PATNA HIGH COURT
N.L.Untwalia, J.
Kapildeo Narain
Versus
Sheo Prasad Singh
Miscellaneous Second Appeal No. 467 of 1958 ;
Decided On : OCTOBER 20, 1959
LIMITATION ACT, 1908 - SECTION 182(5) - TRANSFER OF DECREE - STARTING POINT OF LIMITATION - DATE OF PREPARATION AND SIGNING OF CERTIFICATE OF TRANSFER.
Fact of the Case:
The issue in this case was whether an execution case filed in a transferee court on 8-5-1956 was barred by limitation. The decree-holder had applied for transfer of the decree on 7-5-1953, and the certificate of transfer was prepared and signed on 8-5-1953.
Finding of the Court:
The court held that the execution case was not barred by limitation. It held that the final order for the purposes of Article 182(5) of the Limitation Act was the date when the certificate of transfer was prepared and signed, which was 8-5-1953.
Issues: Whether the execution case filed in the transferee court on 8-5-1956 was barred by limitation.
Ratio Decidendi: The court held that the final order for the purposes of Article 182(5) of the Limitation Act was the date when the certificate of transfer was prepared and signed, which was 8-5-1953. This was because the order directing the office to prepare the certificate was not the final order, and the application before the transferor court was not finally disposed of unless the certificate was prepared and signed.
Final Decision: The appeal was dismissed with costs.
N.L.Untwalia, J.
1. This is a miscellaneous second appeal at the instance of the judgment-debtors and the only point involved in it is as to whether the execution case filed in the transferee court on 8-5-1956 is barred by limitation. Only two more dates are necessary to be mentioned. On 7-5-1953 the court which passed the decree passed an order on the petition of the decree-holder for transfer of the decree to the transferee court, for the preparation of the transfer certificate. The certificate was actually prepared and signed on 8-5-1953.
2. It is conceded by Mr. Sinha, learned Advocate for the appellants, and, in my opinion, rightly that it is well settled now that the date of the final order passed on an application for transfer of the decree would give the fresh starting point for execution of the decree under Clause (5) of Article 182 of the Limitation Act. His contention, however, is that the final order was passed on 7-5-1953, and; therefore, the execution which was levied on 8-5-1956 in the transferee court is late by a day.
The courts below have taken the view that the final order was passed on 8-5-1953 when the certificate was actually prepared and signed, and, therefore, the execution case is not barred by limitation. In my opinion, the decision of the courts below is correct and the contention of the learned Advocate is not sound. In the case of Hafiz Uddin V/s. Firm Parshadi Lal Manohar Lal, AIR 1935 All 757, it has been held that the order directing the office to prepare a certificate of transfer "cannot be considered to have finally disposed of the application which prayed that the certificate be transmitted."
The certificate in that case was actually prepared and handed over to the decree-holder on the 8th March, 1930, although the order directing the preparation of the certificate had been passed on the 17th February, 1930. The latter date was taken to be the starting point under Article 182(5). This view finds support from a Bench decision of this Court in the case of Mahidhar Roy V/s. Kalyani Prasad Singh, AIR 1945 Pat 71.
It is important to notice four dates in that decision, On 18th June, 1936, the transmission of the decree with a certificate of non-satisfaction was ordered. The certificate of non-satisfaction was prepared on the 25th Juno, 1936. The papers were received by the transferee court on the 4th July, 1936, and apparently the final order was passed on 6th July, 1936, by the transferor court. It was held in that case that the starting point of limitation was 25th June, 1936, and the execution case, which was filed three years beyond that was held to be barred by limitation.
Mr. Sinha has endeavoured to distinguish this case on two grounds. His first submission is that the argument of Mr. P.R. Das in that case was that even if 25th June, 1936, was taken to be the date of the final order, the execution case was barred by limitation and 6th July, 1936, could not be taken to be the date of final order as was contended on behalf of the decree-holder. There was no question as to whether 18th June, 1936, or 25th June, 1936, should have been taken as the date of the final order.
There is some force in this argument. But on reading this decision as a whole, it appears to me that there was no argument and no decision that 18th June, 1936, was to be taken as the date of the final order. In absence of any other decision taking a contrary view, I read this decision to hold that 25th June, 1936, was the starting point in that case. If that be so, the view taken by the court below in the present case is well supported by authorities.
Mr. Sinha further submitted that this case of Mahidhar Roy has been dissented from in another later Division Bench case of Sheonath Prasad V/s. Bindeshwari Prasad, AIR 1950 Pat 518, and there it has been held that the date of the final order is the date when the order for transfer is made. Some observations in Mahidhar Roys case, AIR 1945 Pat 71, have been dissented from
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.