2026 Supreme(Bom) 756

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
Sharmila U. Deshmukh, J.
CCI Projects Private Limited - Petitioner
Versus
Mr. Rajesh Kumar Chaudhary - Respondent
Second Appeal No. 479 of 2021
Decided On : 18-06-2026

Important Points

The right to interest for delayed possession under the real estate legislation is an absolute statutory right, which is not subject to the notice requirements of the contract act, even if the allottee remains part of the project or accepts delayed performance.

Subject

Real Estate Law - Delayed Possession and Interest

Act Referred

CONTRACT ACT : S.32, S.55, S.62
REAL ESTATE REGULATION AND DEVELOPMENT ACT : S.11(4)(b), S.11(d), S.11(e), S.18, S.18(1)(a), S.19(4), S.31, S.88
MAHARASHTRA OWNERSHIP OF FLATS ACT : S.4
MAHARASHTRA REAL ESTATE REGULATION AND DEVELOPMENT RECOVERY OF INTEREST, PENALTY, COMPENSATION, FINE PAYABLE, FORMS OF COMPLAINTS AND APPEAL, ETC. RULES : R.6, R.6(2)(h)

Headnote

(A) Real Estate (Regulation and Development) Act, 2016 - Sections 18, 31, 88 and 89 - Indian Contract Act, 1872 - Sections 55, 62 - Delayed possession of residential unit - Interpretation of statutory rights regarding compensation - The right afforded to an allottee to claim interest for delay under the special legislation is an unqualified and absolute statutory right which remains unaffected by any conduct like acceptance of delayed performance or lack of formal protest. (Paras 25, 26, 33, 46)

(B) Conflict of Laws - Special enactment versus general law - Where there exists an inconsistency between the provisions of the real estate legislation and the contract act regarding the prerequisite of notice for claiming compensation, the former, being a special enactment designed to protect consumers, takes precedence by virtue of its overriding effect. (Paras 50)

(C) Force Majeure - Scope of application - Pandemic-related delays occurring after the original agreed deadline cannot be invoked by a developer to escape liability for interest payments where the project was already delayed prior to such events. (Paras 51, 52)

Facts of the case:
A dispute arose between a developer and flat purchasers regarding the failure to deliver possession of a residential unit by the date stipulated in the agreement. Even though the purchasers accepted payments based on revised schedules communicated by the developer, they filed a complaint seeking possession and interest for the delay. The regulatory authority initially allowed the complaint but provided liberty to claim interest later. The appellate tribunal subsequently granted interest from the original due date. The developer appealed, contending that the purchasers had accepted delayed performance without issuing notice, thereby forfeiting their right to claim compensation under the contract law.

Findings of Court:
The court determined that the real estate legislation serves as a special law that provides a complete code for protecting the interests of consumers in the real estate sector. The right to receive interest for delayed possession is an absolute statutory right that is not contingent upon the issuance of any notice by the purchaser. Unilateral extensions of deadlines by the developer are not binding.

Issues: (i) Whether acceptance of delayed performance disentitles an allottee from claiming compensation under the contract law in the absence of notice; (ii) whether the real estate legislation overrides the contract law; and (iii) whether force majeure clauses could be invoked for events occurring after the contractual deadline for possession.

Ratio Decidendi: The court held that Section 18 of the real estate legislation creates an unqualified right to interest for delayed possession which cannot be restricted by general contract law principles. Section 89 of the legislation explicitly provides an overriding effect, rendering the notice requirement under Section 55 of the contract act inapplicable to this statutory remedy.

Result: Second appeal dismissed.

Advocates Appeared:
For the Petitioner:Mr. Naushad Engineer, Senior Advocate i/b Wadia Ghandy and Co.
For the Respondent: Mr. Harshad Bhadbhade

Table of Content
1. factual background regarding delayed possession claims under rera. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8)
2. parties' arguments on section 55 contract act vs. section 18 rera. (Para 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22)
3. section 18 rera confers an unqualified absolute right to interest. (Para 23 , 24 , 25 , 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33 , 34 , 35 , 36 , 37 , 38 , 39 , 40 , 41 , 42 , 43 , 44 , 45 , 46)
4. rera as a special enactment overrides the general contract act. (Para 47 , 48 , 49 , 50)
5. force majeure claims regarding delayed possession periods are rejected. (Para 51 , 52 , 53 , 54 , 55)

JUDGMENT :

Sharmila U. Deshmukh, J.

1. The Second Appeal is filed at the instance of the promoter, challenging the judgment dated 10th March, 2021 passed by Maharashtra Real Estate Appellate Tribunal, Mumbai [for short, “Appellate Tribunal”] quashing the order dated 17th September, 2018 in Complaint No. CC006000000054636 passed by MahaRERA and directing the promoters to pay interest for delayed possession. For sake of brevity, the parties are referred to as Promoter and allottees.

2. By order dated 11th December, 2025, this Court framed the following substantial questions of law:

(i) Whether in view of provisions of Section 55 of the Indian Contract Act, 1872 , the acceptance of delayed performance would disentitle the promisee from compensation claimed on account of non-performance of contract at the agreed time?

(ii) Whether the provisions of Section 18 of the Real Estate (Regulation and Development) Act, 2016 will override the provisions of Section 55 of the Indian Contract Act, 1872 ?

(iii) Whether in view of provisions of Section 32 of Indian Contract Act, 1872 , the force majeure events listed in the contract could have been ignored?

3. The facts of the case are that allottees filed a complaint under Section 31 of the Real Estate (Regulation and Development) Act, 2016 [for short, “RERA Act”] with the Maharashtra Real Estate Regulatory Authority [for short, “1st Authority”] stating that the allottees had booked an apartment in building known as Wintergreen in the project developed by the Promoters. On 1st October, 2011, the allotment letter was issued by the Promoters which mentioned the date of possession as 30th June, 2015 with grace period of six months. The payment schedule which was mentioned in Annexure-1 of allotment letter provided for construction based payment schedule with payment of 5% which would be the balance payable on offer for possession. On 26th March, 2013, an agreement was entered into between the promoters and the allottees and as per Clause 17 thereof, the promoters agreed to give possession to the allottees on or before February, 2016.

4. The grievance was that till the filing of the complaint which was on 23rd May, 2018, the possession was not given. The total flat consideration was Rs. 1,82,18,640/- and the allottees had paid part consideration of Rs 1,73,07,708/- and apart from that had also paid the sum of Rs. 9,44,160/- towards stamp duty and registration charges on 26th March, 2013. The service tax, VAT, GST and TDS amounts were also paid and thus the allottees have paid sum of Rs. 1,91,59,215/- to the promoter.

5. As per the project registration under RERA, the proposed date of completion of project was 31st December, 2018 and revised proposed date of completion was 31st December, 2019. The allottees sought the relief of handing over possession of the apartments along with payment of interest at the rate of 10.35% on the amount paid from the agreed date of possession i.e. from 1st March, 2016 till the date of actual possession and legal expenses of Rs. 1,00,000/-.

6. By order dated 17th September, 2018, the 1st Authority noted the submission of promoters that the construction work of project could not be completed for reasons beyond the promoter’s control and that the construction would be completed before the revised completion date set out in the registratio

1
2
3
4
5
6
7
8
9
10