2007 (4) Crimes 735 (Ori.)
ORISSA HIGH COURT
R.N. Biswal, J.
M/s Korp Gems (India) Pvt. Limited
and Anr. —Petitioners
versus
M/s Suraj Products Ltd. —Opp. Party
Criminal M.C. No. 2992 of 2006
Decided on 19-6-2007
Held: Learned counsel for the petitioners, further submitted that the entire dispute being civil in nature, the criminal proceeding should be quashed. He further submitted that there was an arbitration clause in the agreement entered into between NOVACORP and CARGO LINERS on 27.9.2006, so the dispute ought to have been referred to the arbitrator. It is the established principle of law that if the complaint petition, initial statement of the complainant recorded under Section 200 of Cr.P.C. and the evidence, if any, recorded under Section 202 of Cr.P.C. make out any offence, then cognizance can be taken of the said offence. Furthermore, there is no absolute bar for running of criminal proceeding and civil proceeding simultaneously. (Para 6)
In the instant case it cannot be said that continuance of the criminal proceeding against the petitioners would be abuse of process of the Court with regard to arbitration clause, it can be said that the said clause is there to refer the matter to the arbitrator in case of violation of the terms and condition on that agreement. In the present case, cognizance has been taken under Section 138 of the N.I. Act, because the cheque issued was bounced. So, it has no connection with the arbitration clause. (Para 7)
(ii) Negotiable Instruments Act, 1881—Section 138—Prosecution for dishonour of cheque—Territorial jurisdiction of Court—Notice of demand was issued from Rourkela and petitioner accused failed to make payment—One of the causes of action arose under jurisdiction of Court at Rourkela—Complaint filed before that Court could not be quashed on ground that Court did not hold jurisdiction.
Result: Petition dismissed.
JUDGMENT
R. N. Biswal, J.—The petitioners call in question the order dated 1.12.2006 passed by learned S.D.J.M., Rourkela in I.C.C.No.448 of 2006 taking cognizance of the offence under Section 138 of the Negotiation Instrument Act (hereinafter referred to as “the N.I. Act”) against them. The opposite party company filed the aforesaid complaint case against petitioner No.1, a company having their office at Kolkata and the petitioner No.2, the Director of the said company on the allegation that petitioner No.1 through petitioner No.2 used to purchase iron ore mines from them. On 6.10.2006 petitioner No.2 issued cheque No.883167 for Rs.20,00,000 drawn on Allahabad Bank, Park Street, Kolkata, in favour of opposite party towards payment of outstanding dues. Opposite party company through its representative deposited the said cheque on 6.10.2006 in their accounts maintained with HDFC Bank Limited, Kolkata Branch, but the same returned unpaid on 10.10.2006 due to stop payment advice. So the opposite party company served a notice through their advocate demanding payment of the cheque amount under Registered Post No.1753 dated 26.10.2006, the receipt of which was acknowledged by petitioner No.2 on 30.6.2006. In spite of receipt of the demand notice, petitioner did not pay the cheque amount of Rs.20,00,000 within the statutory period. Hence, they filed the aforesaid complaint case on the allegation of commission of offence under Section 138 of the N.I. Act. After going through the complaint petition, initial statement of the complainant and the evidence of witnesses recorded under Section 202 of Cr.P.C., the trial Court took cognizance of the offence under Section 138 of the N.I. Act against the petitioners, which is under challenge in the present CRLMC.
2. At the out set, learned counsel for the petitioners submitted that since no cause of action arose under the territorial jurisdiction of the learned S.D.J.M., Rourkela, he should not have taken cognizance of the offence under Section 138 of the N.I. Act against the petitioners. But, on perusal of the complaint petition, it is found that the opposite party company have their registered office in village Barapali in the District of Sundargarh and the City Office at W-7, Civil Township Rourkela-4. The demand notice was also issued from Rourkela. In the decision K. Bhaskaran v. Sankaran Vaidhyan Bala and another1 the apex Court held as follows:
“The offence under Section 138 of the Act can be completed only with the concatenation of a number of acts. Following are the acts which are components of the said offence (1) Drawing of the cheque, (2) Presentation of the cheque to the bank, (3) Returning the cheque unpaid by the drawee bank, (4) Giving notice in writing to the drawer of the cheque demanding payment of the cheque amount, (5) failure of the drawer to make payment within 15 days of the receipt of the notice.
It is not necessary that all the above five acts should have been perpetrated at the same locality. It is possible that each of those five acts could be done at 5 different localities. But concatenation of all the above five is a sine qua non for the completion of the offence under Section 138 of the Code. In this context a reference to Section 178 (d) of the Code is useful. It is extracted below:
“Where the offence consists of several acts done in different local areas, it may be inquired into or tried by a Court having jurisdiction over any of such local areas.”
Thus it is clear, if the five different acts were done in five different localities anyone of the Courts exercising jurisdiction in one of the five local area can become the place of trial for the offence under Section 138 of the Act. In other words, the complainant can choose anyone of those Courts having jurisdiction over anyone of the local areas within the territorial limits of which anyone of those five acts was done. As the amplitude stands so widened and so expansive it is an idle exercise to raise jurisdiction
SupremeToday
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.