SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

1993 Supreme(Pat) 327

PATNA HIGH COURT
S.B.Sinha and R.N.Prasad JJ.
Dumraon Textiles Limited
Versus
Bihar State Electricity Board
Civil Writ Jurisdiction Case No. 6499 of 1992 ;
Decided On : JULY 30, 1993

The court held that a consumer is not liable to pay bills raised on the basis of average consumption of electrical energy if the Board has failed to supply adequate electrical energy.

Headnote:

ELECTRICITY - BILLING - AVERAGE CONSUMPTION - INTERPRETATION OF TARIFF AND AGREEMENT - HARMONIOUS CONSTRUCTION - DUTY OF BOARD TO SUPPLY ELECTRICAL ENERGY - REMEDY OF CONSUMER IN CASE OF SUBSTANTIAL FAILURE TO SUPPLY.

Fact of the Case:

The petitioner, a consumer of High Tension electrical energy, challenged the bills raised by the Bihar State Electricity Board (Board) during the period March 1992 to June 1992. The Board had raised the bills on the basis of average consumption of electrical energy as the meter installed at the petitioner's premises was burnt. The petitioner contended that the average consumption was calculated on the basis of a period when there was inadequate supply of electrical energy, resulting in lower consumption.

Finding of the Court:

The court held that clause 16.8 of the tariff, which provided for billing on the basis of average consumption in case of a defective meter, had to be read along with clause 3(c) of the agreement between the parties, which provided that such average bills should be raised having due regard to the conditions of working during the month under dispute and during the previous three months. The court found that the Board had failed to supply adequate electrical energy during the period in question, and therefore, the petitioner was not liable to pay the bills raised on the basis of average consumption.

Issues: 1. Whether clause 16.8 of the tariff, which provided for billing on the basis of average consumption in case of a defective meter, was valid and enforceable. 2. Whether the Board was liable to pay compensation to the petitioner for the inadequate supply of electrical energy.

Ratio Decidendi: 1. The court held that clause 16.8 of the tariff had to be read along with clause 3(c) of the agreement between the parties, which provided that such average bills should be raised having due regard to the conditions of working during the month under dispute and during the previous three months. 2. The court found that the Board had failed to supply adequate electrical energy during the period in question, and therefore, the petitioner was not liable to pay the bills raised on the basis of average consumption.

Final Decision: The court disposed of the petition and directed the petitioner to file a representation before the General Manager-cum-Chief Engineer of the Board, who was to consider the petitioner's claim and pass an appropriate order in accordance with law.

Judgment

S.B.SINHA, J.

1. In this application, the petitioner which is a company incorporated under the Indian Companies Act, 1956 question the bills raised by the Bihar State Electricity Board (hereinafter referred to as the Board) during the period March, 199 2/06/1992.

2. The fact of the matter is not in dispute. The petitioner is a consumer of High Tension electrical energy having contract demand of 1275 K.V.A. of electrical energy in terms of an agreement dated 23-5-1979 as contained in Annexure 1 to the writ application. The Board installed a Trivector meter wherefor the petitioner has to pay rent. The transformer however was installed by the petitioner. According to the petitioner owing to highly unstable and erratic main supply voltage the current transfarmer and potential transformer (C.T.P.T.) of the Boards trivector meter was burnt on 9-5-1990. As the meter was burnt, the petitioner was billed on the basis of 4.03,528 units per month which was said to be the average unit consumed recorded during January, February and March, 1990. The meter however became functional on or from 1/07/1992. The grievance of the petitioner is that during the period March, 199 2/06/1992 there had been inadequate supply of electrical energy as a result whereof the petitioner could not have even consumed units of electrical energy calculated on the basis of three months average supply.

3. Mr. Navaniti Prasad Singh, learned counsel appearing on behalf of petitioner has raised short question in support of the application. Learned counsel submitted that the-bills on the basis of average supply can be raised only in terms of clause 3(c) of the agreement. But the bills have been raised on the basis of clause 16.8 of the new tariff which came into force with effect from 20th Sept. 1991. It has been submitted that average supply of electrical energy was only 45%. In this connection our attention was drawn to paragraphs 4, 5, 6 and 7 of the supplementary affidavit.

4. Learned counsel drew our attention to the amount of bill which used to be paid previously by the consumer and which has to be paid now. He, therefore, submitted that clause 16.8 of 1991 tariff must be held to be irrational as no provision therein has been made for grant of proportionate reduction in the matter of consumption of electrical energy. Learned counsel submitted that clause 3(c) of the agreement has to be read with clause 6(1) and if the same is compared with clause 16.8 of the new tariff, it must be held that the same is wholly irrational.

5. Mr. Singh has further submitted that whereas clause 13 of the High Tension Agreement provides for redressal of the consumers grievance of obtaining proportionate reduction in minimum guarantee charges in case of non-supply/ short supply of the electrical energy but no provision has been made in relation to consumption of the electrical energy. Learned counsel in this connection has relied upon a decision of the Supreme Court in M/s. Northern Indian Iron and Steel Co. V/s. The State of Haryana reported in AIR 1976 SC 1100.

6. Mr. Shiva Kirti Singh, learned counsel appearing on behalf of the Board on the other hand submitted that clause 16.8 of the tariff has been held to be intra vires by Division Bench of this Court in Bihar Chamber of Commerce V/s. Bihar State Electricity Board reported in (1993) 1 Pat LJR 36. He further submitted that the clause relating to raising of bill on average consumption of electrical energy must be held to be rational and even if there has been short supply of electrical energy the consumer cannot raise any grievance in relation thereto.

7. In this case evidently the meter was burnt on 9-5-1990 and the petitioner did not make any protest with regard to the bills raised on the basis of average consumption of electrical energy from January, February and March, 1990; till February, 1992. Admittedly it has also paid the bills for the month of March and April, 1992. It is true that normally consumer is supposed to






















Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top