IN THE HIGH COURT OF BOMBAY AT NAGPUR BENCH
A.S. Chandurkar, N.B. Suryawanshi, JJ.
M/s Musale Constructions - Appellant
Versus
Vidarbha Irrigation Development Corporation - Respondent
Writ Petition No. 2209 of 2020; Writ Petition (St) No. 7625 of 2020, 7626 of 2020
Decided On : 29-10-2020
Royalty Charges - Construction Business - Clause 33, Clause 36, Clause 36(A) - The court considered the impugned circular dated 17.02.2020 and the terms of the tender agreements/contracts entered into between the petitioner and the first respondent in 2011 and 2014. It held that the impugned circular cannot be made applicable retrospectively to the contracts and that the petitioner's case would be governed by the tender agreements/contracts. The court restrained the respondents from deducting price escalation charges on Royalty from the petitioner's bills.
Fact of the Case:
The petitioner, a construction business partnership firm, sought quashing of Circular No. 9 dated 17.02.2020, issued by the respondent no. 1-V.I.D.C. The petitioner had entered into tender agreements/contracts with the first respondent for construction projects, and the dispute arose regarding the deduction of royalty charges and price escalation in royalty charges from the running bills.
Finding of the Court:
The court found that the impugned circular cannot be made applicable retrospectively to the contracts entered into between the petitioner and the first respondent in 2011 and 2014. It held that the petitioner's case would be governed by the tender agreements/contracts and restrained the respondents from deducting price escalation charges on Royalty from the petitioner's bills.
Issues: The main issue was whether the impugned circular dated 17.02.2020 could be retrospectively made applicable to the petitioner's case or whether the petitioner's cases would be governed by the terms and conditions of the tender agreements/contracts.
Ratio Decidendi: The court held that the impugned circular cannot be made applicable retrospectively to the contracts entered into between the petitioner and the first respondent in 2011 and 2014. It emphasized that the terms of the tender agreements/contracts would govern the case of the petitioner in respect of payment of royalty and price escalation in royalty charges.
Final Decision: The court declared that the impugned circular dated 17.02.2020 shall not apply to the case of the petitioner and restrained the respondents from deducting price escalation charges on Royalty from the bills of the petitioner.
JUDGMENT
N. B. Suryawanshi, J. - Rule. Rule made returnable forthwith. Heard finally by consent of learned counsel appearing for the parties.
2. Since in all these three petitions, the challenges raised, so also the grounds of challenge are same, they are heard together and are decided by this common judgment. The petitioner in these three petitions seeks quashing of Circular No. 9 dated 17.02.2020, issued by the respondent no. 1-V.I.D.C.
3. The petitioner is a partnership firm doing construction business and has been taking contracts from Government, first respondent and other authorities. The first respondent is a Corporation constituted for removing backlog of irrigation and for carrying out various irrigation projects in Vidarbha region. The first respondent from time to time issued tender notices in respect of construction of various projects. The petitioner filled in tenders and three tenders of the petitioner were accepted as follows :-
i) Construction of earthwork and structure along Minor-1 RD 2350M and its sub minor, Minor-2 L RD-3090M and its sub minor, tail minor RD-4330 and its sub minor of distributory D-5 at RD-5850 on Gosikhurd Righ Bank Canal.
ii) Construction of earthwork and structure TAS Minor No. 2 offtaking from main canal of Mokhaburdi Lift Irrigation Scheme.
iii) Work of construction of dam and head regulator of Shirud M.I. tank, Hinganghat, Dist. Wardha.
Accordingly, tender agreements/contracts were executed between the petitioner and respondent no. 1 and work orders were issued in favour of the petitioner on 27.05.2014, 19.12.2011 and 17.06.2014 respectively.
4. In accordance with the terms of the contract, the royalty charges were being deducted from the running bills of the petitioner. So far as escalation in the royalty charges are concerned, the same were calculated in accordance with the terms of the contract. The governing council of the first respondent in its 55th meeting dated 24.02.2014, passed resolution no. 55/6. On that basis, a circular dated 28.03.2016 was issued wherein, it was provided that from the bills of the contractor, the difference of price escalation in the royalty be recovered and proposal for refund of difference amount of increase in the royalty rates be submitted along with the demand for funds for payment of the bills.
On 16.11.2016, the Executive Engineer of first respondent addressed a communication to the Chief Engineer, Water Resources Department, Amravati by giving reference to a letter of Regional Office dated 30.09.2016. It was stated that the price escalation on the royalty shall be applicable to the royalty rates, which are included in the tender rates and the price escalation shall not be applicable to the difference in price increase in the royalty rates. Thereafter, by giving reference to the 55th meeting of the governing council and the resolution no. 55/6, circular no. 23 was issued by the second respondent on 30.12.2017, which states that while making the payments to the contractor, on account of increase in royalty levied on minor minerals, price escalation on royalty (as stipulated in the agreement/contract) shall not be deducted.
The royalty payment was being deducted from the running bills of the petitioner and the price escalation in the royalty charges was being calculated in terms of the tender agreement/contract.
5. The second respondent on 17.02.2020 issued circular no.9, reiterating the circular dated 28.03.2016 and communication dated 06.11.2016 and canceling circular no.23 dated 30.12.2017 thereby issuing revised instructions, by placing reliance on paragraph no.17 of the judgment of the Hon'ble Supreme Court in National Highway Authority of India ..Vrs.. Progressive MVR (JV), (2018) 14 SCC 688 . As per the revised instructions while calculating the price escalation as per the circular dated 28.03.2016 and letter dated 16.11.2016, the amount of royalty was to be deducted and the price escalation was to be calculated on the remaining amount. The S
C-5 Facility and Security Services, Nagpur ...Versus Bharat Sanchar Nigam Ltd., Nagpur
Kusum Hotels (P) Limited ..Vs.. Kerla SEB
Manjeri Vijaysinh Patil ...Versus State of Maharashtra and another
National Highway Authority of India ..Vrs.. Progressive MVR (JV)
AI
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.