SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Bom) 171

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
R.D. DHANUKA, V.G. BISHT, JJ.
Valentine Maritime Ltd. and Another – Appellants
Versus
Kreuz Subsea Pvt. Ltd. and Others – Respondents
Commercial Appeal (L) Nos. 7013, 8386 of 2020, Comm. Arbitration Petition (L) No. 6973 of 2020, Interim Application (L) Nos. 7017, 8389 of 2020
Decided On : 22-01-2021

Advocates:
Advocate Appeared:
For the Appellants : Rahul Narichania, Prathamesh Kamat, Shivkumar Iyer, Ankita Sen, Aditi Maheshwari, J.P. Cama, Rajalakshmy Mohandas, Pratibha Mehta, Rajalakshmy.
For the Respondents: Aspi Chinoy, Prasad Shenoy, Prashant Asher, Bulbul Singh Rajpurohit, Nirav Shroff.

The Court has the power to grant interim measures under Section 9 of the Arbitration Act against a third party who is not a party to the arbitration agreement, if that third party is likely to be affected by the interim measures. The Court also has the power to grant interim measures to secure the amount in dispute in arbitration, which may be in the form of a bank guarantee or deposit of money in Court.

Headnote:

The Court considered the scope of interim measures under Section 9 of the Arbitration and Conciliation Act, 1996 (the "Arbitration Act") in the context of a dispute between two parties, Valentine Maritime Limited (VML) and Kreuz Subsea Private Limited (KSS), arising out of a sub-contract agreement for the laying of pipelines. The Court also considered the role of a third party, Oil and Natural Gas Corporation Limited (ONGC), which had entered into a contract with VML for the main pipeline project.

Fact of the Case:

VML and KSS entered into a sub-contract agreement for the laying of pipelines. Disputes arose between the parties, and KSS filed a petition under Section 9 of the Arbitration Act seeking interim measures to secure its claims against VML. The Court granted an interim order directing VML to deposit a certain amount with the Court or face the risk of ONGC being directed to deposit the amount out of the payments due to VML from ONGC.

Finding of the Court:

The Court held that the power of the Court under Section 9 of the Arbitration Act is wide and can be exercised against a third party who is not a party to the arbitration agreement, if that third party is likely to be affected by the interim measures. The Court also held that the Court has the power to grant interim measures to secure the amount in dispute in arbitration, which may be in the form of a bank guarantee or deposit of money in Court.

Issues: 1. Whether the Court has the power to grant interim measures under Section 9 of the Arbitration Act against a third party who is not a party to the arbitration agreement. 2. Whether the Court has the power to grant interim measures to secure the amount in dispute in arbitration.

Ratio Decidendi: 1. The Court has the power to grant interim measures under Section 9 of the Arbitration Act against a third party who is not a party to the arbitration agreement, if that third party is likely to be affected by the interim measures. 2. The Court has the power to grant interim measures to secure the amount in dispute in arbitration, which may be in the form of a bank guarantee or deposit of money in Court.

Final Decision: The Court dismissed the appeals filed by VML and ONGC against the interim order passed by the Single Judge. The Court also extended the time for VML to comply with the order and directed ONGC to deposit the amount in Court if VML failed to do so.

JUDGMENT :

R.D. DHANUKA, J.

1. By these two appeal filed under Section 37 of the Arbitration and Conciliation Act, 1996 (for short “the Arbitration Act”) both these appellants (original respondent no. 1 and respondent no. 2 respectively) have impugned the order passed by the learned Single Judge granting interim measures in favour of the respondent no. 1 (original petitioner) under Section 9 of the Arbitration Act.

2. The appellant in Commercial Appeal (L) No. 7013 of 2020 has impugned the entire order passed by the learned Single Judge whereas the appellant in Commercial Appeal (L) No. 8386 of 2020 has impugned the directions issued by the learned Single Judge in paragraph 42(e)(i) to (vi) of the order dated 11th November 2020. By consent of parties, both these appeals were heard together and are being disposed of by common order. Some of the relevant facts for the purpose of deciding these two appeals are as under.

3. On 21st August 2019, Oil and Natural Gas Corporation Limited (hereinafter referred to as “ONGC”) entered into a contract with the appellant i.e. Valentine Maritime Limited (hereinafter referred to as “VML”) for laying of 165.77 kms. subsea pipeline spread in 23 segments including associated subsea activities, Installation of 27 nos. riser, Modification of 18 nos. topside and Demolition of 86 nos. riser (redundant and replacement). On 30th October 2019, ONGC issued a Letter of Award in favour of VML. On 30th October 2019, VML issued a Letter of Acceptance appointing Kreuz Subsea Pvt. Ltd. (hereinafter referred to as “KSS”) as a Sub-contractor for subsea installation work associated with the pipeline replacement project of ONGC i.e. part of the work under ONGC-VML contract.

4. It is the case of KSS that VML failed to establish letter of credit for 20% of the Sub Contract value i.e. US$ 5.4 million during the period between October 2019 and March 2020. Only in the month of February 2020, VML issued a conditional Letter of Credit for US $ 2 million. The KSS therefore did not issue performance bank guarantee (PBG) of 12.2% i.e. US$ 2.9 million. It is the case of KSS that KSS repeatedly offered/reiterated that on the VML establishing a contractually compliant irrevocable and unconditional Letter of Credit for US $ 5.4 million, they will immediately issue a contractually compliant PBG for US $ 2.9 million.

5. It is the case of KSS that till the end of 2020, there was no dispute between KSS and VML. The KSS had received the amount of their invoice approximately US $ 12.118 Million. However, after 24th March 2020, progress of the work was affected by the Nation Wide Lockdown. There was also delay by the VML in timely delivery/supply of materials. The KSS however preserved and almost managed to maintain the pace of the work. By letter dated 14th May 2020, VML recorded its appreciation for KSS. In the month of May 2020, the KSS submitted invoices for US $ 4765570 duly supported by completion certificates signed/issued by ONGC. It is the case of the KSS that VML did not raise any dispute within the five day period as stipulated.

6. By letter dated 27th May 2020, the VML alleged that there had been one weeks’ delay by KSS in mobilisation of the Barge in February 2020 under Clause 11.2(a) and further it was entitled to provisionally withhold as liquidated damages an amount of 10% of the Contract value under Clause 11.2 (b) i.e. USD 2,567,346 until the KSS remobilised its marine spread and completed the same. Entitled to provisionally withhold as liquidated damages an amount of 10% of the Contract value under Clause 11.2 (b) i.e. USD 2,567,346 until the KSS remobilised its marine spread and completed the same. In the said letter, it was alleged by VML that as the KSS had failed to furnish a Performance Bank Guarantee for 12.20%, the VML was entitled to withhold 12.20% of the contract value i.e. US $ 2,972,900. The VML further alleged that it was not liable to make payment of the April invoices of US $ 4.765 Million.

7. It is the case

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon Back to top