2020 Supreme(Bom) 1468
IN THE HIGH COURT OF BOMBAY
K.R. Shriram, J.
State of Maharashtra - Appellants
Vs.
Karkala Venkatrai Pai - Respondent
Cri. App. No. 358 of 2007
Decided On : 21-12-2020
Important Points
Subject
Criminal Law - Corruption and Bribery
Act Referred
PREVENTION OF CORRUPTION ACT : S.13(1)(d), S.13(2), S.7
Headnote
Prevention of Corruption Act - Acquittal - Section 7, Section 13(1)(d) r/w Section 13(2) - [Section 7, Section 13(1)(d) r/w Section 13(2)] - The court discussed the demand of illegal gratification as a sine qua non to constitute the offence under Section 7 of the Prevention of Corruption Act. It emphasized that mere recovery of currency notes cannot constitute the offence unless it is proved beyond all reasonable doubt that the accused voluntarily accepted the money knowing it to be a bribe. The court also highlighted the importance of a valid previous sanction for prosecution, emphasizing that the sanctioning authority must apply its own independent mind for the generation of genuine satisfaction where prosecution has to be sanctioned or not. The court found the sanction in this case to be invalid, leading to the dismissal of the appeal.
Fact of the Case:
The prosecution alleged that the accused, a public servant, demanded illegal gratification for permitting the lifting of scrap material. The accused denied the charge, claiming that the marked currencies were planted without his knowledge. The evidence presented by the prosecution was filled with contradictions, and the sanction obtained was found to be invalid.
Finding of the Court:
The court found that the prosecution failed to prove beyond reasonable doubt the accused's voluntary acceptance of the money as a bribe. It also concluded that the sanctioning authority did not apply its own independent mind, rendering the sanction invalid. As a result, the appeal was dismissed, and the accused was acquitted.
Issues: The key issues revolved around the demand of illegal gratification, the validity of the previous sanction for prosecution, and the sufficiency of the evidence presented by the prosecution.
Ratio Decidendi: The court emphasized that the demand of illegal gratification is essential to constitute the offence under Section 7 of the Prevention of Corruption Act. It also highlighted the importance of a valid previous sanction for prosecution, stating that the sanctioning authority must apply its own independent mind for genuine satisfaction. The court's decision was based on the lack of proof of the accused's voluntary acceptance of the money as a bribe and the invalidity of the sanction.
Final Decision: The appeal was dismissed, and the accused was acquitted. The Government/Appropriate Authority was directed to pay all pensionary or other benefits/dues stalled, and if promotions or increments of the accused were affected, the concerned Authority/Department was instructed to factor in all entitlements and pay the amounts accordingly within 30 days.
Advocate Appeared:
For the Appellant : Anamika Malhotra, APP
For the Respondents: Indrajeet Joshi
ORDER :
K.R. Shriram, J.
1. This is an appeal impugning an order and judgment dated 28 August, 2004 passed by the Special Judge, Kolhapur acquitting respondent (Hereinafter referred as accused) of offence punishable under Section 7 (Public servant taking gratification other than legal remuneration in respect of an official act), Section 13(1)(d) r/w Section 13(2) of the Prevention of Corruption Act, 1988.
2. It is the case of the prosecution that one Mahesh Mohanlal Kothari (P.W. 1) resident of Pune was a scrap dealer and along with his friend one Santosh Jewarechand Sethia (P.W. 4) was carrying on business in the name and style as "Siddhesh Traders". Siddhesh Traders used to buy scrap from various parties including Government offices. In the course of their business, they came across a notice inviting tender dated 04/08/2000 from Metal Scrap Trade Corporation Ltd. (hereinafter referred to as M.S.T.C.) which is a Government of India undertaking. Siddhesh Traders submitted its tender for Rs. 4,31,000/- and the tender was accepted. Acceptance of the bid was conveyed by M.S.T.C. by an office order dated 14/09/2000 and Siddhesh Traders was directed to deposit a sum of Rs. 4,96,943/- by way of demand draft with M.S.T.C. Upon making that payment M.S.T.C. issued a delivery order in favour of Siddhesh Traders on 29/09/2000.
3. To pick up the scrap, complainant P.W. 1, his friend Sethia P.W. 4 and nine labourers went to Kolhapur on 05/10/2000 to the place where materials were kept. There they meet one Assistant General Manager, Planning Mr. Kulkarni (who has not been examined) and after perusing papers submitted by them, Mr. Kulkarni orally granted permission to break the machinery as mentioned in the tender notice. The Department of Telecommunication had decided to scrap the A.C. Plant and other scrap articles. The work of breaking started immediately and thereafter P.W. 1 and P.W. 4 went back to Pune. On 16/10/2000 P.W. 1 went to Kolhapur and met Mr. Kulkarni once again for permission to lift the broken scrap material. At that time Kulkarni told P.W. 1 that the file was with Deputy General Manager Mr. Sanjay Choudhari and they should meet him. At that time on 16/10/2000 P.W. 1 complainant's supervisor, one Mr. Rajesh Tiwari who also has not been examined, accompanied P.W. 1. They both went to Mr. Choudhari who informed them that the file is with General Manager Mr. Koli. Therefore, on 17/10/2000, P.W. 1 and Mr. Tiwari went to meet Mr. Koli. But as they could not meet Mr. Koli they went back to Mr. Choudhari, who also has not been examined, and informed him that they could not meet Mr. Koli. Mr. Choudhari advised them to meet Internal Legal Adviser Mr. Pai-accused. Therefore, P.W. 1 and Mr. Tiwari went to meet accused at 6.00 p.m. on 17/10/2000 in his cabin and narrated the entire facts to accused. They requested accused to permit them to lift the scrap and move it to their godown. At that time, it is alleged that accused told P.W. 1 "Do you understand or not?" before lifting the material you have not paid the amount of 5% and unnecessarily you are visiting office for four to five days, you should have met me earlier. You come with Rs. 20,000/- and I will give permission for lifting the scrap material. The complainant at that time told accused that they have already sustained loss in this transaction, nine labourers were sitting idle and therefore, they be permitted to lift the material soon. Thereupon, accused alleged to have told complainant to bring Rs. 20,000/- and take permission or else their tender will be cancelled and complainant will have to face unnecessary problems. When complainant requested accused to reduce the amount, accused reduced the amount to Rs. 15,000/- and told the complainant to bring the amount at 3.00 p.m. on 20/10/2000. Accused also told complainant that unless the amount is brought, his work will not be done.
As accused felt there was no other alternative, he approached the Anti Corruption Bureau, Kolhapur offi