2026 Supreme(Bom) 914

IN THE HIGH COURT OF JUDICATURE AT BOMBAY
Manish Pitale, Shreeram V. Shirsat, JJ.
M/s. Citron Infraprojects Limited - Petitioners
Versus
IFCI Limited, through its Authorised Officer & Ors. - Respondents
Writ Petition (L) No. 14684 of 2026
Decided On : 29-04-2026

Act Referred

SECURITISATION AND RECONSTRUCTION OF FINANCIAL ASSETS AND ENFORCEMENT OF SECURITY INTEREST ACT : S.13(2), S.13(4), S.14, S.26(d), S.31, S.31(j)

Advocates Appeared:
For the Petitioner: Mr. Yohaan Limathwalla a/w Ms. Ravleen Sabharwal (through V.C.), Ms. Aarushi Yadav (through V.C.), Mr. Prakash Tandon (through V.C.) and Ms. Yashi Bhatt i/by R. S. Justicia Law Chambers
For the Respondent: Mr. Charles De Souza a/w Mr. Nikhil Rajani i/by M/s. V. Deshpande and Co.

ORDER :

Manish Pitale, J.

1. The subject matter of challenge in this writ petition is an order passed by the Debts Recovery Tribunal-II, Mumbai (DRT), whereby interlocutory application bearing IA No. 981 of 2026 has been rejected. The said application was filed in pending Securitisation Application No. 487 of 2025. By the said interlocutory application, the petitioner No.1 had prayed for stay of taking over of possession of a property (secured asset) at the instance of respondent No.1 (secured creditor), in pursuance of steps taken under the Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002 (Securitisation Act).

2. The petitioners have filed this petition directly, without taking recourse to the alternative remedy of filing an appeal before the Debts Recovery Appellate Tribunal (DRAT) on the ground that respondent No.1 (secured creditor) could not have taken recourse to the provisions of the Securitisation Act, due to Section 31(j) thereof and that the DRT failed to appreciate that the entire action of respondent No.1 was rendered without jurisdiction.

3. Considering the rival stands taken before this Court, detailed reference to facts is not necessary, other than stating that the respondent No.1, upon defaults committed by the petitioner No.1 in repayment of credit facilities, was constrained to issue notice dated 30.09.2021 under Section 13(2) of the Securitisation Act. Thereafter, when the petitioner No.1 failed to discharge its liability in full within the period specified in the notice under Section 13(2) of the Securitisation Act, respondent No.1 was constrained to take action under Section 13(4) thereof and took symbolic possession of the secured asset. The matter proceeded to the Magistrate under Section 14 of the Securitisation Act, who passed an order dated 18.08.2025 for taking physical possession of the secured asset.

4. At this stage, on 24.09.2025, the petitioner No.1 filed the said securitisation application and when the order passed by the Magistrate under Section 14 of the Securitisation Act was on the verge of being executed, the said IA No. 981 of 2026 was filed in the pending securitisation application.

5. The petitioner No.1 contended that interim stay was necessary as the respondent No.1 could not have taken recourse to the provisions of the Securitisation Act. Firstly, on the ground that registration of the security interest of respondent No.1 in the Central Registry of Securitisation Asset Reconstruction and Security Interest of India (CERSAI) was obtained after the action under the Securitisation Act had been undertaken. Secondly, it was contended that even though at the time of issuance of notice under Section 13(2) of the Securitisation Act, the amount due was more than 20% of the principal amount and interest thereon, in the light of payments made by the petitioner No.1 after initiation of action under Section 13(2) of the Securitisation Act, the amount due had clearly gone below 20% and therefore, further action under the Securitisation Act was not sustainable.

6. The DRT rejected both the grounds and on that basis, rejected the interlocutory application by the impugned order.

7. Mr. Yohaan Limathwalla, the learned counsel appearing for the petitioners submitted that the DRT failed to appreciate the admitted facts on record and wrongly rejected the interlocutory application for stay filed on behalf of the petitioners. It was submitted that recourse to the provisions of the Securitisation Act was no longer available to the respondent No.1 by operation of Section 31(j) of the Securitisation Act and therefore, on this short ground, the impugned order deserves to be set aside.

8. On the first ground pertaining to CERSAI registration, it was claimed that although the notice under Section 13(2) was issued on 30.09.2021, the CERSAI registration was dated 30.10.2025. The same was obtained after the securitisation application was filed by the petitioner No.1 before