Important Points

The sufficiency of pleadings to establish a complete cause of action against a guarantor and the scope of claims for interest under summary judgment proceedings.

Subject

Civil Law - Commercial Law

Act Referred

CIVIL PROCEDURE CODE : O.47 R.1, O.37 R.2, O.37 R.3(5)
NEGOTIABLE INSTRUMENTS ACT : S.138

Headnote

Review - Summary Judgment - Companies Act - Order 37 Rule 3 (5) CPC - Negotiable Instruments Act,1881 - Section 138 - Order 37 CPC

Fact of the Case:

The plaintiff sought a summary judgment against the defendants for dishonoured cheques issued by defendant No. 1, claiming a decree in the sum of Rs. 2,36,02,600/- with interest. The court found that the plaintiff failed to establish the personal liability of defendant No. 3 and claimed interest beyond the scope of Order 37 CPC.

Finding of the Court:

The court found that the plaintiff's pleadings lacked assertions necessary to establish a complete cause of action against the guarantor and that the claim for interest exceeded the scope of the summary judgment under Order 37 CPC.

Issues: The issues revolved around the sufficiency of the plaintiff's pleadings to establish the personal liability of defendant No. 3 and the claim for interest beyond the scope of the summary judgment under Order 37 CPC.

Ratio Decidendi: The court held that to establish a complete cause of action against a guarantor, specific pleadings regarding the guarantee, default in payment, and the guarantor's liability are necessary. Additionally, the court found that the claim for interest exceeded the scope of the summary judgment under Order 37 CPC.

Final Decision: The court dismissed the application for review and granted leave to defend to defendant No. 3, citing insufficiency of the plaintiff's pleadings and the claim for interest beyond the scope of the summary judgment under Order 37 CPC.

PRADEEP NANDRAJOG, J.

( 1 ) BY the present application under Order 47 Rule 1 CPC, plaintiff seeks review of the order dated 11. 2. 2005 by which order IA. No. 4016/03 filed defendant no. 3 under Order 37 Rule 3 (5) CPC was disposed of. Defendant No. 3 was granted unconditional leave to defend.

( 2 ) REVIEW is principally sought on the ground that the plaintiff did not get an opportunity to present its case for the reason when IA. No. 4016/03 came up for hearing on 4. 2. 2005, counsel for defendant No. 3 made a request for an adjournment. Suit being of the year 1998, adjournment was declined. Defendant No. 3 was directed to file written submissions within three days. Counsel for the plaintiff was given two days time to respond thereto. IA. No. 4016/03 was reserved for orders. No written submissions being received from either party, this court went through the pleadings of the parties on its own and vide order dated 11. 2. 2005 disposed of ia. No. 4016/03. It is stated in the present application that the plaintiff was awaiting written submissions from the defendants and for said reason, plaintiff did not file its written submissions.

( 3 ) ON 18. 5. 2005, I heard the parties on the issue of leave to defend in the context whether order dated 1. 2. 2005 needs to be reviewed/recalled.

( 4 ) SUIT seeks a summary judgment against the defendants. As per the averments made in the plaint, defendant No. 1 is a company registered under the companies Act. Defendant No. 2 is its Managing Director and defendant No. 3 is its director. As per the plaint, defendants 2 and 3 secured credit facilities from the plaintiff on behalf of defendant No. 1. Material used to be lifted from the stockyard of the plaintiff. 22 cheques were issues totalling Rs. 2,07,95,253/ -. Cheques were issued on behalf of defendant No. 1 under the signatures of defendants 2 and 3. Cheques were dishonoured. Principle amount payable is stated to be the sum covered by said 22 cheques i. e. Rs. 2,07,95,253/ -. Interest @ 27% per annum calculated from 22. 7. 1998 till date of suit is stated to be Rs. 28,07,347/ -. Suit, therefore, claims a decree in the sum of Rs. 2,36,02,600/- together with interest @ 27% per annum.

( 5 ) WHILE allowing IA. 4016/03, on reading of the plaint I had noted that there was no averment in the plaint that defendant No. 3 stood as a guarantor. I had read the plaint and held that a meaningful reading of the plaint shows that liability was being fastened on defendant No. 3 because he was a Director of defendant No. 1. That defendant No. 3 had signed some cheques from the account of defendant No. 1 would not make him personally liable in a civil action for recovery of the amount from defendant No. 1.

( 6 ) I was wrong in my observation pertaining to there being no averment against defendant No. 3 as a guarantor for the reason, as point out at the hearing, in para 8 of the plaint it is stated that defendant No. 3 as well as defendant No. 2 were guarantors.

( 7 ) REASON why said averment of the plaintiff was overlooked is that the plaintiff has pleaded cause of action only on the cheques and had otherwise made averments in the plaint which are far from satisfactory. Averments made in paras 3 to 9 of the plaint are relevant and may be noted : wÆ’u¢w¢ââ‚Å¡u 3. The defendant No. 2 is the Managing Director and defendant No. 3 is the director of defendant No. 1 company respectively and had sought and secured credit facilities on behalf of defendant No. 1 and in their personal capacities from the plaintiff in respect of the dues or amounts payable to the plaintiff for the supply of various types of steel materials from time to time. The plaintiff supply different types of steel materials from time to time either by issuing offer letters and delivery orders or through railway receipts. The defendant Nos. 2 and 3 are looking after the business of defendant No. 1.

"4. THE defendant No. 2 and 3 on behalf of defendant No. 1 used to lift materials from the stockya

















1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top