2020 Supreme(Bom) 843

IN THE HIGH COURT OF BOMBAY
G.S. Patel, J.
Reliable Spaces Pvt Ltd - Appellant
Versus
Evonik India Pvt Ltd - Respondent
Commercial Arbitration Petition No. 1019 of 2019
Decided On : 19-10-2020

Important Points

The central legal point established in the judgment is that the arbitrator's interpretation of contractual provisions and the force majeure clause was reasonable and just, and the court found no merit in the petition challenging the arbitral award.

Subject

Arbitration Law - Challenge to Arbitral Award

Act Referred

ARBITRATION AND CONCILIATION ACT : S.34

Headnote

patent illegality - Arbitration & Conciliation Act, 1996 - [SINGLE GROUND OF 'PATENT ILLEGALITY'] - [Ssangyong Engineering & Construction Co Ltd v National Highways Authority of India (NHAI), (2019) 15 SCC 131] - The court discussed the interpretation of specific contractual provisions, force majeure clause, MIDC approval, and NMMC property tax dues. The court found that the arbitrator's interpretation was not implausible and was the only possible view. The court dismissed the petition and awarded costs to the respondent.

Fact of the Case:

The case involved a petition challenging an arbitral award under Section 34 of the Arbitration & Conciliation Act, 1996. The dispute arose from a lease agreement between Reliable and Evonik for premises in Airoli, Navi Mumbai. Evonik terminated the lease invoking the force majeure provision, citing the lack of necessary permissions and property tax dues. Reliable contested the termination and sought a return of the security deposit but not damages or costs.

Finding of the Court:

The court found that the arbitrator's interpretation of the force majeure clause and contractual provisions was reasonable and just. The court dismissed the petition, stating that it lacked merit. Costs were awarded to the respondent.

Ratio Decidendi: The court held that the arbitrator's interpretation was not implausible and was the only possible view. The court found no merit in the petition and dismissed it. Costs were awarded to the respondent.

Final Decision: The court dismissed the petition, finding it entirely without merit. Costs were awarded to the respondent in the amount of Rs. 7,35,500/-, with interest at 12% per annum from the date of the order until payment or realization.

Advocates Appeared:
Navroz Seervai, Advocate, Gulnar Mistry, Advocate, Dhirendra Sinha, Advocate, Saket Mone, Advocate, Subit Chakrabarty, Advocate, Abhishek Salian, Advocate, Vishesh Karla, Advocate, Vidhi Partners, Advocate, Dinesh Purandare, Advocate, Shyam Kapadia, Advocate, Gaurav Shah, Advocate, Jigisha Vadodaria, Advocate, Negandhi Shah, Advocate, Himayatullah, Advocate, Cyrus Ardeshir, Advocate

JUDGMENT

G. S. Patel, J. - A. INTRODUCTION

1. I heard counsel on 13th and 14th October 2020 by video- conferencing on this Petition under Section 34 of the Arbitration & Conciliation Act, 1996 challenging an arbitral award dated 8th May 2019 made by a sole arbitrator, Mr Cyrus Ardeshir, an advocate of our Court.

2. Of necessity, and especially in view of the Supreme Court decision in Ssangyong Engineering & Construction Co Ltd v National Highways Authority of India (NHAI), (2019) 15 SCC 131 , the scope of the challenge is limited. Conscious of this, Mr Seervai for the Petitioner limited his grounds of challenge to a single ground of 'patent illegality'; and, specifically, perversity as a dimension of patent illegality. [1] Following the Ssangyong enunciation, he divides this ground into two components. First, that the learned Sole Arbitrator's interpretation of specific contractual provisions and, in particular, a force majeure clause, is so thoroughly implausible as to be perverse and therefore constitutes patent illegality. Second, that the arbitrator ignored vital evidence before him and this, too, constitutes perversity and vitiates the Award as being patently illegal. Mr Purandare for the Respondent defended the Award.

3. A summary background may be useful. The Petitioner (" Reliable ") is a lessee from the Maharashtra Industrial Development Corporation (" MIDC ") of some property in Airoli, Navi Mumbai. On this, there stands a building known as Liberty Tower. It has several units. In August 2014 Reliable gave three of these units in Liberty Tower to the Respondent (" Evonik ") on lease. Evonik proposed to use these premises for its specialty chemicals business. It placed an interest-free refundable security deposit of Rs.1,90,01,100 with Reliable. The term was nine years, and the first five of these were a lock-in. Evonik was to pay a little over Rs 30 lakhs a month from 1st January 2015 or completion of fit-out works, whichever was earlier. As is usual, Reliable had to obtain MIDC permission. This is one area of dispute. Equally, Evonik needed a license ("consent to establish") from the Maharashtra Pollution Control Board (" MPCB "), and that permission depended on MIDC permission. Evonik says Reliable ought to have obtained the MIDC permission before-hand or 'immediately' on signing on the contract or, at any rate, before 1st January 2015. Without it, Evonik could not get MPCB permission, and without that permission, the premises were useless to it. Reliable contends that it never knew about MIDC approval being needed urgently or any time-line; that it was informed of this very late; and that there is evidence to show that MIDC approval used to come in well after the event, sometimes even after the lease or leave and license term was over. The Agreement itself had no deadline for obtaining MIDC approval. There is also an issue about Reliable not paying its property tax dues to the Navi Mumbai Municipal Corporation (" NMMC "), and whose no-dues certificate, too, was needed by the MPCB. Evonik says time ran out on it: on the one hand, Reliable neither procured the MIDC permission nor did it pay the dues and, on the other, Evonik faced the prospect of having to pay a huge amount per month for premises it could not use from January 2015. In February 2015, Evonik invoked the force majeure provision of the Agreement and terminated. This is the clause that is to be interpreted. According to Evonik, correctly read, if, for no fault of its own, it could not carry on its business from these premises, that constituted a sufficient cause to invoke the force majeure clause. Reliable contends otherwise. It says the force majeure clause is in two parts and is to be read with a recital that defines 'business'. If the premises did not exist (earthquake, fire, etc.) or were rendered useless, undoubtedly the force majeure provision would apply. But the second part, Reliable says, had nothing at all to do with the premises and operated onl

1
2
3
4
5
6
7
8
9
10
11