PATNA HIGH COURT
Rekha Kumari, J.
State Of Bihar
Versus
Shakti Tubes Limited
First Appeal No. 8 of 2000 ;
Decided On : FEBRUARY 20, 2006
Limitation Act, 1963-Section 14-Suit filed beyond the period of limitation-Earlier writ also filed for the same relief which was permitted to be withdrawn with liberty to file property constituted suit-A direction given to exclude the period during which unit was pending for disposal if an application is filed by plaintiff u/s 14-Application filed u/s 14-Suit not barred by limitation. (Para 24)
Interest of Delayed payments to Small scale and Aucillary Industrial under taking Acts, 1993-Sections 3, 4, & 5-It is not the date of agreement or the date on which payment became due which is material in determining whether the provisions of the Act would be attracted-The crucial date is the date of supply order. (Para 39)
AIR 2006 SC 131-Relied upon.
Rekha Kumari, J.
1. This appeal is directed against the judgment and decree dated 31.5.1999 passed by Shri Nritya Nand Sinha, Subordinate Judge 1st, Patna in Money Suit No. 153 of 1997 by which he has decreed the suit with costs in favour of the plaintiff-respondent and has ordered the defendants-appellants to pay interest compounding at monthly rests at the rate of 24%: per annum on the decreetal amount of Rs. 38,13,480.00 of Money Suit No. 97 of 1996, with effect from 1.6.1993 till realisation.
2. The case of the respondent is that the plaintiff is a Company incorporated under the Indian Companies Act and is registered as a Small Scale Industry in the Industries Department Bihar. It manufactures Mild Steel Black Pipes. The defendant Chief Engineer, Minor Irrigation Department issued, notice inviting tenders for the supply of E.R.W. M.S. Black Pipes 100mm N.B. Light Class. The date of opening of the tenders was 21.3.1992. The plaintiff submitted its tender on 21.3.1992 for Supply of 11 lac metres of M.S. Black Pipes. Many other firms also submitted their tenders. All the tenders were opened and the tender of the plaintiff was accepted and after negotiation, the plaintiff offered to supply the pipes at the rate of Rs. 147.95P. per metre. The offer was accepted by the Chief Engineer vide his memo No. 3956 dated 16.7.1992 and by the same memo he also placed orders for the supply of pipes and directed to execute an agreement with the Executive Engineer, Investigation Division, Patna within 15 days of issue of the order. In the above letter it was clearly mentioned that 90% payment of the total value of the material supplied, would be made on receipt of the materials, and the balance would be paid after full verification of the same within one month of the receipt of the materials.
3. The Steel Authority of India Limited, in the meantime, increased price of H.R. coils on 19.5.1992. Accordingly, the plaintiff informed the defendants by letter dated 18.6.1992. about the increase and requested that it may be allowed to make supply on the escalated rates. After several reminders, the department informed through its letter. No. 4444 dated 4.8.1992 that the matter was under consideration and the escalated rates would be communicated after decision. According to the above direction of the Chief Engineer and the assurance given vide above letter dated 4.8.1992 the plaintiff on 8.8.1992 executed agreement with the Executive Engineer. The terms of payment was duly incorporated therein, It was stated in the agreement that event of variation in total cost of steel, the payment would be made at the escalated rate applicable for the quantity of pipes supplied after such escalation came into force. The other terms of the payment as enumerated in the above letter dated 16.7.1992 of the Chief Engineer remained un-changed.
4. The further case of the plaintiff-respondent is that as per the price escalation the defendants were to fix the rate at Rs. 199.04 per metre with effect from 16.07.1992 but the department erroneously granted price after calculating the actual amount of escalation at Rs. 190.48 P only per metre vide letter No. 6287 dated 4.11.1992. There was thus, an apparent calculation mistake in deciding the exact amount of escalation.
5. The plaintiff supplied the pipes as per agreement to the concerned consignees, who duly accepted the pipes as per measurement, but the payments were not made. The plaintiff sent reminders to the Chief Engineer for making payment. After some time, the payment was made at the rate of Rs. 190.48P, instead of actual escalated rate of Rs. 199.04P. A sum of Rs. 38,13,480.00 thus was curtailed illegally by the department.
6. The plaintiff through its letter dated 4.1.1993 wrote to the Secretary, Minor Irrigation Department (defendant No. 3) to pay the pending dues otherwise it would charge interest over the amount for the period of delay as per the provisions of the Interest on Delayed Payment to Small Sca
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.