2020 Supreme(Bom) 184

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
Pradeep Nandrajog, Bharati Dangre, JJ.
Mudhit Gupta & Another – Appellants
Versus
Sussanne Khan – Respondent
Commercial Appeal Lodging No. 474 of 2018 in Comm. Arbitration Petition No. 917 of 2018
Decided On : 04-02-2020

Important Points

An arbitral award will be upheld if it is based on a possible view of the evidence and there is no error apparent on the face of the Award.

Subject

Arbitration and Conciliation Act, 1996 - Enforcement of Arbitral Awards

Act Referred

ARBITRATION AND CONCILIATION ACT : S.34, S.9, S.37
SPECIFIC RELIEF ACT : S.16(c)

Headnote

The Court upheld the Arbitral Award directing the Appellants to pay the Respondent the agreed price for the drawings/designs supplied by her, which were used by the Appellants in the project without employing her to execute them.

Fact of the Case:

The Respondent, an architect and interior designer, entered into an agreement with the Appellants, a real estate company, to provide architectural and design services for a project involving the construction of 12 villas. The agreement stipulated a two-phase fee schedule, with the first phase covering the design and submission of architectural and interior design drawings, and the second phase covering the execution of the interiors of the villas. The Respondent claimed entitlement to a sum of Rs.2,52,81,000/-, which was payable if the Appellants used her designs and executed the works through another contractor without her consent. The Appellants terminated the agreement, alleging breach of contract by the Respondent, and engaged third-party contractors to complete the project.

Finding of the Court:

The Arbitral Tribunal found that the Respondent had complied with her obligations under the agreement and had submitted all the required drawings and designs. It also found that the Appellants had used the Respondent's drawings and designs in the project without employing her to execute them. The Tribunal rejected the Appellants' claim that the drawings were incomplete or unusable, and held that the Respondent was entitled to the agreed price for the drawings/designs supplied.

Issues: 1. Whether the Respondent was entitled to the sum of Rs.2,52,81,000/- for the use of her designs and drawings by the Appellants without her consent. 2. Whether the Respondent had breached the agreement by failing to submit complete and usable drawings and designs.

Ratio Decidendi: The Court held that the Arbitral Tribunal's findings were based on a possible view of the evidence and that there was no error apparent on the face of the Award. It also held that the Tribunal had correctly interpreted the agreement between the parties and that the Respondent was entitled to the agreed price for the drawings/designs supplied.

Final Decision: The Court dismissed the appeal and upheld the Arbitral Award.

Advocates Appeared:
For the Appellant :Simil Purohit, Jairam Chandnani, Vishal Raman, Ashish Gupta i/b. Lexim Associates, Advocates.
For the Respondent:Sharan Jagtiani, Dr. Abhinav Chandrachud, Pooja Tidke, Krushi N. Barfiwala i/b Parinam Law Associates, Advocates.

JUDGMENT :

Bharati Dangre, J.

1. Prolix pleadings akin to a Banyan tree having aerial roots dropping on to the ground and with passage of time taking the shaping of a trunk, resulting in the viewer seeing multiple trunks, warranting each and every trunk to be viewed with a piercing eye to determine where from the seed sprouted to form the original trunk has resulted in an equally lengthy Award. But it is not the fault of the learned Arbitrator because a reasoned Award required the process of reasoning by which the learned Arbitrator determined the place where the seed germinated to be stated with clarity.

2. Agreement, Ex-C-148, dated 18th September 2003, is the fertile ground where the seed germinated. Before we come to the agreement, the parties need to be briefly referred to. The Appellant no.1 is a partner of Appellant no.2 EMGEE Properties and is engaged in the business of Real Estate, specifically property development. The Respondent (hereinafter referred to as 'the Claimant) is the sole proprietor carrying on business in the name and style of Suzanne Khan, House of Design, and claim to be a leading name in the field of Architecture and Interior design. She asserts that she is the founder of conceptual interior design store “The Charcoal project” and asserts a good will and reputation both nationally and internationally. The Appellants conceived a project of 12 uniquely styled villas to be constructed in Goa and approached the Respondent to avail her professional designing services for the proposed project. To give effect to the arrangement between the two, the agreement dated 18th September 2013, though in form of a letter addressed by the Appellant no.1 to the Respondent was penned down. The Respondent who agreed to the terms contained in the said letter inked the same and on acceptance of the terms and conditions, it culminated into a binding contract between the parties. It is the Letter of Award of the contract by which the Appellants authored the terms under which the Respondent/Claimant was to be paid remuneration as Designer and Architect as also contractor for 12 villas in the proposed project styled as “Naira”.

3. As one would expect to be recorded in such kind of works, the letter commences with the scope of work being listed. The same is reproduced hereinafter:-

“SCOPE OF WORK

1. PHASE 1 - Inception

[a] Discussing general requirements of the project including time scale and financial budgets and providing general advice on how to proceed.

[b] Determining the client’s requirements in sufficient detail for subsequent stages to begin.

[c] Develop, from approved outline a scheme design or master plan as appropriate. Conceptual Schematic design consisting of drawings and outline specification sufficient to indicate spatial arrangements, materials and appearance. Broader site landscaping division of proposed 12 plots and services for each plot.

2. PHASE 2 - Detailed Design

Providing of Architect's designs of Vilas

[a] The detailed design stage will entail the following detailed information to create a finished interior.

General Layout – Space Planning

Detail plan/elevation/sections

Material Spaces sampling, finishing

Furniture Drawings

Services – Electrical – Lighting HVAC Plumbing

Landscaping for each villa

Branding Logo design, brochure designing and design of other marketing material for the project.

Walk-through's and rendered drawings for the entire project interiors.”

4. Thereafter, as is to be expected, keeping in view the nature of the work assigned, the time duration has been penned and relevant would it be to state that while so doing, the Appellants have written: 'Time Duration Approximate'. The said clause though contain certain time stipulations, it specifically mention the completion of project in time is dependent on client co-operation and also subject to force majeure events which include non-receipt of permissions