SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1958 Supreme(Bom) 208

IN THE HIGH COURT OF BOMBAY
N.L. VYAS, J.
Associated Industries Ltd. – Appellant
Versus
Its Workmen (Associated Industries Kamgar Sangh) – Respondent
Adjudications Nos. 24, 89 of 1956
Decided On : 19-03-1958

Provision for rehabilitation of the plant and buildings should be made on the basis of the current price of similar new plant and buildings, and not on the basis of the book value of the existing plant and buildings.

Headnote:

BONUS - Computation - Rehabilitation of plant and buildings - Provision for - Current price of plant and buildings - How to be determined - Future life of plant and buildings - How to be estimated - Bonus for 1954 and 1955 - Whether payable.

Fact of the Case:

The company was formed in 1943 and acquired the factory as a going concern in 1947. The factory was constructed in 1933-34 and was not working for several years. The company claimed that substantial provision for rehabilitation of the plant and buildings will have to be made in the next few years, as the plant acquired from the Bhavnagar State in 1947 is very old and requires to be replaced in the course of the next three to seven years. The workmen claimed bonus equivalent to four months' basic earnings for both 1954 and 1955.

Finding of the Court:

The court held that provision for rehabilitation of the plant and buildings should be made on the basis of the current price of similar new plant and buildings, and not on the basis of the book value of the existing plant and buildings. The court also held that the future life of the plant and buildings should be estimated on the basis of the evidence of experts and the condition of the plant and buildings. The court found that there was no surplus from which bonus could be paid to the workmen for the year 1954, but there was sufficient surplus to pay bonus equivalent to three months' basic earnings to the workmen for the year 1955.

Issues: 1. Whether provision for rehabilitation of the plant and buildings should be made on the basis of the current price of similar new plant and buildings, or on the basis of the book value of the existing plant and buildings? 2. How should the future life of the plant and buildings be estimated? 3. Whether there was any surplus from which bonus could be paid to the workmen for the year 1954? 4. Whether there was sufficient surplus to pay bonus equivalent to three months' basic earnings to the workmen for the year 1955?

Ratio Decidendi: 1. Provision for rehabilitation of the plant and buildings should be made on the basis of the current price of similar new plant and buildings, and not on the basis of the book value of the existing plant and buildings. This is because the company is entitled to make provision for the replacement of the plant and buildings at their current cost, and not at their original cost. 2. The future life of the plant and buildings should be estimated on the basis of the evidence of experts and the condition of the plant and buildings. This is because the future life of the plant and buildings is a matter of expert opinion, and the court must rely on the evidence of experts to determine the future life of the plant and buildings. 3. There was no surplus from which bonus could be paid to the workmen for the year 1954. This is because the company had made substantial provision for rehabilitation of the plant and buildings, and there was no surplus left after making this provision. 4. There was sufficient surplus to pay bonus equivalent to three months' basic earnings to the workmen for the year 1955. This is because the company had made provision for rehabilitation of the plant and buildings, and there was still sufficient surplus left after making this provision.

Final Decision: The court directed that the workmen should be paid bonus equivalent to one-fourth of their basic earnings in the year 1955 within two months from the date of publication of the award.

JUDGMENT :

N.L. VYAS, J.

1. In both these references the parties are the same. In Adjudication No. 24 of 1956 the demand is for bonus for the year 1954 and in Adjudication No. 89 of 1956 the demand is for bonus for the year 1955. As the same points arise for decision in both these adjudications, common evidence was heard, and I am disposing of both these references by a common award.

2. The factory at Bhavnagar appears to have been constructed in 1933-34, though no definite evidence was produced before me on this point. The manager has given evidence and he has stated that the buildings were constructed and the plant was installed in 1933 or thereabout. Thereafter, the factory was working for about two or three years, and was then closed as it was not possible for the factory to market the finished goods outside Saurashtra because of the customs cordon at Viramgam. According to the manager, the factory was not working for several years, and ultimately it was rented by the company in 1943. The company appears to have been formed also in 1943. From 1943 to 1945 the factory was working intermittently, and almost continuously from 1945 to 1947. Towards the end of 1947 the factory was acquired as a going concern in 1947 by the company. After 1947 the factory is working continuously. Originally, the factory was producing canvas footwear, but after three, four years the company has started producing automobile components and other mechanical rubber goods. For producing the additional items, the company has made certain additions to the original plant during the period from 1948 to 1953. No dispute about bonus was ever raised before by the workmen, but it was stated by the manager in the course of his evidence that bonus was paid in some years. There is also no dispute that for the years 1954 and 1955 bonus at the rate of fifteen days' basic earnings has been paid to all the workmen. But the workmen have claimed higher bonus on the ground that during these two years the company has made substantial profits. It would appear from the statements submitted by the union that bonus equivalent to four months' basic earnings is claimed for both these years by the workmen.

3. The company has contended in its written statements in both the references that the company has not been making profits regularly, and that substantial provision for rehabilitation of the plant will have to be made in the next few years, as the plant acquired from the Bhavnagar State in 1947 is very old and requires to be replaced in the course of the next three to seven years. It is urged in the written statement that annual provision of Rs. 1.33 lakhs will have to be made for the replacement and rehabilitation of the plant and buildings. If this provision is made for both these years, it is urged, there will be no surplus left from which bonus can be paid to the workmen. In support of this contention the company has produced the report of Mr. Dalal about the present condition of the plant and about its estimated future life. On the basis of this report which is Ex. 15, the company has submitted statement Ex. 12 in which the machinery is divided into three groups:

(1) the machinery acquired from Bhavnagar State in 1947.

(2) additions made during 1948 to 1950.

(3) additions made during 1951 to 1953.

According to this statement, the company has claimed a provision of Rs. 2 lakhs annually for rehabilitation and replacement of the plant. The company has also produced the report of the architects Jamnadas and Bhide, in order to show the future life of the buildings and the amount required at current cost for replacing them. On the basis of this report the company has submitted the statement Ex. 11. On the basis of this statement the company claims an annual provision of Rs. 14,306 for replacement of buildings. A third statement Ex. 13 is submitted by the company in which Rs. 15,9

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top