2026 Supreme(Bom) 754

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
Sharmila U. Deshmukh, J.
CCI Projects Private Limited - Appellant
Versus
Mr. Sriram Krishnan - Respondent
Second Appeal No. 472 of 2021
Decided On : 18-06-2026

Important Points

Section 18 of the Real Estate (Regulation and Development) Act, 2016 confers an unconditional, absolute statutory right to interest for delayed possession. This special legislation overrides the general requirements of the Indian Contract Act, 1872, and is not subject to waiver or the necessity of notice.

Subject

Property Law - Real Estate Regulation

Act Referred

CONTRACT ACT : S.55, S.62
REAL ESTATE REGULATION AND DEVELOPMENT ACT : S.12, S.14, S.18, S.18(1)(a), S.19, S.19(4), S.31, S.38, S.89
MAHARASHTRA REAL ESTATE REGULATION AND DEVELOPMENT RECOVERY OF INTEREST, PENALTY, COMPENSATION, FINE PAYABLE, FORMS OF COMPLAINTS AND APPEAL, ETC. RULES : R.6, R.6(2)(h)
CIVIL PROCEDURE CODE : S.96(3)

Headnote

(A) Real Estate (Regulation and Development) Act, 2016 - Section 18 - Indian Contract Act, 1872 - Sections 55, 62 and 88 - Maharashtra Ownership Flats Act, 1963 - Section 4 - Delayed possession of residential unit - Claim for interest - Whether acceptance of delayed possession disentitles allottee from claiming compensation - Statutory right to interest under the 2016 Act is an unqualified and absolute right, which cannot be defeated by the doctrine of waiver or acquiescence, nor is it dependent on notice under the general law of contracts. (Paras 25, 26, 30, 31, 35)

(B) Appeal - Scope and maintainability - Plea of concession - Requesting an order based on parity with an earlier decision does not constitute an express waiver or abandonment of a statutory right - Estoppel does not apply against a mandatory statutory provision. (Paras 56, 57, 58)

Facts of the case:
The allottees filed a complaint seeking possession and interest for delay against the promoter who failed to deliver the flat by the agreed date. The promoter contended that the allottees had accepted revised timelines and payment schedules, thereby waiving their right to interest under the general law. The initial authority granted liberty to demand interest at a later stage, which the appellate authority modified to award interest from the original due date.

Findings of Court:
Section 18 of the 2016 Act confers an unconditional right to interest for every month of delay. This provision prevails over general contract law principles. The allottees' request for parity with other co-allottees did not amount to a legally binding waiver of their statutory entitlement.

Issues: The primary issues were whether Section 55 of the Contract Act impacts the right to interest under the 2016 Act, whether force majeure events (pandemic) justify the delay, and whether the appeal was maintainable following the allottees' request for an identical order to a prior case.

Ratio Decidendi: Section 18 of the 2016 Act constitutes a special law offering an unqualified statutory remedy to allottees. In contrast, Section 55 of the Contract Act imposes conditions for compensation that are inconsistent with the 2016 Act. By virtue of the overriding effect of the 2016 Act, the allottees' right to interest remains enforceable regardless of whether they continued with the project or accepted delayed performance. Furthermore, citing parity with other orders does not preclude a party from exercising their statutory right to appeal.

Result: Second Appeal dismissed.

Advocates Appeared:
For the Appellant : Mr. Rubin Vakil, Mr. Abir P. and Mr. Kartik Joshi i/b Wadia Ghandy and Co.
For the Respondent: Mr. Bhavin Gada i/b Mr. Chirag Desai

Table of Content
1. factual history regarding real estate project delays and initial rera orders. (Para 1 , 3 , 4 , 5 , 6 , 7 , 8)
2. contentions regarding contract act vs. rera act and maintainability of appeal. (Para 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21)
3. rera section 18 provides absolute rights overriding section 55 contract act. (Para 22 , 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46 , 47 , 48 , 49 , 50 , 51 , 52 , 53 , 54 , 55 , 56 , 57 , 58 , 59 , 60 , 61)
4. dismissal of appeal and procedural orders. (Para 62 , 63 , 64)

JUDGMENT :

Sharmila U. Deshmukh, J.

1. The Second Appeal is filed at the instance of the promoter, challenging the judgment dated 10th March, 2021 passed by Maharashtra Real Estate Appellate Tribunal, Mumbai [for short, “Appellate Tribunal”] quashing the order dated 31st January, 2019 in Complaint No. CC006000000056115 passed by MahaRERA and directing the promoters to pay interest for delayed possession. For sake of brevity, the parties are referred to as Promoter and allottees.

2. By order dated 5th March, 2026, this Court framed the following substantial questions of law:

“(i) Whether in view of provisions of Section 55 of the Indian Contract Act, 1872 , the acceptance of delayed performance would disentitle the promisee from compensation claimed on account of non-performance of contract at the agreed time?

(ii) Whether the provisions of Section 18 of the Real Estate (Regulation and Development) Act, 2016 will override the provisions of Section 55 of the Indian Contract Act, 1872 ?

(iii) Whether in view of provisions of Section 32 of Indian Contract Act, 1872 , the force majeure events listed in the contract could have been ignored?”

(iv) Whether the Appeals would be maintainable at instance of Respondents in view of the concession given by the Respondents that the issue of interest will be considered subsequent to the completion of the project?

3. The facts of the case are that allottees filed a complaint under Section 31 of the Real Estate (Regulation and Development) Act, 2016 [for short, “RERA Act”] with the Maharashtra Real Estate Regulatory Authority [for short, “1st Authority”] stating that the allottees had booked an apartment in building known as Wintergreen in the project developed by the Promoters. On 18th November, 2014, an agreement was entered into between the promoters and the allottees and as per Clause 17 of the agreement, the promoters agreed to give possession to the allottees on or before 30th June, 2017.

4. The grievance was that till the filing of the complaint, the possession of the flat was not given. The total flat consideration was Rs. 1,95,06,060/- and the allottees had paid part consideration of Rs. 1,85,32,899/- and apart from that had also paid the sum of Rs. 10,09,220/- towards stamp duty and registration charges on 18th September, 2014. The service tax, VAT, GST and TDS amounts were also paid and thus the allottees have paid sum of Rs. 2,05,89,715/- to the promoter.

5. As per the project registration under RERA, the proposed date of completion of project was 31st December, 2018 and revised proposed date of completion was 31st December, 2019. The allottees sought the relief of handing over possession of the apartments along with payment of interest for delayed possession from 1st July, 2017 till the handing over possession.

6. By order dated 31st January, 2019, the 1st Authority noted the submission of promoters that the construction work of project could not be completed for reasons beyond the promoter’s control and that the construction would be completed before the revised completion date set out in the registration web page. The submission of learned counsel for complainants before the 1st Authority was that in Complaint No. CC006000000054636, the 1st Authority had directed the Promoter to handover possession by December, 2019 allowing the Promoter in the interest of completing the pro

1
2
3
4
5
6
7
8
9
10
11