PATNA HIGH COURT
N.L.Untwalia and S.K.Jha JJ.
East Indian Coal Co.Ltd.
Versus
Union Of India
Appeal from Original Order No. 267 of 1967 ;
Decided On : AUGUST 31, 1973
COAL BEARING AREAS (ACQUISITION AND DEVELOPMENT) ACT, 1957 - SEC. 4, 5, 7, 9, 10, 13, 15, 16, 20 - COMPENSATION FOR ACQUISITION OF MINING LEASE - INTERPRETATION OF PROVISIONS - INTEREST ON EXCESS COMPENSATION - AWARD OF COSTS.
Fact of the Case:
The East India Coal Company Limited challenged the compensation awarded by the Tribunal for the acquisition of its mining lease under the Coal Bearing Areas (Acquisition and Development) Act, 1957. The company claimed additional compensation under various heads, interest on the excess compensation, and costs.
Finding of the Court:
The court held that the company was not entitled to additional compensation under Section 13(4) of the Act, as it had already been compensated for the period when mining operations were suspended due to the acquisition process under Section 13(2)(iii). However, the court allowed interest on the excess compensation awarded by the Tribunal from the date it became payable until the date of payment, as mandated by Section 16 of the Act.
Issues: 1. Whether the company was entitled to additional compensation under Section 13(4) of the Act. 2. Whether the Tribunal erred in not awarding interest on the excess compensation. 3. Whether the company was entitled to costs under Section 15 of the Act. 4. Whether the cross-objection filed by the Central Government was maintainable.
Ratio Decidendi: 1. Section 13(4) of the Act provides compensation for the period when a mining lease ceases to have effect due to the acquisition process. However, the company had already been compensated for this period under Section 13(2)(iii). Therefore, it was not entitled to additional compensation under Section 13(4). 2. Section 16 of the Act mandates the Tribunal to award interest on the excess compensation from the date it becomes payable until the date of payment. The Tribunal erred in not awarding interest, and the court directed the Central Government to pay the interest. 3. The Tribunal has the discretion to award costs under Section 15 of the Act. In this case, the Tribunal directed the parties to bear their own costs, and the court found no reason to interfere with this decision. 4. A cross-objection in an appeal filed under Section 20 of the Act is not maintainable. The Central Government should have filed its own appeal within the prescribed period if it wanted to challenge any portion of the award.
Final Decision: The court allowed the appeal in part, modified the Tribunal's award, and directed the Central Government to pay interest on the excess compensation. The court also awarded costs to the company.
Untwalia, J.
1. This is a miscellaneous first appeal filed by the claimant -- the East India Coal Company Limited -- under Sec.20 of the Coal Bearing Areas (Acquisition and Development) Act, 1957 (hereinafter called the Act). A certain mining lease in respect of land measuring 700 bighas and odd in Sutikdih was acquired under the Act and the proceeding was initiated by issuance of a preliminary notification under Sec. 4 of the Act. Eventually, a declaration of acquisition under Section 9 was issued on 18-12-61. On the issuance of such a declaration, the land and rights in the Sutikdih Colliery vested in the Central Government under Sec.10. The Central Government under Sec.10. The Central Government determined the amount of compensation to the tune of Rs. 36,449-83 payable to the claimant. The claimant did not agree to this amount and accepted the payment under protest. It filed its claim before the Tribunal appointed under the Act and as against its claim put forward before the Central Government to the tune of Rs. 19,35,902.03, it out forward a claim of Rs. 14,79,149/-before the Tribunal. The Tribunal has considered the matter in detail and allowed a total compensation of Rs. 3,37,929.52. It thus allowed an extra amount of Rs. 3.01,479.69 including interest under Sec.13 (2) (iv) of the Act. The claimant has filed this appeal to claim more amount of compensation under some head, interest under Sec.16 of the Act on the extra sum of compensation allowed or to be allowed and costs under Sec.15 in respect of the reference. The respondent, namely, the Central Government, on service of a notice of appeal filed a cross-objection objecting to the awarding of certain items of compensation to the appellant.
2. The learned Advocate-General appearing in support of the appeal urged five points--
(i) That compensation under Sec.13 (4) of the Act also ought to have been awarded and the Tribunal has not done it.
(ii) That it is compulsory for the Tribunal to award interest in accordance with Sec.16 pr in any event without exercise of judicial discretion and without mentioning any valid around interest under Sec.16 could not be disallowed.
(iii) That cost ought to have been allowed under Sec.15 of the Act.
(iv) That certain items of compensation claimed by the appellant have wrongly been disallowed by the Tribunal.
(v) That the cross-objection filed by the respondent is not maintainable and cannot be entertained.
3. The first point urged on behalf of the appellant is not sound and must be rejected. When a notification under Sec. 4 is issued then the effect of such notification on prospecting licences and mining leases is provided in Sec. 5. Clause (b) which reads as follows--
"On the issue of a notification under Sub-section (1) of Sec. 4 in respect of any land -- X X X
(b) any mining lease shall, in so far as it authorises the lessee or any person claiming through him to undertake any operation in the land, cease to have effect for so lone as the notification under that sub-section is in force."
If land in respect of which notification under Sec. 4 has been issued is not acquired within the maximum period of three years then under Section 7 (2) of the Act the notification issued under Sub-section (1) of Sec. 4 ceases to have effect on the expiration of three years from the date thereof. If, however, within the said period a declaration of acquisition is made under Section 9 then there is no question of the effect of notification ceasing or the effect under Section 5 (b) coming to an end. In that event the land vests in the Central Government and becomes its property. When land is acquired then under Sec.13 (2) (iii) the expenditure, if any, incurred by wav of dead rent or minimum royalty during any year or years when there was no production of coal is fully paid irrespective of the question whether the non-production of coal was because of the mining operations not going on or because of the effect brought about under Sec. 5 (b) of th
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.