IN THE HIGH COURT OF JUDICATURE AT BOMBAY
S.C. GUPTE, J.
Narendra Hirawat and Co. – Plaintiff
Versus
Sholay Media Entertainment Pvt. Ltd. and Another – Defendants
Notice of Motion Nos. 2591, 2607 of 2019, Commercial IP Suit Nos. 1387, 1469 of 2019
Decided On : 09-03-2020
IP Suit - Film Licence Agreements - Section 14(d) of the Specific Relief Act - The court discussed the film licence agreements, the deed of settlement, and the termination of the agreements. It highlighted the provisions of Section 14(d) of the Specific Relief Act and its interpretation in the context of the determinability of the contracts. The court found that the contracts were not inherently determinable and granted interim protection to the Plaintiff.
Fact of the Case:
The Plaintiff and Defendant No. 1 entered into film licence agreements for the distribution and exploitation rights of two films. Disputes arose regarding the payment of consideration under the agreements, leading to the termination of the agreements by Defendant No. 1. Defendant No. 2 claimed to have entered into a separate film licence agreement with Defendant No. 1.
Finding of the Court:
The court found that the Plaintiff's case of wrongful termination of the agreements by Defendant No. 1 was legitimate and needed to go to trial. It also ruled that the Plaintiff deserved interim protection pending trial.
Issues: The issues involved the payment of consideration under the film licence agreements, the termination of the agreements by Defendant No. 1, and the subsequent agreements entered into by Defendant No. 1 with Defendant No. 2.
Ratio Decidendi: The court interpreted Section 14(d) of the Specific Relief Act and found that the contracts were not inherently determinable, leading to the grant of interim protection to the Plaintiff.
Final Decision: The court granted interim protection to the Plaintiff, restraining Defendants from dealing with the licensed rights in the films until a specified date, and ordered the Plaintiff to deposit the balance consideration with interest as a condition of the reliefs granted.
JUDGMENT :
S.C. GUPTE, J.
1. This notice of motion (Notice of Motion No. 2591 of 2019) has been taken out in a commercial IP Suit in respect of distribution and exploitation rights in two suit films, by the names of Sholay and Sholay-3D.
2. The rights are claimed by virtue of a film licence agreement executed between the parties thereto on 9 September 2015 for the period between 1 April 2016 to 31 March 2022 (“first agreement”) and a further agreement entered into between the parties on the same date i.e. 9 September 2015, for the period between 1 April 2022 and 31 March 2027 (“second agreement”). The first agreement was for a total consideration of Rs. 20 crores, whereas the second was for a total consideration of Rs. 5 crores. The agreements covered exploitation rights, such as electronic media rights, television rights, satellite broadcasting rights, etc. on a sole and exclusive basis by the Plaintiff herein (described in the agreements as ‘licensee’ Defendant No. 1 herein, the owner of copyright in the two suit films, being described as ‘licensor’). It is not in dispute that consideration payable under the first agreement has been more or less paid. The dispute really pertains to payment of consideration under the second agreement. The agreements were followed by an addendum. Disputes arose between the parties and these were finally resolved by the parties entering into a deed of settlement on 3 December 2018. (This deed of settlement was preceded by a memorandum of settlement between the parties, the deed of settlement being a formal execution of the settlement.) Under this deed of settlement, the Plaintiff was to pay an aggregate sum of Rs. 8.71 crores, along with GST, for the suit films for the second term, namely, the term commencing on 1 April 2022 and ending on 31 March 2027, and which was extended upto 30 September 2028. In pursuance of the settlement, Defendant No. 1 raised its first invoice for a sum of Rs. 1.25 crores on 5 November 2018, which, along with applicable GST (both CGST and SGST), worked out to Rs. 1.40 crores. This amount was to be paid to the credit of Defendant No. 1 partly to one HRVS Financial Consultants Private Limited and partly to Defendant No. 1 itself. It is not in dispute that this amount was duly paid by the Plaintiff. This was followed by a second invoice raised by Defendant No. 1 on the Plaintiff on 3 December 2018 for licence fees of Rs. 2.46 crores, which, together with GST, worked out to about Rs.2.75 crores. It is also not in dispute that this amount was duly paid by the Plaintiff to Defendant No. 1 or to its credit. Defendant No. 1 then raised its third invoice for a sum of Rs. 1.75 crores on 3 June 2019, which, together with applicable GST, worked out to Rs. 1.96 crores. This amount was also paid by the Plaintiff to, or to the account of, Defendant No. 1, albeit with a delay. The Plaintiff thus paid a total sum of about Rs. 5.46 crores as against the total consideration of Rs. 8.71 crores reserved under the deed of settlement. The dispute between the parties pertains to the balance amount.
3. According to Defendant No. 1, the payment was not made in time, time being of essence, and Defendant No. 1, accordingly, proceeded to terminate the films licence agreements between the parties by its letter dated 18 June 2019. Defendant No. 1 claims to have entered into a separate film licence agreement with Defendant No. 2 herein, creating same distribution rights in favour of the latter. (That is how Defendant No. 2 has been arraigned as a party to the present suit.) On the other hand, it is the Plaintiff’s case that Defendant No. 1 was expected to issue invoices separately for licence fees to be charged from out of the total consideration reserved under the deed of settlement (i.e. Rs. 8.71 crores) and applicable GST on that amount, and the Plaintiff was to make payment only according to such invoices. It is submitted that without raising such invoices, the Plaintiff could not have straightaway
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.