 ("Act"), Real Estate (Regulation and Development) Act, 2016 ('RERA'), Maharashtra Ownership Flats (Regulation of the Promotion of Construction, Sale, Management and Transfer) Act, 1963 ("MOFA") Summary:
Fact of the Case:
The case involves a dispute arising from a development agreement for the redevelopment of a property owned by a cooperative housing society. The developer failed to complete the project within the stipulated period, leading to various legal actions and arbitration proceedings.Finding of the Court:
The court found that the protection granted to the developer in the order of the arbitrator shall also benefit third-party purchasers. It held that the interest of third-party purchasers had been adequately protected by previous orders.Issues:
The main issue was whether third-party purchasers should be granted protective relief in a redevelopment project where completion was delayed due to breaches by the developer.Ratio Decidendi:
The court emphasized that there was no privity of contract between the society and third-party purchasers claiming through the developer. It also clarified that RERA did not make landowners liable for complying with obligations under development agreements or RERA provisions.Final Decision:
The impugned order was quashed and set aside. The court rejected an application for further protective relief for third-party purchasers.JUDGMENT :
S.C. Gupte, J.
The appeal is admitted and taken up for hearing forthwith by consent of counsel.
2. This appeal from order challenges an order passed by Bombay City Civil Court at Dindoshi, Mumbai on a notice of motion. By the impugned order, the Appellant (original Defendant) was restrained from alienating, or creating any third party interest in, the suit flat. This was by way of an ad-interim protection to the Respondents (original Plaintiffs). This order has since been perpetuated and obtains till date. On these bare facts, ordinarily I should have asked the parties to go for an expeditious hearing of the notice of motion instead of entertaining this appeal from an ad-interim order. Considering, however, the peculiar facts of the case and particularly, having regard to the fact that this controversy has had a long and chequered history, where the parties have already gone right upto the Supreme Court, I am of the considered view that I should hear the parties at length and consider the case threadbare at the stage of ad-interim relief itself. Learned Counsel for both sides have showed their inclination to go in for a detailed hearing. I have accordingly heard Counsel and propose to dispose of the appeal by a detailed order.
3. The controversy in the present matter concerns redevelopment of a property owned by the Appellant, who is a cooperative housing society of about sixty members, who have already handed over possession of their respective flats for redevelopment and are currently said to be roofless. The redevelopment was entrusted by the Appellant society to Respondent No.2 developer (original Defendant No.2) under a development agreement. Under this agreement, the developer was duty bound to complete the project within twenty-two months from the date of receipt of commencement certificate with a three months grace period. The project involved construction of two wings of the new building, Wings A and B. Both wings were to partly accommodate the members of the Appellant society and partly third party purchasers of the free sale component of the project. In pursuance of the agreement, all members of the Appellant society vacated their respective flats by handing over possession to Respondent No.2 developer. Respondent No.2 had executed a bank guarantee in favour of the society in the sum of Rs.5 crores for fulfilling his commitment under the agreement. On or about 17 June 2008, a commencement certificate for construction of the new building was issued by the Municipal Corporation of Greater Mumbai ('MCGM') to the developer. Though construction was undertaken in pursuance thereof, it was nowhere near completion even as late as by August 2016, that is to say, even after passage of eight years from issuance of the commencement certificate. In the premises, by their notice dated 16 August 2016, the Appellant revoked the Power of Attorney given by it to the developer for development of the suit property. This was followed by an arbitration petition under Section 9 of the Arbitration and Conciliation Act, 1996 ("Act") by the Appellant society seeking inter alia appointment of a court receiver for taking over the redevelopment project and completing it. Various breaches on the part of Respondent No.2 developer were alleged in the arbitration petition. These included non-completion of the project within the stipulated period of 25 months, change of plans without the society's consent and unauthorised construction of two additional floors for which stop-work notice was issued by MCGM. In the meantime, the bank guarantee of Rs.5 crores was invoked and encashed by the Appellant society. After various interim orders passed by this court on that arbitration petition, finally, on or about 7 July 2017, the parties entered into consent terms. Under these consent terms, the total liability of the developer was fixed at about Rs.7.62 crores. It was agreed that Rs.2.5 crores would be adjusted, from out of the bank guarantee amount